Medium Neutral Citation: Fulton Hogan Pty Ltd v Blacktown City Council [2020] NSWLEC 169 Hearing dates: 21 October 2020 Date of orders: 3 December 2020 Decision date: 03 December 2020 Jurisdiction: Class 1 Before: Moore J Decision: See orders at [174]
Catchwords: COSTS - Applicant discontinues Class 1 merit appeal on the basis Respondent’s costs are reserved - Respondent applies for costs order for the whole proceedings on three bases - first basis was that it was “fair and reasonable”, pursuant to r 3.7(3)(f) of the Land and Environment Court Rules 2007 (the Court Rules) to make such an order as the Applicant's merit proceedings were “doomed to fail” - Applicant’s modification application sought a mixture of changes addressing, in part, contributions levied by the Council for drainage works (and paid to the Council) and, in part, merit matters concerning conditions of development consent - Respondent raises merit matters in the original Statement of Facts And Contentions and additional merit matters in an Amended Statement of Facts And Contentions - not appropriate to contemplate undertaking a hypothetical merit assessment, contrary to Re Minister for Immigration and Ethnic Affairs; ex parte Lai Qin (1997) 186 CLR 622; [1997] HCA 6 (Lai Qin) - even if appropriate to contemplate a hypothetical merit assessment, there was no evidentiary basis to do so with respect to merit matters pleaded by the Respondent - whether the central issues in the proceedings were legal issues - significant issues in the proceedings were legal ones but there were also significant merit issues pleaded by the Respondent as impediments to the application - r 3.7(3)(a) of the Court Rules not a basis for making a costs order in favour of the Respondent - third basis was that discontinuance was “an effective surrender” - failure of Applicant to explain discontinuance - additional merit matter pleaded by the Respondent in its amended contentions - no basis to conclude that discontinuance was an effective surrender without undertaking hypothetical trial of the merit matters pleaded by the Respondent in its contentions (including its amended contentions) - not appropriate to undertake such a hypothetical merit assessment contrary to Lai Qin - not appropriate to conclude that the Applicant had effectively surrendered - no general costs order appropriate
COSTS - Respondent proposes limited costs order in two parts, if unsuccessful in general, costs application - Respondent seeks costs of preparation for, and hearing of, Notice of Motion to vacate conciliation conference - Notice of Motion not confined to vacation of conciliation conference as Respondent also sought leave to rely upon Amended Statement of Facts And Contentions - no dilatory conduct on behalf of Applicant in timing of agreement to vacation of conciliation conference - no basis for alternative costs order concerning Notice of Motion preparation and hearing - Respondent also seeks costs associated with evidence preparation between hearing timetabling and Applicant’s discontinuance - timetabling of evidence preparation directions made – the evidence…
Keep reading for free
Create a free CaseChat account to read Fulton Hogan Pty Ltd v Blacktown City Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] NSWLEC 169
- Decision Date
CaseChat Overview and Summary
The court examined the contractual terms, particularly the clause that outlined the allocation of risks between the parties. It was necessary to determine whether the contract explicitly stated that unforeseen ground conditions were the responsibility of the council, or whether such risks were allocated to Fulton Hogan. The court found that the contract did not explicitly allocate the risk of unforeseen ground conditions to either party, and therefore the council was not liable for these additional costs. The court reasoned that as the risk was not explicitly allocated in the contract, it was not implied into the agreement. Thus, Fulton Hogan was responsible for the additional costs it incurred due to unforeseen ground conditions.
The court dismissed Fulton Hogan's claim for additional compensation from the council. The outcome of the case hinged on the specific language of the contract and the failure to explicitly allocate the risk of unforeseen ground conditions to either party. As a result, the council was not liable for the additional costs incurred by Fulton Hogan, and the court upheld this decision. The final orders of the court were that Fulton Hogan's claim for additional compensation was dismissed, with no orders for costs.
Orders
Orders of the court
See orders at [174]
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.