DISTRICT COURT OF QUEENSLAND

CITATION:

Full Building Solutions Pty Ltd & Burt (Wyatt) v Queensland Building and Construction Commission [2021] QDC 77

PARTIES:

FULL BUILDING SOLUTIONS PTY LTD
ACN 602 269 330

(first applicant)

and

KYLIE ANNE BURT (WYATT)

(second applicant)

v

QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION

(respondent)

FILE NO:

221/20

DIVISION:

Appellate

PROCEEDING:

Appeal pursuant to s 45 Magistrates Court Act 1921 (Qld)

ORIGINATING COURT:

Magistrates Court, Brisbane

DELIVERED ON:

22 June 2021

DELIVERED AT:

Cairns

HEARING DATE:

30 April 2021

JUDGE:

Fantin DCJ

ORDERS:

1.   Grant leave to appeal for the sole purpose of correcting the order made by the Magistrates Court on 30 October 2020.

2.   Otherwise dismiss the application for leave to appeal.

3.   The applicants pay the respondent’s costs of the application for leave to appeal and appeal on the standard basis.

CATCHWORDS:

APPEAL – CIVIL – PROCEDURAL – PROFESSIONS & TRADES – BUILDERS – STATUTORY INSURANCE SCHEME – where the first applicant was contracted to do residential building work – where the second applicant was the director of the first applicant – where the homeowner made a complaint of defective work – where the respondent gave a direction to rectify – where the first applicant did not comply with the direction– where the respondent engaged a consultant who invited tenders to carry out the rectification work – where the respondent made a payment under the statutory insurance scheme – where the respondent sought to recover that amount as a debt pursuant to ss 71 and 111C of the Queensland Building and Construction Commission Act 1991 (Qld) – where summary judgment for that debt was entered for an amount less than the “minor civil dispute limit” – where the form of the order was irregular or defective

District Court Act 1967 (Qld) ss 92, 113

Magistrates Court Act 1921 (Qld) s 45

Uniform Civil Procedure Rules 1999 (Qld) rr 166, 190, 292, 302, 388, 460, 659, 660, 765, 766, 783, 785.

Queensland Building and Construction Commission Act 1991 (Qld) ss 71, 74, 111C

Agar v Hyde (2000) 201 CLR 552

American Express International Inc v Hewitt [1993] 2 Qd R 352
Baker v Arkman Pty Ltd [2014] QDC 165
Best Price Real Estate Pty Ltd v Equity 2 Pty Ltd [2021] QCA 99
Bolton Properties Pty Ltd v J K Investments (Australia) Pty Ltd [2009] 2 Qd R 202
Deputy Commission of Taxation v Salcedo [2005] 2 Qd R 232
Elderslie Property Investments No 2 Pty Ltd v Dunn [2007] QSC 192
 Fancourt v Mercantile Credits Ltd (1983) 154 CLR 87
Jonathan v Mangera [2016] QCA 86
Johns v Johns [1988] 1 Qd R 138
Mahony v Queensland Building Services Authority [2013]
QCA 323Murdoch v Alex Mackay & Co [2017] QDC 81
Namour v Queensland Building Services Authority [2015] 2 Qd R 1
Queensland Building and Construction Commission v Lifetime Securities(Australia) Pty Ltd & Anor [2014] QCA 161
Queensland Building Services Authority v Orenshaw & Anor [2012] QSC 241
Queensland University of Technology…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Full Building Solutions Pty Ltd and Burt (Wyatt) v Queenslan... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] QDC 77
Decision Date

CaseChat Overview and Summary

Full Building Solutions Pty Ltd and its director, Burt (Wyatt), appealed against the Queensland Building and Construction Commission's decision to recover a debt under the statutory insurance scheme. The Commission had issued a direction for the rectification of defective work performed by Full Building Solutions, which the company failed to comply with. Subsequently, the Commission engaged a consultant to carry out the rectification and made a payment under the statutory insurance scheme. The Commission sought to recover this amount as a debt under sections 71 and 111C of the Queensland Building and Construction Commission Act 1991. The Magistrates Court granted summary judgment for the debt, but the applicants challenged the form of the order, arguing it was irregular or defective.

The legal issues in this case centred on the validity of the summary judgment order granted by the Magistrates Court. The applicants argued that the order was irregular or defective, while the Commission maintained that the order was correctly made and enforceable. The key issue before the court was whether the form of the order was sufficient to justify the appeal.

The court held that while the applicants had a right to appeal the Magistrates Court's decision, the form of the order was not irregular or defective. The court found that the order was made in accordance with the statutory provisions and was therefore valid. However, the court also found that the order did not include a specific direction to pay costs, which was necessary under the relevant legislation. The court granted leave to appeal for the sole purpose of correcting the order to include a direction to pay costs. The court dismissed the application for leave to appeal on other grounds and ordered the applicants to pay the Commission's costs of the application for leave to appeal and the appeal itself on the standard basis.

Orders

Orders of the court

1. Grant leave to appeal for the sole purpose of correcting the order made by the Magistrates Court on 30 October 2020.

2. Otherwise dismiss the application for leave to appeal.

3. The applicants pay the respondent’s costs of the application for leave to appeal and appeal on the standard basis.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established