| CITATION: | Fowler v The Society for the Mount Isa Garden Settlement [2016] QCAT 64 |
| PARTIES: | Keith Fowler t/as Beach Haven Landscapes (Applicant) |
| v | |
| The Society for the Mount Isa Garden Settlement t/as The Laura Johnson Home (Respondent) |
| APPLICATION NUMBER: | BDL056 - 15 |
| MATTER TYPE: | Building matter |
| HEARING DATE: | 24 March 2016 |
| HEARD AT: | Brisbane |
| DECISION OF: | Member Traves |
| DELIVERED ON: | 3 May 2016 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. The respondent pay the applicant $31 017.60 by 31 May 2016. 2. The respondent pay the applicant’s costs fixed at $710.00 by 31 May 2016. |
| CATCHWORDS: | BUILDING MATTER – claim for work done by contractor - claim for damages by contractor where site not ready – amount of damages. Queensland Building and Construction Commission Act 1991 (Qld), s 75(1), s 77(1), s 77(3)(h), Schedule 2. Commonwealth v Amann Aviation Pty Ltd (1991) 174 CLR 64 at 80 |
REASONS FOR DECISION
Introduction
This is a claim by Keith Fowler trading as BeachHaven Landscapes (BL) for $41 310.37 for damages comprising wages, costs and interest.
BL agreed with The Society for the Mount Isa Memorial Garden Settlement trading as The Laura Johnson Home (LJH), the respondent, to do landscaping works at premises owned by LJH.
BL claims the site was not ready for BL to perform the work at the agreed time. Consequently, BL says, its commencement and completion of the work was delayed, causing it loss.
BL was paid the agreed contract price of $170 203.00 by LJH.
The claim concerns the period between 18 August 2014 and 28 September 2014 which represents the time BL was not doing its work (as defined in the contract) or rectification work which it was subsequently engaged to do.
BL argued that it was entitled to $41 310.37 on a number of alternative bases: that “delay damages” are recoverable under the contract, that LJH agreed after entry into the contract to pay its delay costs, and, that LJH are in breach of contract and the claim represents the damages caused to BL by the breach.
Background
BL entered into a contract with LJH on 29 April 2014 to complete landscaping works to an aged care facility in Mt Isa. The premises were and are owned by LJH.
The form of contract entered into was a Standard HIA Small Works contract. This contract was designed to apply to domestic building works and does not arguably apply to the work to be done by BL for LJH at the aged care facility. However, although the terms are not ideally suited for the work carried out, both parties agreed to them.
The commencement date was 25 May 2014 (clause 4).…
Keep reading for free
Create a free CaseChat account to read Fowler v The Society for the Mount Isa Garden Settlement and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] QCAT 64
- Decision Date
CaseChat Overview and Summary
The primary legal issue the court had to address was whether the applicant was entitled to compensation for the work completed on a site that did not meet the contractual standards. This involved examining the terms of the contract, the condition of the site at the time of the contractor's arrival, and the extent to which the site's unsuitability affected the contractor's ability to perform the work. The court needed to determine if the applicant had a valid claim for the additional costs incurred due to the site's unpreparedness and if the damages claimed were reasonable and justified under the circumstances.
The court found that the respondent's site was indeed not ready for construction as required by the contract, which led to the applicant incurring additional costs. The court accepted that the applicant had fulfilled his contractual obligations but was hindered by the site's condition. The court held that the applicant was entitled to compensation for the extra costs incurred due to the site's unsuitability. After assessing the evidence presented, the court ordered the respondent to pay the applicant $31,017.60 for the additional work and expenses, along with costs of $710.00. This decision was based on the clear breach of contract by the respondent and the necessity for the applicant to incur additional costs due to the site's unsuitability.
Orders
Orders of the court
1. The respondent pay the applicant $31 017.60 by 31 May 2016.
2. The respondent pay the applicant’s costs fixed at $710.00 by 31 May 2016.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.