District Court
New South Wales
- Amendment notes
Medium Neutral Citation: Forte Sydney Construction Pty Ltd v N Moit & Sons (NSW) Pty Ltd [2021] NSWDC 673 Hearing dates: 1- 4, 26 November 2021 Date of orders: 14 December 2021 Decision date: 14 December 2021 Jurisdiction: Civil Before: Russell SC DCJ Decision: (1) Judgment for the defendant on the plaintiff’s claim.
(2) Judgment for the defendant on the cross-claim for $418,485.04.
(3) Order the plaintiff to pay the defendant’s costs of the proceedings.
(4) Grant leave to approach my Associate within 7 days to obtain a date for submissions as to any application for a different costs order arising from any settlement offers made.
Catchwords: CONTRACT – offer and acceptance – objective test as to whether there was a concluded bargain – implied acceptance and inferences from surrounding circumstances - offeror cannot stipulate that no response to an offer will be treated as an acceptance – three categories in Masters v Cameron
CONTRACT – tender to perform work for a price and upon conditions – tender accepted but subcontract put forward which contained different conditions – subcontract never signed – variations and deductions – extensions of time
Cases Cited: Brambles Holdings Limited v Bathurst City Council [2001] NSWCA 61, 53 NSWLR 153
Branir Pty Ltd v Owston Nominees (No 2) Pty Ltd [2001] FCA 1833; (2001) 117 FCR 424
Empirnall Holdings v Machon Paull Partners (1988) 14 NSWLR 523
Felthouse v Bindley (1862) 142 ER 1037
Texts Cited: Radan & Gooley, Principles of Australian Contractor, 4th Edition, LexisNexis
Category: Principal judgment Parties: Forte Sydney Construction Pty Ltd (Plaintiff)
N Moit & Sons (NSW) Pty Ltd (Defendant)Representation: Counsel:
Solicitors:
J Cameron (solicitor) (Plaintiff)
D Hand (Defendant)
J Cameron Lawyers Pty Ltd
Coleman Greig Lawyers
File Number(s): 2019/00145109
Judgment
Introduction
-
The plaintiff Forte Sydney Construction Pty Ltd (“Forte”) was the builder engaged by a developer on a site at Porter Street in Ryde. The defendant N Moit & Sons (NSW) Pty Ltd (“Moit”) was a subcontractor engaged by Forte to carry out excavation, piling works and shotcreting at Porter Street.
-
These proceedings concern whether or not there was a contract between the parties, and if there was, what were the terms of the contract?
-
The parties agree that Forte and Moit entered into an arrangement for Moit to supply, install and undertake excavation, anchoring, shotcrete and related civil works for a price of $1,536,739 plus GST, a total of $1,690,412.90.
-
In an Amended Statement of Claim filed during the course of the hearing, Forte alleged that the parties did enter into a contract on 25 May 2018 or 28 May 2018 or 7 June 2018.
-
Forte pleaded (Amended Statement of Claim, par 3) as follows:
“In so far as the contract was in writing, it consisted of:
a. a letter of engagement dated 16 May 2018
b. a contract which is headed…
Keep reading for free
Create a free CaseChat account to read Forte Sydney Construction Pty Ltd v N Moit and Sons (NSW) Pt... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] NSWDC 673
- Decision Date
CaseChat Overview and Summary
The central legal issues were whether there was an objective indication of acceptance of an offer by the plaintiff, and if the defendant's conduct implied acceptance despite the absence of a formal agreement. The court also considered whether the defendant's conduct constituted acceptance of the plaintiff's tender and whether the subcontract proposed by the defendant formed part of the contract between the parties. Furthermore, the court examined the effect of variations and deductions made by the defendant in relation to the contract and the plaintiff's entitlement to an extension of time.
The court held that there was no concluded bargain between the parties. The plaintiff's offer was not accepted by the defendant as the defendant's conduct did not objectively indicate acceptance of the plaintiff's tender. The subcontract proposed by the defendant was not accepted by the plaintiff and therefore did not form part of the contract. The court also found that the defendant was not liable for variations and deductions made in relation to the contract and that the plaintiff was not entitled to an extension of time. Consequently, the court dismissed the plaintiff's claim and the cross-claim made by the defendant. The court ordered the plaintiff to pay the defendant's costs of the proceedings and granted leave for the plaintiff to approach the Associate for a date for submissions regarding any application for a different costs order arising from any settlement offers made.
The final orders were that judgment be entered in favour of the defendant on the plaintiff's claim and the cross-claim, that the plaintiff pay the defendant's costs, and that leave be granted for the plaintiff to apply for a different costs order if any settlement offers were made.
Orders
Orders of the court
(1) Judgment for the defendant on the plaintiff’s claim.
(2) Judgment for the defendant on the cross-claim for $418,485.04.
(3) Order the plaintiff to pay the defendant’s costs of the proceedings.
(4) Grant leave to approach my Associate within 7 days to obtain a date for submissions as to any application for a different costs order arising from any settlement offers made.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi