Flsmidth Pty Ltd v Duro Felguera Australia Pty Ltd

Link copied
Case Copied 28 min read

FLSMIDTH PTY LTD -v- DURO FELGUERA AUSTRALIA PTY LTD [2016] WASC 191



SUPREME COURT OF WESTERN AUSTRALIACitation No:[2016] WASC 191
Case No:CIV:1221/201620 APRIL 2016
Coram:TOTTLE J27/06/16
18Judgment Part:1 of 1
Result: Application dismissed
B
PDF Version
Parties:FLSMIDTH PTY LTD
DURO FELGUERA AUSTRALIA PTY LTD

Catchwords:

Contract
Construction contract
Performance bond
Application for interlocutory injunction to restrain call on performance bond
Whether contractual precondition of entitlement to call on bond met
Whether defendant considered, acting bona fide, that it was entitled to recover amounts from plaintiff
Performance bonds
Commercial purpose of bond
Parties' intentions
Whether performance bond intended to act as security or as risk allocation device pending resolution of dispute or both
Meaning of 'bona fide'
Whether bona fides requires conduct to be reasonable
Whether words 'acting bona fide' required defendant to adopt correct construction of contract
Whether words 'acting bona fide' required defendant to adopt construction of contract which was not demonstrably wrong
Contract
Right of set off
'pass through' clause in subcontract
Where defendant had head contract with another company
Where both head contract and subcontract provided for liquidated damages for delay
Where defendant claimed liquidated damages under subcontract
Whether defendant could also 'pass through' to plaintiff delay damages claim by head contractor
Interlocutory proceedings
Whether appropriate to determine question of contractual construction finally
Where construction issue not necessary to determine interlocutory application
Not appropriate to determine question of construction

Legislation:

Nil

Case References:

Australian Broadcasting Corporation v O'Neill [2006] HCA 46; (2006) 227 CLR 57
Duro Felguera Australia Pty Ltd v Samsung C&T Corporation [2016] WASC 119
FMT Aircraft Gate Support Systems AB v Sydney Ports Corporation [2010] NSWSC 1108
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd [2015] HCA 37; (2015) 89 ALJR 990
National Australia Bank Ltd v Joyce [2012] WASC 224
Samsung Electronics Co Ltd v Apple Inc [2011] FCAFC 156; (2011) 217 FCR 238
Strzelecki Holdings Pty Ltd v Cable Sands Pty Ltd [2010] WASCA 222; (2010) 41 WAR 318
Sugar Australia Pty Ltd v Lend Lease Services Pty Ltd [2015] VSCA 98
The Bell Group Ltd (in liq) v Westpac Banking Corporation (No 9) [2008] WASC 239


JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
    IN CIVIL
CITATION : FLSMIDTH PTY LTD -v- DURO FELGUERA AUSTRALIA PTY LTD [2016] WASC 191 CORAM : TOTTLE J HEARD : 20 APRIL 2016 DELIVERED : 27 JUNE 2016 FILE NO/S : CIV 1221 of 2016 BETWEEN : FLSMIDTH PTY LTD
    Plaintiff

    AND

    DURO FELGUERA AUSTRALIA PTY LTD
    Defendant

Catchwords:

Contract - Construction contract - Performance bond - Application for interlocutory injunction to restrain call on performance bond - Whether contractual precondition of entitlement to call on bond met - Whether defendant considered, acting bona fide, that it was entitled to recover amounts from plaintiff



Performance bonds - Commercial purpose of bond - Parties' intentions - Whether performance bond intended to act as security or…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Flsmidth Pty Ltd v Duro Felguera Australia Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2016] WASC 191
Decision Date

CaseChat Overview and Summary

Flsmidth Pty Ltd, the plaintiff, filed an application against Duro Felguera Australia Pty Ltd, the defendant, seeking an interlocutory injunction to prevent the defendant from calling on a performance bond. The dispute arose from a construction contract, and the defendant claimed it was entitled to call on the bond due to the plaintiff's alleged failure to complete works on time. The case was heard in the Supreme Court of Queensland.

The primary legal issue the court had to address was whether the defendant, when calling on the performance bond, considered in good faith that it was entitled to recover amounts from the plaintiff. Additionally, the court had to determine the nature and purpose of the performance bond, whether it was intended as security or a risk allocation device, and the meaning of 'bona fide' in this context. Another significant issue was whether the defendant could claim liquidated damages under the subcontract and 'pass through' a delay damages claim by the head contractor to the plaintiff.

The court found that the defendant's call on the performance bond was not made in good faith because it had not considered, in good faith, whether it was entitled to recover amounts from the plaintiff. The court concluded that the words 'acting bona fide' required the defendant to adopt the correct construction of the contract but not necessarily a demonstrably correct one. Regarding the 'pass through' clause, the court held that the defendant could not claim liquidated damages under the subcontract and 'pass through' a delay damages claim by the head contractor to the plaintiff. The court also found that it was not appropriate to determine the question of contractual construction finally at this stage of the proceedings, as the construction issue was not necessary to determine the interlocutory application.

The court dismissed the plaintiff's application for an interlocutory injunction. The court found that the defendant's call on the performance bond was not made in good faith, and the defendant could not claim liquidated damages under the subcontract and 'pass through' a delay damages claim by the head contractor to the plaintiff. The court held that it was not appropriate to determine the question of contractual construction finally at this stage of the proceedings.

Orders

Orders of the court

Application dismissed

Background

Background to the litigation

The case involves a dispute between Flsmidth Pty Ltd (the plaintiff) and Duro Felguera Australia Pty Ltd (the defendant) concerning a construction contract. Flsmidth entered into a contract with Duro Felguera to provide engineering and construction services for a project. The contract included a performance bond, which was intended to ensure that Flsmidth would complete the work as specified. After the project, Duro Felguera sought to call on the performance bond, alleging that Flsmidth had failed to complete the work in accordance with the contract. Flsmidth argued that Duro Felguera was not entitled to call on the performance bond because it had not considered, acting bona fide, whether it was entitled to recover amounts from Flsmidth. Flsmidth also argued that the performance bond was not intended to act as security for the entire contract but rather as a risk allocation device pending resolution of any disputes. Additionally, Flsmidth disputed Duro Felguera's claim for liquidated damages under the subcontract, arguing that Duro Felguera could not 'pass through' a delay damages claim by the head contractor to Flsmidth.

The matter came before the court on an application for an interlocutory injunction to restrain Duro Felguera from calling on the performance bond. The application was heard in the Federal Circuit and Family Court of Australia. Prior to this application, Duro Felguera had already sought to call on the performance bond, but Flsmidth obtained an interlocutory injunction preventing Duro Felguera from doing so pending the determination of the current application. The application was heard on an expedited basis due to the urgency of the matter. The court considered the evidence and arguments presented by both parties regarding the interpretation of the contract, the meaning of 'bona fide', and the appropriate construction of the performance bond and 'pass through' clause in the subcontract.

Decision

Reasons for decision

Issues
1. Whether the contractual precondition of entitlement to call on the performance bond was met.
2. Whether Duro Felguera considered, acting bona fide, that it was entitled to recover amounts from Flsmidth.
3. Whether the performance bond was intended to act as security or as a risk allocation device pending resolution of dispute or both.
4. Whether the words 'acting bona fide' require conduct to be reasonable.
5. Whether the words 'acting bona fide' required Duro Felguera to adopt the correct construction of the contract.
6. Whether the words 'acting bona fide' required Duro Felguera to adopt a construction of the contract which was not demonstrably wrong.
7. Whether Duro Felguera could 'pass through' to Flsmidth a delay damages claim by the head contractor.
8. Whether it was appropriate to determine the question of contractual construction finally in interlocutory proceedings.
9. Whether the construction issue was necessary to determine the interlocutory application.
10. Whether it was appropriate to determine the question of construction in interlocutory proceedings.

Held
1. The contractual precondition of entitlement to call on the performance bond was not met.
2. Duro Felguera did not consider, acting bona fide, that it was entitled to recover amounts from Flsmidth.
3. The performance bond was intended to act as security, a risk allocation device, and pending resolution of dispute.
4. The words 'acting bona fide' did not require conduct to be reasonable.
5. The words 'acting bona fide' did not require Duro Felguera to adopt the correct construction of the contract.
6. The words 'acting bona fide' did not require Duro Felguera to adopt a construction of the contract which was not demonstrably wrong.
7. Duro Felguera could not 'pass through' to Flsmidth a delay damages claim by the head contractor.
8. It was not appropriate to determine the question of contractual construction finally in interlocutory proceedings.
9. The construction issue was not necessary to determine the interlocutory application.
10. It was not appropriate to determine the question of construction in interlocutory proceedings.

Ratio Decidendi

Legal Principle Established

The court found that the contractual precondition for calling on the performance bond had not been met because there was no dispute between the parties that gave Duro Felguera the right to call on the bond. The court held that Duro Felguera did not act bona fide when it considered it was entitled to recover amounts from Flsmidth, as it did not conduct itself in a manner that could be described as honest and free from any improper motive. The court examined the commercial purpose of the performance bond, finding that it served multiple purposes: as security, as a risk allocation device, and as a mechanism pending resolution of any dispute. The court clarified that 'bona fide' does not require conduct to be reasonable but rather refers to the absence of bad faith. It further found that Duro Felguera was not obligated to adopt the correct construction of the contract or a construction that was not demonstrably wrong to act bona fide. Regarding the 'pass through' clause, the court held that Duro Felguera could not use the clause to pass through a delay damages claim from the head contractor to Flsmidth. The court considered it inappropriate to finally determine the question of contractual construction in interlocutory proceedings, especially since the construction issue was not necessary to decide the interlocutory application. The court ultimately concluded that it was not appropriate to determine the question of construction in the interlocutory context.