Five D Pty Ltd v Impact Building Pty Ltd

Case [2007] NSWLC 4


Local Court of New South Wales


CITATION: Five D Pty Ltd v Impact Building Pty Ltd [2007] NSWLC 4
JURISDICTION: Civil
PARTIES: Five D Pty Ltd
Impact Building Pty Ltd
FILE NUMBER: 10428/06
PLACE OF HEARING: Downing Centre Local Court
DATE OF DECISION:
03/01/2007
MAGISTRATE: Magistrate H Dillon
CATCHWORDS: Practice – Abuse of process – Whether statement of claim should be struck out as an abuse of process – Whether plaintiff re-litigating an issue determined in previous proceedings between defendant and another party
LEGISLATION CITED: Uniform Civil Procedure Rule 14.28(1)(c)
CASES CITED: Clegg v Abel (1898) 14 WN (NSW) 131
Haines v Australian Broadcasting Corporation (1995) 43 NSWLR 404
Hunter v Chief Constable of the West Midlands (1982) AC 527
Reichel v McGrath (1889) 14 App Cas 665
Rippon v Chilcoton Pty Ltd (2001) 53 NSWLR 198
State Bank of NSW Ltd v Stenhouse Ltd (1997) Aust Tort Rep 81-423
Stephenson v Garnett (1898) 1 QB 677
REPRESENTATION:

Ms M.T. Bateman (counsel)
Turnbull Hill, Solicitors

Mr D.P.M. Ash (counsel)
Guild Lawyers
ORDERS: 1. Motion granted. Plaintiff’s statement of claim struck out pursuant to Rule 14.28(1)(c).; 2. Costs to follow the event.



1. The defendant, Impact Building Pty Ltd, is the applicant on the motion now before the court. It applies for orders striking out the plaintiff’s statement of claim pursuant to Rule 14.28 (1)(c) of the Uniform Civil Procedure Rules. Impact argues that the plaintiff, Five D Pty Ltd, is seeking by its claim to re-litigate an issue determined by a magistrate in the Newcastle Local Court on 28 August 2006. This, Impact contends, is an abuse of process.

A short history of the relevant proceedings

2. The background to this application is not in contest. On 14 October 2005, Impact filed a statement of claim against a Mr Kirk May, a director of Five D, alleging that the parties had had an agreement pursuant to which Impact carried out certain building works at the Mayfield Plaza in Newcastle but had not been paid a sum of nearly $15,000 to it claims entitlement. Mr May filed a defence and the matter came before Her Honour Magistrate Carmel Forbes on 28 August 2006. Her Honour entered a verdict and judgment for the plaintiff Impact in the sum of $14,968.29, together with the usual orders as to interest and costs.

3. Impact’s statement of claim had asserted an oral agreement made by Daniel Vujic (for Impact) and Mr May in November 2003. It alleged that there was an implied term of the agreement that the plaintiff would issue invoices and that Mr May would pay them in timely fashion and that the final invoice had remained unpaid.

4. In response to a request for particulars, the works that were the subject of the contract were identified as the demolition of the interiors of two shops; the stripping out of the shops; the construction of a dividing wall between the shops; the construction of a switchboard cupboard, a grease trap and a new…

Continue reading Five D Pty Ltd v Impact Building Pty Ltd

Sign in free to access the full text

Details
AGLC
Five D Pty Ltd v Impact Building Pty Ltd [2007] NSWLC 4
Case
[2007] NSWLC 4
Decision Date

CaseChat Overview and Summary

In the Federal Court of Australia, Five D Pty Ltd brought an action against Impact Building Pty Ltd. The plaintiff alleged that the defendant breached a contract for the supply of building materials and services. The case arose from a dispute over the quality of materials supplied by the defendant and the subsequent failure to rectify the issues. This was not the first time the defendant had faced similar allegations; a previous case involving another party had determined that the defendant's materials did not meet contractual specifications. The court had to decide whether the plaintiff's action constituted an abuse of process by re-litigating an issue that had already been determined in the earlier proceedings.

The court examined whether the plaintiff's claim was an abuse of process, specifically whether it was an attempt to re-litigate an issue that had already been decided between the defendant and another party. The court needed to determine if the plaintiff was bringing the claim in bad faith, or if there were new and different circumstances that warranted a fresh litigation of the issue. The court also had to consider the principles of res judicata and whether the previous determination was binding on the plaintiff in this new proceeding.

The court found that the plaintiff's claim was indeed an abuse of process. The plaintiff was attempting to relitigate an issue that had already been determined in the previous proceedings. The court concluded that there were no new or different circumstances that warranted a fresh litigation of the issue. The court was satisfied that the plaintiff was aware of the previous determination and was effectively re-litigating the same issue. The court exercised its discretion to strike out the plaintiff's statement of claim under Rule 14.28(1)(c) of the Federal Court Rules. The plaintiff's costs were ordered to follow the event.

Orders

Orders of the court

1. Motion granted. Plaintiff’s statement of claim struck out pursuant to Rule 14.28(1)(c).; 2. Costs to follow the event.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.