Civil and Administrative Tribunal
New South Wales
Medium Neutral Citation: Fitzgerald v Waterstop Solutions (NSW) Pty Ltd [2022] NSWCATCD 84 Hearing dates: 20 April 2022 Date of orders: 20 June 2022 Decision date: 20 June 2022 Jurisdiction: Consumer and Commercial Division Before: P French, Senior Member Decision: (1) Pursuant to s 55(1)(b) of the Civil and Administrative Tribunal Act 2013 the application is dismissed on the basis that it is misconceived.
(2) Any application for costs is to be made with supporting submissions by 4 July 2022. Submissions are to be limited to 5 A4 pages in not less than 11 point font.
(3) Any reply to any application for costs is to be made with supporting submissions by 28 July 2022. Submissions are to be limited to 5 A4 pages in not less than 11 point font.
(4) Subject to order (5), pursuant to s 50(1)(c) of the Civil and Administrative Tribunal Act 2013 the Tribunal dispenses with any further hearing on the issue of costs.
(5) If a party contends for any different order to order (4) they are to set out the order sought and the grounds for that order in any application for costs or reply to any application for costs.
Catchwords: BUILDING AND CONSTRUCTION – Home Building Act 1989 (NSW) – Statutory warranty – Due care and skill – Standing of Lot Owners to bring an application under the Home Building Act 1989 against a builder engaged by the Owners Corporation in relation to the repair of common property in a Strata Scheme
Legislation Cited: Civil and Administrative Tribunal Act 2013 (NSW)
Home Building Act 1989 (NSW)
Strata Schemes (Freehold Development) Act 2015 (NSW)
Strata Schemes Management Act 2015 (NSW)
Strata Schemes Management Regulation 2015 (NSW)
Cases Cited: Alchin v Rail Corporation NSW [2012] NSWADT 142
BDK v Department of Education and Communities [2015] NSWCATAP 129
EK Constructions Pty Ltd v Zhu [2017] NSWCATAP 102
Grygiel v Baine & Ors [2005] NSWCA 218
Seiwa v Owners Strata Plan 35042 [2006] NSWSC 1157
Texts Cited: Nil
Category: Principal judgment Parties: Robert Fitzgerald (First Applicant)
Emma Fitzgerald (Second Applicant)
Waterstop Solutions (NSW) Pty Ltd (Respondent)Representation: Counsel:
Solicitors:
B Anderson (Respondent)
Bull, Son and Schmidt (First and Second Applicant)
ITC Law (Respondent)
File Number(s): HB 21/45759 Publication restriction: Nil
REASONS FOR DECISION
Introduction
-
This is an application by Robert and Emma Fitzgerald (the applicants) for an order pursuant to s 480(1)(a) of the Home Building Act 1989 (NSW) (HB Act) that would require Waterstop Solutions (NSW) Pty Ltd (the respondent) to pay them $70,721.40 in compensation for the costs they contend they will incur in rectifying defective building work the respondent has carried out on the balcony of their apartment. This application was made to the Tribunal on 7 November 2021 (the application).
-
The Tribunal has dismissed the application because it is misconceived. The applicants are lot owners in a strata scheme. The building works about which they complain were carried out on common property on their…
Keep reading for free
Create a free CaseChat account to read Fitzgerald v Waterstop Solutions (NSW) Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] NSWCATCD 84
- Decision Date
CaseChat Overview and Summary
The primary legal issue for the Tribunal to decide was whether the individual lot owners had standing to bring an application under the Home Building Act 1989 against the builder, who was engaged by the Owners Corporation to carry out repairs on common property. The Tribunal had to consider the responsibilities of the Owners Corporation in maintaining and repairing the common property, and whether the individual lot owners could recover damages for any loss suffered due to a contravention of the statutory duty by the Owners Corporation.
In dismissing the application, the Tribunal found that the individual lot owners did not have standing to bring the application against the builder, as the statutory warranties under the Home Building Act 1989 were intended to protect lot owners from defects in the construction of their individual lots, rather than from defects in the maintenance and repair of common property. The Tribunal held that the Owners Corporation, as the entity responsible for maintaining and repairing the common property, was the proper party to bring an action against the builder for any breaches of statutory warranties in relation to the repair of common property.
In addition to dismissing the application, the Tribunal made orders regarding the costs associated with the proceedings. The Tribunal dismissed the application on the basis that it was misconceived and dispensed with any further hearing on the issue of costs, except where a party sought a different order and provided supporting submissions. The Tribunal also set deadlines for any applications for costs and replies to such applications, limiting the length of the submissions.
Orders
Orders of the court
(1) Pursuant to s 55(1)(b) of the Civil and Administrative Tribunal Act 2013 the application is dismissed on the basis that it is misconceived.
(2) Any application for costs is to be made with supporting submissions by 4 July 2022. Submissions are to be limited to 5 A4 pages in not less than 11 point font.
(3) Any reply to any application for costs is to be made with supporting submissions by 28 July 2022. Submissions are to be limited to 5 A4 pages in not less than 11 point font.
(4) Subject to order (5), pursuant to s 50(1)(c) of the Civil and Administrative Tribunal Act 2013 the Tribunal dispenses with any further hearing on the issue of costs.
(5) If a party contends for any different order to order (4) they are to set out the order sought and the grounds for that order in any application for costs or reply to any application for costs.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Duty of owners corporation to maintain and repair property An owners corporation for a strata scheme must properly maintain and keep in a state of good and serviceable repair the common property and any personal property vested in the owners corporation. An owner of a lot in a strata scheme may recover from the owners corporation, as damages for breach of statutory duty, any reasonably foreseeable loss suffered by the owner as a result of a contravention of this section by the owners corporation. This section is subject to the provisions of any common property memorandum adopted by the by-laws for the strata scheme under this Division, any common property rights by-law or any by-law made under section 108. Common property memorandum The by-laws for a strata scheme may adopt a common property memorandum prescribed by the regulations for the purposes of this section. The common property memorandum is to specify whether an owner of a lot or the owners corporation is responsible for the maintenance, repair or replacement of any part of the common property. The following warranties by the holder of a contractor license, or person required to hold a contractor license before entering into a contract, are implied in every contract to do residential building work - Definition of residential building work In this Act, A person who is a successor in title to a person entitled to the benefit of a statutory warranty under this Act is entitled to the same rights as the person’s predecessor in title in respect of the statutory warranty.