Fitzgerald v Ryan McLaren t/as Dialled Earthworks & Construction

Link copied
Case Copied 27 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Fitzgerald v Ryan McLaren t/as Dialled Earthworks & Construction [2025] QCAT 307

PARTIES:

CIARAN FITZGERALD

(applicant)

v

RYAN MCLAREN T/AS DIALLED EARTHWORKS & CONSTRUCTION

(respondent)

APPLICATION NO/S:

BDL425-23

MATTER TYPE:

Building matters

DELIVERED ON:

18 August 2025

HEARING DATE:

16 June 2025

HEARD AT:

Brisbane

DECISION OF:

Senior Member Brown

Member Benjamin

ORDERS:

1.     Ryan McLaren t/as Dialled Earthworks & Construction must pay to Ciaran Fitzgerald $29,997 within 28 days of the date of this decision.

2.     Ryan McLaren t/as Dialled Earthworks & Construction must pay to Ciaran Fitzgerald costs fixed in the amount of $379.50 within 28 days of the date of this decision.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – IMPLIED TERMS – where applicant homeowner entered into regulated domestic building contract with respondent builder – where a contractual relationship was formed between the parties by email communications – where a term about reasonable payment implied – where builder required to carry out works with  reasonable care and skill in accordance with implied warranties contained in Queensland Building and Construction Commission Act 1991 (Qld) schedule 1B – where respondent did not carry out works with due care and skill – where respondent breached contract

DAMAGES – ASSESSMENT OF DAMAGES IN ACTIONS FOR BREACH OF CONTRACT – where author of quote for rectification works not called to give evidence at hearing – where no conflicting quotes or evidence of damages in evidence – where respondent’s bases for challenging the quote unsubstantiated by evidence – where quote accepted as evidence of cost of rectification work

Building Act 1975 (Qld), s 21, s 22
Electronic Transactions (Queensland) Act 2014 (Qld), s 14

Queensland Building and Construction Commission Act1991 (Qld), s 19, s 21, s 22, schedule 1B s 4, schedule 2

Bellgrove v Eldridge (1954) 90 CLR 613
Geebung Investments Pty Ltd v Varga Group Investments (No 8) Pty Ltd (1995) 7 BPR 14,551
Munro v Camdun Pty Ltd [2024] QCAT 452
Olindaridge Pty Ltd & Anor v Tracey & Anor [2014] QCATA 207
Renbar Constructions Pty Ltd v Sader [2022] NSWSC 172
Robinson v Harman (1848) 1 Ex Rep 850
Stellard Pty Ltd & Anor v North Queensland Fuel Pty Ltd [2015] QSC 119

Toyota Motor Corp Australia Ltd v Ken Morgan Motors Pty Ltd [1994] 2 VR 106

APPEARANCES & REPRESENTATION:

Applicant:

Self-represented

Respondent:

Self-represented

REASONS FOR DECISION

What is this proceeding about?

  1. This proceeding is about a building dispute.

  2. Mr McLaren undertook concreting work for Mr and Mrs Fitzgerald at their home. Mr Fitzgerald says that the work is defective and seeks to recover from Mr McLaren damages for the cost of rectification work.

    Findings about jurisdiction

  3. We are satisfied as to the following:

    (a)Mr Fitzgerald is a building owner;[1]

    (b)Mr McLaren is a building contractor;[2]

    (c)Mr McLaren undertook domestic building work for Mr Fitzgerald;[3]

    (d)The dispute, the subject of the proceeding, is a domestic building dispute;[4]

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Fitzgerald v Ryan McLaren t/as Dialled Earthworks & Construc... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] QCAT 307
Decision Date

CaseChat Overview and Summary

The case of Fitzgerald v Ryan McLaren t/as Dialled Earthworks & Construction involved a dispute between a homeowner, Ciaran Fitzgerald, and a builder, Ryan McLaren, trading as Dialled Earthworks & Construction. The homeowner alleged that the builder breached a regulated domestic building contract by failing to carry out the work with reasonable care and skill, contrary to the terms of the contract and the implied warranties contained in the Queensland Building and Construction Commission Act 1991 (Qld). The builder denied the allegations and counterclaimed for payment of an outstanding balance.

The primary legal issues before the court were whether a binding contract existed between the parties, what the terms of the contract were, and whether the builder breached those terms. The court had to determine if the email communications between the parties satisfied the requirements of a written contract under the Electronic Transactions Act 2000 (Qld) and the Queensland Building and Construction Commission Act 1991 (Qld). The court also had to assess whether the builder carried out the work with reasonable care and skill and, if not, to determine the appropriate quantum of damages.

The court found that the parties had indeed entered into a binding contract through their email communications, which satisfied the requirements of Schedule 1B of the QBCC Act. The court concluded that the contract included the terms and conditions of the revised quote, as well as the implied term regarding the payment of the contract price. The court also found that the builder breached the contract by failing to carry out the work with reasonable care and skill, and that the homeowner was entitled to damages for the breach. The court accepted the homeowner's quote for rectification works as evidence of the cost of the necessary repairs and awarded damages accordingly.

The court ordered that Ryan McLaren t/as Dialled Earthworks & Construction must pay Ciaran Fitzgerald $29,997 within 28 days of the decision date, along with costs fixed in the amount of $379.50 within the same timeframe. This decision underscores the importance of adhering to contractual obligations and the consequences of failing to do so in the context of building and construction contracts.

Orders

Orders of the court

1. Ryan McLaren t/as Dialled Earthworks & Construction must pay to Ciaran Fitzgerald $29,997 within 28 days of the date of this decision.

2. Ryan McLaren t/as Dialled Earthworks & Construction must pay to Ciaran Fitzgerald costs fixed in the amount of $379.50 within 28 days of the date of this decision.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

The effect of s 14 of the ET Act was explained by Martin J (as His Honour then was) in Stellard Pty Ltd & Anor v North Queensland Fuel Pty Ltd:[13] 66. Section 14 provides that the requirement for a person’s signature is met for an electronic communication if a method is used to identify the person whose signature is required and to indicate that person’s intention in relation to the information communicated. In the acceptance email, there is no identification of any person as the acceptor of the earlier offer. That is not fatal.67. Section 14(1)(b) provides two alternative methods which will satisfy s 14(1)(a). In this case, the second method has been established. The identification of the person and the person’s intention can be established by further evidence. That further evidence is made up of the various conversations which were had prior to 31 October 2014 and the offer email together with the admission in the pleading that Drew Kellehan sent the email which expressed acceptance of the offer.68. The other point raised by the defendant is that the plaintiff has not demonstrated that it consented to the requirement of the signature being met by using the method referred to above. In circumstances where parties have engaged in negotiation by email and, in particular, where an offer is made by email, then it is open to the court to infer that consent has been given by conduct of the other party. (footnotes omitted)Conclusion on whether the parties entered into a contract complying with the requirements of Schedule 1B of the QBCC Act[13][2015] QSC 119. No direct evidence was given by Mr Fitzgerald or Mr McLaren in relation to the email communications surrounding the revised quote. We are satisfied that the email from Mr McLaren to Mr Fitzgerald on 1 March 2022 and the email from Mr Fitzgerald to Mr McLaren on 10 March 2022 satisfy the requirements of s 14(1)(a) and (b) of the ET Act. In relation to the requirement in s 14(1)(c), we are prepared to infer that, the parties having engaged in negotiation by email, both parties consented to the requirement for a signature being met by the email communications.The terms of the contract Having found that the parties entered into a contract meeting the requirements of schedule 1B of the QBCC Act, we turn to the terms of the contract. In addition to the terms and conditions contained in the revised quote, and the implied term as to payment of the contract price, the warranties mentioned in Division 2 of Part 3, schedule 1B of the QBCC Act form part of the agreement between the parties:[14] (a)Mr McLaren warranted that the work would be carried out in accordance with all relevant laws and legal requirements including for example the Building Act 1975 (Qld);[15] and(b)Mr McLaren warranted the work would be carried out:(i) In an appropriate and skilful way; and(ii) With reasonable care and skill.[16][14]QBCC Act schedule 1B s 19(1).[15]Ibid schedule 1B s 21. [16]Ibid schedule 1B s 22. Finally, before moving on from the issue of the contract, it is necessary to address the effect of the Construction Contract. As we have observed, the Construction Contract was not signed by the parties. The document largely reflected the revised quote albeit with additional conditions. To the extent that the Construction Contract imposed obligations on Mr McLaren regarding the performance of the work there is no inconsistency with the original agreement. The Construction Contract also included a payment schedule which we have also earlier referred to. It does not appear to be controversial that the parties considered the Construction Contract to form part of the agreement for the performance of the works by Mr McLaren. Although not expressed thus by the parties it seems that, and we find, the Construction Contract was a variation of the original agreement. The parties acted consistently with this, noting the evidence that the payments made by Mr Fitzgerald to Mr McLaren were in accordance with the payment schedule. While the Construction Contract was not signed, this does not render the variation unenforceable.[17] Ultimately, nothing turns on the status of the Construction Contract on the basis that the determination of the proceeding turns on whether Mr McLaren undertook the work in breach of the original agreement and the implied statutory warranties. [17]Munro v Camdun Pty Ltd [2024] QCAT 452.The building work

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.