JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
CITATION: FIRM CONSTRUCTION PTY LTD -v- FIRESAFE GROUP PTY LTD [2022] WASC 288
CORAM: MASTER SANDERSON
HEARD: 14 JUNE 2022
DELIVERED : 30 AUGUST 2022
PUBLISHED : 30 AUGUST 2022
FILE NO/S: COR 39 of 2022
BETWEEN: FIRM CONSTRUCTION PTY LTD
Plaintiff
AND
FIRESAFE GROUP PTY LTD
Defendant
Catchwords:
Corporations Law - Application to set aside statutory demand - Turns on own facts
Legislation:
Corporations Act 2001 (WA)
Result:
Demand set aside
Representation:
Counsel:
| Plaintiff | : | J M Healy |
| Defendant | : | J R Shepherd |
Solicitors:
| Plaintiff | : | Pinsent Masons |
| Defendant | : | Blackwall Legal |
Case(s) referred to in decision(s):
Saferack Pty Ltd v Marketing Heads Australia Pty Ltd [2007] NSWSC 1143
MASTER SANDERSON:
This is the plaintiff's application to set aside a statutory demand. The application is supported by an affidavit of Aidan Hugh Glenn sworn 1 March 2022. A copy of the statutory demand is attachment AG‑1 to Mr Glenn's affidavit. The amount claimed in the demand is $33,483.45. The plaintiff also relied on a further affidavit of Mr Glenn sworn 7 April 2022. In opposition to the application, the defendant relied on an affidavit of Jonathan Smallman sworn 1 April 2022.
The application is brought under s 459H(1)(b) of the Corporations Act 2001 (Cth). Reference is made to other sections of the Act, but really the matters argued focussed on s 459H(1)(b). It is the plaintiff's position it has an offsetting claim greater than the amount claimed in the statutory demand. There was no dispute between the parties as to the relevant law. The threshold to establish a genuine dispute is not high. Both parties were prepared to accept what was said on this issue in Saferack Pty Ltd v Marketing Heads AustraliaPty Ltd [2007] NSWSC 1143 [46].
The plaintiff puts its position in this way. The plaintiff entered into a contract with the defendant which comprised, among other things, a purchase order, terms and conditions, scope of work, specifications, drawings and a works schedule 'R1'. Mr Glenn in his affidavit refers to these documents collectively as the 'Contract'. The defendant was to install wet and dry fire systems for a new Royal Perth Hospital helipad ('Works'). The Contract required the defendant (referred to in the Contract as the 'Supplier') to complete all Works including variations so directed by the plaintiff and to deliver compliant handover documents. These documents included as constructed drawings and Operations and Maintenance Manuals. This was to be done by 30 April 2021 ('Completion Date').
On 11 August 2021, as a consequence of the variations, the Contract quantum increased from $294,500 to $303,974.50 ('Contract Sum'). The plaintiff, according to its right to do so under cl 3.4 of the terms and conditions of the Contract, issued the defendant an updated Works Schedule ('Schedule R3'). Schedule R3 included four extensions of time issued by the plaintiff and referred to as 'E1, 2, 3 and 4' ('Plaintiff Issued EOTs').
It is the plaintiff's position that none of the…
Keep reading for free
Create a free CaseChat account to read Firm Construction Pty Ltd v Firesafe Group Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] WASC 288
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the plaintiff had established a genuine dispute with respect to the debt claimed in the statutory demand, as required by section 459H(1)(b) of the Corporations Act 2001 (Cth). Both parties agreed on the relevant legal principles, referencing the case of Saferack Pty Ltd v Marketing Heads Australia Pty Ltd [2007] NSWSC 1143. The plaintiff argued that it had an offsetting claim greater than the amount claimed in the statutory demand due to the defendant's failure to complete the Works by the specified Completion Date. The defendant countered that the Completion Date was uncertain, rendering the clause under which the plaintiff sought liquidated damages void for uncertainty.
The court found that determining the precise terms of the Contract and whether a particular clause was void for uncertainty was beyond the scope of the statutory demand regime. The court held that the issue of the uncertain Completion Date and its implications for the validity of the liquidated damages clause was a matter suited for full litigation rather than summary adjudication. Consequently, the court concluded that the plaintiff had demonstrated a genuine dispute with respect to the debt, and the statutory demand should be set aside. The court also proposed that the defendant pay the plaintiff's costs of the application, including reserved costs.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi