SUPREME COURT OF QUEENSLAND
CITATION:
Ferrari Estate Holdings Pty Ltd v Sovereign Resort Developments Pty Ltd & Ors [2015] QSC 126
PARTIES:
FERRARI ESTATE HOLDING PTY LTD
(ACN 099 918 760) AS TRUSTEE
(Plaintiff)v
SOVEREIGN RESORT DEVELOPMENTS PTY LTD (ACN 010 434 018)
(First Defendant)
and
COOKTOWN EARTHMOVING & QUARRYING PTY LTD (ACN 010 827 540)
(Second Defendant)
and
MATTHEW TROY CAREY TRADING AS MTC BUILDER (BN17682757)
(Third Defendant)FILE NO/S:
SC 139 of 2010
DIVISION:
Trial
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court at Cairns
DELIVERED ON:
13 May 2015
DELIVERED AT:
Cairns
HEARING DATE:
13 February 2015
JUDGE:
Henry J
ORDERS:
1. The claim as against the first defendant is dismissed.
2. I will hear the parties as to costs and as to directions regarding the future of the remainder of the claim at 10 am on 19 June 2015.
CATCHWORDS:
PROCEDURE – COURTS AND JUDGES GENERALLY – COURTS – DISMISSAL OF PROCEEDINGS FOR WANT OF PROSECUTION – PRINCIPLES APPLICABLE – RELEVANT CONSIDERATIONS – where the defendant in the original claim seeks dismissal – where no step has been taken for more than 2 years – where the proceedings were characterised by periods of delay – whether it is in the interests of justice that the matter proceed.
Bird v Ace Insurance Limited [2011] QSC 262, considered
Tyler v Custom Credit Corp Ltd & Ors [2000] QCA 178, appliedParadise Grove Pty Ltd v Stubberfield [2000] QSC 214, cited
Uniform Civil Procedure Rules 1999 (Qld) r 5, r 280, r 389(2), r 429, r 444, r 445
COUNSEL:
Nil
SOLICITORS:
The plaintiff’s director, Ms EPD Ferrari, appeared without legal representation for the plaintiff.
Williams Graham Carman Lawyers for the first defendant
Gadens Lawyers for the second defendant
Moray & Agnew Lawyers for the third defendant
The first defendant applies for the dismissal of the plaintiff’s claim against it for want of prosecution.
Background
The plaintiff and the first defendant are adjoining lot owners of two properties located in Cooktown. The plaintiff owns the Ferrari Estates Building, said by its director Ms Ferrari to be heritage listed and have been built in 1886 for the then Bank of North Queensland. The first defendant owns the Sovereign Resort Hotel, the modern incarnation of which was the subject of development work in 2004.
The second and third defendants were engaged by the first defendant to carry out the development works.
The plaintiff alleges that the works carried out by the second and third defendants in 2004 were done negligently and also involved some transgression beyond the property boundary onto its land. The natural conformation and contours of both the first defendant’s land and the plaintiff’s land were allegedly altered by the works, resulting in the diversion of surface and subsurface water onto the plaintiff’s land from the first defendant’s land. It is alleged that the diverted water pooled, causing flooding, and that this flooding caused structural and superficial damage to the Ferrari Estates Building in 2004, requiring significant…
Keep reading for free
Create a free CaseChat account to read Ferrari Estate Holdings Pty Ltd v Sovereign Resort Developme... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] QSC 126
- Decision Date
CaseChat Overview and Summary
The central legal issue for the court to decide was whether it was in the interests of justice for the proceedings to continue against the first defendant, given the prolonged inactivity and delays. The court needed to consider the principles applicable to the dismissal of proceedings for want of prosecution, including the relevant considerations that must be taken into account in such a context. The court also had to evaluate whether the plaintiff had taken any steps to progress the claim within the relevant time frames, and whether any factors justified the delay or could mitigate against dismissal.
In reaching its decision, the court considered the principles that guide the dismissal of proceedings for want of prosecution. The court observed that there had been no steps taken to progress the claim against the first defendant for over two years, and the proceedings had been characterised by periods of inactivity. The court held that it was not in the interests of justice for the matter to proceed against the first defendant, and accordingly, the claim was dismissed as against that party. The court also made orders for a future hearing to discuss the costs and directions for the remaining claim.
Orders
Orders of the court
1. The claim as against the first defendant is dismissed.
2. I will hear the parties as to costs and as to directions regarding the future of the remainder of the claim at 10 am on 19 June 2015.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi