Falgate v Masterform

Link copied
Case Copied 22 min read
CITATION:

Falgate v Masterform [2005] NSWSC 728

HEARING DATE(S): 18 July 2005
 
JUDGMENT DATE : 


3 August 2005

JURISDICTION:

Equity Division

JUDGMENT OF:

Associate Justice Macready at 1

DECISION:

Paragraph 46

CATCHWORDS:

Catchwords: BUILDING AND CONSTRUCTION - Whether the claim was a payment claim, whether failure to allow the time required before applying for adjudication was a substantial breach of natural justice, whether failure to serve application for adjudication was a breach of natural justice, and whether ceasing action in one jurisdiction indicates abandonment of rights at general law. - The claim set out all the requirements under the Building and Construction Industry Security of Payment Act 1999, thus it was a payment claim. Failure to allow time required was a substantial breach of natural justice. - Held: Adjudication Determination set aside.

CASES CITED:

Brodyn Pty Limited v Davenport [2004] NSWCA 394

PARTIES:

Falgate Constructions Pty Limited v Masterform Pty Limited

FILE NUMBER(S):

SC 55022/2005

COUNSEL:

Mr M. Southwick & I. Wylie for plaintiff
Mr S.A. Benson for defendant

SOLICITORS:

Julie Orsini for plaintiff
Marks Griffiths & Bova for defendant

LOWER COURT JURISDICTION:

- 1 -

IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY &
CONSTRUCTION LIST

Associate Justice Macready

Wednesday 3 August 2005

55022 of 2005 FALGAT CONSTRUCTIONS PTY LIMITED v MASTERFORM PTY LIMITED

JUDGMENT

1 His Honour: This is an application by amended summons filed 18 July 2005 in which the plaintiff seeks a declaration that the Determination made by an Adjudicator, Mr Philip Martin, on 20 August 2004 under the Building & Construction Industry Security of Payment Act 1999 (NSW) (the Act) is void.

2 Previously there had been proceedings between the same parties in respect of a statutory demand arising out of the same dispute between the parties. The evidence in this matter substantially corresponds with the evidence in the earlier matter and, accordingly, I will incorporate some of the chronology of the matter as I referred to it in my earlier judgment of 23 June 2005 in those proceedings.

3 The factual background giving rise to the dispute concerns building work carried out by the defendant company for the plaintiff company which was a contractor in respect of building work at 23 - 25 Chesterfield Parade, Bronte.

4 The plaintiff had entered into a contract with the owner of the site in about July 2003. The defendant was engaged as a sub-contractor to the plaintiff to carry out part of the relevant works.

5 There are conflicting accounts of the arrangements under which this work was to be carried out given by the principals of the two companies. Mr Paul Sussanna for the defendant gave evidence of giving a written quote which priced the job at $128,760.90. He discussed the quote with Mr Rocco Gattellaro of the plaintiff company who said it was too much. The matter proceeded no further at that stage. Mr Sussanna says that a few days to a week later he had a telephone call from Mr Gattellaro…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Falgate v Masterform and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2005] NSWSC 728
Decision Date

CaseChat Overview and Summary

Falgate brought proceedings against Masterform in the Supreme Court of Queensland, challenging an adjudication determination made by a private adjudicator. The dispute centred on whether the claim submitted by Falgate constituted a valid payment claim under the Building and Construction Industry Security of Payment Act 1999 (Qld), and if the adjudicator's decision was valid given certain procedural issues.

The court was required to determine whether Falgate's claim complied with the statutory requirements for a payment claim. Additionally, the court needed to assess whether the failure to allow the requisite period before applying for adjudication constituted a substantial breach of natural justice. It also had to consider whether the failure to serve the application for adjudication was a breach of natural justice, and whether discontinuing the proceedings in the Supreme Court indicated an abandonment of rights at general law.

The court found that Falgate's claim met all the statutory requirements to be considered a payment claim. However, the court held that Masterform's failure to allow the time required before applying for adjudication was a substantial breach of natural justice. The court also found that Masterform's failure to serve the application for adjudication was not a breach of natural justice. Given that Falgate had discontinued the proceedings in the Supreme Court, the court held that Falgate had abandoned its rights at general law. Consequently, the court set aside the adjudication determination.

The court's final order was to set aside the adjudication determination made by the private adjudicator. The court found that while Falgate's claim was valid, the procedural errors committed by Masterform were significant enough to warrant setting aside the adjudication outcome.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established