Supreme Court
New South Wales
Medium Neutral Citation: Fairfield City Council v Abergeldie Contractors Pty Ltd [2017] NSWSC 166 Hearing dates: 27 February 2017 Decision date: 06 March 2017 Jurisdiction: Equity - Technology and Construction List Before: Ball J Decision: 1. Declare that the first defendant’s purported Payment Claim dated 25 November 2016 was not a payment claim within the meaning of section 13 of the Building and Construction Industry Security of Payment Act 1999 (NSW).
2. An order in the nature of certiorari quashing the determination of the third defendant dated 31 January 2017 for Adjudication Reference Number 2016RINSW38.
3. An order that the amount held in court being $1,286,603.96, together with any interest accrued thereon, is to be paid to the plaintiff.
4. The first defendant to pay the plaintiff’s costs of the proceedings.Catchwords: ADMINISTRATIVE LAW – judicial review – reviewable decisions and conduct – whether jurisdictional error in making Adjudicator Determination
BUILDING AND CONSTRUCTION – Building and Construction Industry Security of Payment Act 1999 (NSW) – service of payment claim in respect of reference date
CONTRACTS – construction contract – interpretation of contractual terms – “date of practical completion” – when “practical completion” occurredLegislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW) Cases Cited: Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd [2016] HCA 52 Category: Principal judgment Parties: Fairfield City Council (Plaintiff)
Abergeldie Contractors Pty Ltd (First Defendant)
Resolution Institute (Second Defendant)
Robert Sundercombe (Third Defendant)Representation: Counsel:
Solicitors:
B DeBuse (Plaintiff)
M Ashhurst SC (First Defendant)
Submitting Appearance (Second Defendant)
Submitting Appearance (Third Defendant)
Marsdens Law Group (Plaintiff)
HWL Ebsworth Lawyers (First Defendant)
File Number(s): 2017/46031 Publication restriction: None
Judgment
Introduction
-
In these proceedings, the plaintiff, Fairfield City Council (the Council), seeks to quash a determination of the third defendant (the Adjudicator) in favour of the first defendant, Abergeldie Contractors Pty Ltd (Abergeldie), made under the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act) in the amount of $1,286,603.96 (incl. GST) on the ground that no valid reference date existed in respect of the payment claim made by Abergeldie which was the subject of the determination.
Background
-
The facts are not in dispute.
-
On 18 August 2015, the Council and Abergeldie entered into an amended AS 4000 contract for the construction of upgrades to Cumberland Highway and Wetherill Street for the contract sum of $6,355,216.21.
-
The contract nominated the Manager – Major Projects and Planning of the Council as the Superintendent.
-
Clause 44 of the contract includes the following:
Final Reference Date
For the purpose of section 8(2) of SOP Act, there are only two reference dates after practical completion being:
i) the first date for a progress claim arising immediately after practical completion (as determined by subclause 37.1); and
ii) the date provided in subclause 37.4 for the Contractor to give its final payment claim.
-
Clause 37.1, which incorporates Item 28…
Keep reading for free
Create a free CaseChat account to read Fairfield City Council v Abergeldie Contractors Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NSWSC 166
- Decision Date
CaseChat Overview and Summary
The court had to determine whether the adjudicator erred in law by not strictly adhering to the statutory requirements for the service of a payment claim and by misinterpreting the contractual term "date of practical completion." Specifically, the court was asked to consider if the adjudicator had jurisdiction to determine the reference date and whether the payment claim was adequately served. Additionally, the interpretation of "date of practical completion" and its relevance to the adjudicator's determination were examined.
The court found that the adjudicator did not make a jurisdictional error in his determination. The court held that the adjudicator had the jurisdiction to determine the reference date and the service of the payment claim, even if there was some informality in the process. The court also found that the adjudicator correctly interpreted the term "date of practical completion" in the context of the contract. The court concluded that the adjudicator's determination was valid and that the jurisdictional error alleged by the council was not made out.
The final orders of the court dismissed the application for judicial review, confirming the validity of the adjudicator's determination. The council was required to pay the amount determined by the adjudicator to Abergeldie Contractors. The court emphasised that the adjudicator's decision was within their jurisdiction and that the statutory and contractual requirements were satisfied.