Land and Environment Court
New South Wales
Medium Neutral Citation: EZRA 1 Pty Ltd v Georges River Council [2019] NSWLEC 1275 Hearing dates: 3-5 June 2019 Date of orders: 19 June 2019 Decision date: 19 June 2019 Jurisdiction: Class 1 Before: Horton C Decision: (1) Leave is granted to the applicant to amend the application for development consent, by relying on the information and the amended plans in Exhibit E and Exhibit N.
(2) The Applicant is to pay Council’s costs thrown away as a result of the Applicant amending the development application, as agreed or assessed.
(3) The appeal is dismissed.
(4) The Development Application DA2018/0071 for the demolition of 2 existing structures and construction of basement car park and eight x2-storey attached units to be used as seniors living housing and other ancillary storage works at 10-12 Mimosa Street, Oatley is refused.
(5) The exhibits are returned, except for Exhibits B, E, N and O.Catchwords: DEVELOPMENT APPEAL – against deemed refusal – seniors living development – infill self-care housing – cl 26 location and access to facilities – clause 4.6 written request Legislation Cited: Environmental Planning and Assessment Act 1979
Kogarah Local Environmental Plan 2012
State Environmental Planning Policy (Housing for Seniors or People with a Disability) 2004Cases Cited: Al Maha Pty Ltd v Huajun Investments Pty Ltd [2018] NSWCA 245
Australian Nursing Home Foundation Limited v Ku-ring-gai Council [2019] NSWLEC 1205
Baron Corporation Pty Limited v Council of the City of Sydney [2019] NSWLEC 61
Initial Action Pty Ltd v Woollahra Municipal Council [2018] NSWLEC 118
Wehbe v Pittwater Council (2007) 156 LGERA 446; [2007] NSWLEC 827Category: Principal judgment Parties: EZRA 1 Pty Ltd (Applicant)
Georges River Council (Respondent)Representation: Counsel:
Solicitors:
J Farrell (Applicant)
M Staunton (Respondent)
Boskovitz Lawyers (Applicant)
Georges River Council (Respondent)
File Number(s): 2018/140860 Publication restriction: No
Judgment
Introduction
-
COMMISSIONER: This Class 1 appeal concerns a development application brought before the Court under s 8.7 of the Environmental Planning and Assessment Act 1979 (EPA Act) against the deemed refusal of Development Application DA2018/0071 (the DA) which seeks consent for the demolition of 2 existing structures and construction of basement car park and eight x2-storey attached units to be used as seniors living housing and other ancillary storage works (the amended DA) at 10-12 Mimosa Street, Oatley.
-
The applicant was granted leave to rely on amended plans on 15 February 2019, and the Council re-notified the amended plans to resident objectors on 12 March 2019.
The site and its context
-
The site is located at the corner of two streets with frontage to both Mimosa Street to the south and Winter Place to the east, and incorporates Lot 1 in DP 237970 and Lot 2 in DP 123593.
-
The site is irregular in shape, comprising the amalgamation of two lots of differing geometry. No.10 Mimosa Street is a corner allotment at the intersection with Winter Place, and a total area of 506m2. No.12 Mimosa Street adjoins the T4 Eastern Suburbs…
Keep reading for free
Create a free CaseChat account to read Ezra 1 Pty Ltd v Georges River Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] NSWLEC 1275
- Decision Date
CaseChat Overview and Summary
The key legal issues before the court were whether the applicant was entitled to amend its development application after the appeal had commenced, and if so, what the implications of such an amendment would be, including any costs incurred by the Council due to the amendment. The court needed to determine the appropriate exercise of its discretion regarding the amendment and whether the amendment was justified under the circumstances.
The court found that it was appropriate to grant leave for the applicant to amend the application, considering the information and the amended plans provided. However, the court also determined that the amendment was not in the public interest and that the amended application should be refused. The court held that the amendment resulted in the Council incurring costs that were thrown away, and it was reasonable for the applicant to bear those costs. The appeal was dismissed, and the development application was refused. The exhibits were returned, except for those which were integral to the amended application.
The court's final orders included granting leave for the amendment of the development application, requiring the applicant to pay the Council's costs incurred due to the amendment, dismissing the appeal, refusing the development application, and returning the exhibits except for those pertinent to the amendment.
Orders
Orders of the court
(1) Leave is granted to the applicant to amend the application for development consent, by relying on the information and the amended plans in Exhibit E and Exhibit N.
(2) The Applicant is to pay Council’s costs thrown away as a result of the Applicant amending the development application, as agreed or assessed.
(3) The appeal is dismissed.
(4) The Development Application DA2018/0071 for the demolition of 2 existing structures and construction of basement car park and eight x2-storey attached units to be used as seniors living housing and other ancillary storage works at 10-12 Mimosa Street, Oatley is refused.
(5) The exhibits are returned, except for Exhibits B, E, N and O.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi