Environmental Planning and Assessment Amendment (Wagga Wagga and Western Region Regional Planning Panels) Regulation 2009 (NSW)
2009 No 405
New South Wales
Environmental Planning and
Assessment Amendment (Wagga
Wagga and Western Region Regional
Planning Panels) Regulation 2009
under the
Environmental Planning and Assessment Act 1979
Her Excellency the Governor, with the advice of the Executive Council, has made the following Regulation under the Environmental Planning and Assessment Act 1979.
KRISTINA KENEALLY, MP
Minister for Planning
Explanatory note
The object of this Regulation is to make a transitional provision relating to Crown development and to provide for development applications currently being dealt with by the Wagga Wagga City Council Planning Panel to be dealt with by the Wagga Wagga Interim Joint Planning Panel.
This Regulation is made under the Environmental Planning and Assessment Act 1979, including clause 1 (1) of Schedule 6 to that Act and section 157 (the general regulation-making power) of that Act.
| Published LW 21 August 2009 | Page 1 |
| 2009 No 405 | Environmental Planning and Assessment Amendment (Wagga Wagga and |
| Clause 1 | Western Region Regional Planning Panels) Regulation 2009 |
Environmental Planning and Assessment Amendment (Wagga Wagga and Western Region Regional Planning Panels) Regulation 2009
under the
Environmental Planning and Assessment Act 1979
1 Name of Regulation
This Regulation is the Environmental Planning and Assessment Amendment (Wagga Wagga and Western Region Regional Panels) Regulation 2009.
2 Commencement
This Regulation commences on 1 September 2009 and is required to be published on the NSW legislation website.
3 Amendment of Environmental Planning and Assessment Regulation 2000
(1) Schedule 7 Savings and transitional provisions Insert after clause 18 (4):
(5)
On the constitution of the Wagga Wagga Interim Joint Planning Panel and the Western Region Joint Planning Panel, a development application made by or on behalf of the Crown relating to land within a part of the State covered by those Panels that was referred to the Planning Assessment Commission under sections 23D (1) (d) and 89 of the Act, and not finally dealt with by the Commission, is to be dealt with by the applicable Panel instead of the Commission.
(2) Schedule 7, clause 19 (4) Insert after clause 19 (3):
(4) Despite subclause (3), this clause applies in respect of a development application that may be determined by the Wagga Wagga Interim Joint Planning Panel.