I, the Minister for Planning and Infrastructure, in pursuance of section 115U (4) of

the Environmental Planning and Assessment Act 1979, make the following Order.

Dated, this 16th day of October 2012.

BRAD HAZZARD, MP

Minister for Planning and Infrastructure

Explanatory note

The object of this Order is to amend the State Environmental Planning Policy (State and Regional Development) 2011 to provide that development on land in the Northern Beaches Hospital Precinct that is carried out by or on behalf of a public authority and that has a capital investment value of more than $30 million is State significant infrastructure.

This Order is made under section 115U (4) of the Environmental Planning and Assessment

Act 1979.

Published LW 26 October 2012

Page 1

2012 No 537

Environmental Planning and Assessment Amendment (State Significant

Clause 1

Infrastructure - Northern Beaches Hospital Precinct) Order 2012

Environmental Planning and Assessment Amendment

(State Significant Infrastructure - Northern Beaches

Hospital Precinct) Order 2012

under the

Environmental Planning and Assessment Act 1979

1      Name of Order

This Order is the Environmental Planning and Assessment Amendment (State Significant Infrastructure—Northern Beaches Hospital Precinct) Order 2012.

2      Commencement

This Order commences on the day on which it is published on the NSW legislation website.

3 Amendment of State Environmental Planning Policy (State and Regional Development) 2011

(1)

Clause 4 Definitions

Insert in alphabetical order in clause 4 (1):

State Significant Infrastructure Sites Map means the State Environmental Planning Policy (State and Regional Development) 2011—State Significant Infrastructure Sites Map.

(2)

Schedule 4 State significant infrastructure—specified development

on specified land

Insert after Part 1:

Part 2

Other development

2      Northern Beaches Hospital Precinct

Development carried out by or on behalf of a public authority that has a capital investment value of more than $30 million on land identified as being within the Northern Beaches Hospital Precinct on the State Significant Infrastructure Sites Map.