Environment Protection Authority v Yolarno Pty Limited

Link copied
Case Copied 22 min read

Land and Environment Court


of New South Wales


CITATION: Environment Protection Authority v Yolarno Pty Limited [2004] NSWLEC 764
PARTIES:

PROSECUTOR:
Environment Protection Authority

DEFENDANT:
Yolarno Pty Limited
FILE NUMBER(S): 50108-12 of 2003
CORAM: Bignold J
KEY ISSUES: Environmental Offences :- air pollution odours generated by abattoir's effluent waste waters by malfunctioning of waste water system-mitigating factors
LEGISLATION CITED: Protection of the Environment Operations Act 1997, ss 126, 250(1)(c)
CASES CITED:
DATES OF HEARING: 07/07/2004
EX TEMPORE
JUDGMENT DATE :
07/07/2004
LEGAL REPRESENTATIVES:


PROSECUTOR:
Mr T Howard, Barrister
SOLICITORS
Solicitor for Environmental Protection Authority

DEFENDANT:
Mr J Robson, Barrister
SOLICITORS
Henry Davis York



JUDGMENT:

- 1 -

      THE LAND AND
      ENVIRONMENT COURT
      OF NEW SOUTH WALES

      BIGNOLD J

      7 July 2004

      50108-12 of 2003 ENVIRONMENT PROTECTION AUTHORITY V YOLARNO PTY LIMITED

      JUDGMENT

HIS HONOUR:


1 The Defendant has pleaded guilty to three separate charges of an offence against the provisions of the Protection of the Environment Operations Act 1997, s 126. That section provides in sub-section (1)—

          The occupier of any premises who deals with materials in or on those premises in such a manner as to cause air pollution from those premises is guilty of an offence if the air pollution so caused or any part of the air pollution so caused is caused by the occupier’s failure to deal with those materials in a proper and efficient manner.

2 The Dictionary to the Act contains relevant definitions of “air pollution”, (meaning any emission into the air of any air impurity) and defines “air impurity” (as including smoke, dust, including fly ash, cinders, solid particles of any kind, gases, fumes, mists, odours and radioactive substances).


3 The offence created by s 126 of the Act is one of a number of offences created in Part 5.4 of the Act dealing with air pollution. A number of discrete offences dealing with that subject matter are created by the provisions of 5.4 of the Act and s 132 prescribes the maximum penalty for air pollution offences, not discriminating between the offences, imposing a maximum penalty of $250,000 in the case of a corporation and $120,000 in the case of an individual.


4 The three separate offences were committed during three separate periods of time specified in each of the summonses. The first offence was committed between 10 and 11 December 2002. The second offence was committed between the period 16 December and 19 December 2002, and the third offence was committed on or about 22 January 2003. All three offences were committed at the Defendant’s abattoir premises situate in Clergate Road, Orange, on the outskirts of the Orange town centre some five or six kilometres distant.


5 In each case, the summons specifies that the relevant “materials” (and that term is defined in of s 126(2) to include “raw materials, materials in the process of manufacture, manufactured materials, by products or waste materials)” was in each case effluent waste water generated from…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Environment Protection Authority v Yolarno Pty Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2004] NSWLEC 764
Decision Date

CaseChat Overview and Summary

In the Land and Environment Court of New South Wales, the Environment Protection Authority (EPA) prosecuted Yolarno Pty Limited for three charges under the Protection of the Environment Operations Act 1997 for causing air pollution from their abattoir premises. The offences occurred due to the malfunctioning of the wastewater system at the abattoir, leading to the emission of odours and gases into the atmosphere. The court had to determine the appropriate penalty for these offences, considering both the gravity of the offences and the mitigating factors presented by the defendant. The court found that the defendant, while operating the abattoir, should have recognised the potential issues with the wastewater system and taken steps to prevent the odour problem. However, the court also acknowledged the defendant's early guilty pleas, cooperation with the EPA, and efforts to resolve the problem, which led to a significant reduction in the penalty. The court decided to register a conviction for the offences, reserve the question of penalty, and allow the defendant to propose an environmental restoration project as an alternative to the penalty. The court also ordered the defendant to pay the EPA's legal costs.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.