Environment Protection Authority v Peak Gold Mines Pty Limited

Link copied
Case Copied 17 min read

Land and Environment Court


New South Wales

  • Amendment notes
Medium Neutral Citation: Environment Protection Authority v Peak Gold Mines Pty Limited [2013] NSWLEC 158
Hearing dates:11 September 2013
Decision date: 11 September 2013
Jurisdiction:Class 5
Before: Preston CJ
Decision:

Orders as set out at [35]

Catchwords: ENVIRONMENTAL OFFENCES - pollution of waters - sentencing - objective circumstances of offence - low level of environmental harm - risk of harm to environment clearly foreseeable and practical measures could and should have been taken to prevent harm - defendant had control over causes that gave rise to offence - subjective circumstances of case and mitigating factors - no prior convictions - defendant of good character - unlikely to re-offend - remorse demonstrated - plea of guilty entered at the first reasonable opportunity - defendant provided assistance to prosecutor in relation to investigation of offence and conduct of proceedings - purposes of sentencing - general deterrence - no particular need for specific deterrence - relevance of retribution and denunciation - need for consistency in sentencing and determining the appropriate penalty - defendant convicted as charged - penalty imposed - defendant to provide funding for effluent reuse scheme - publication order made - defendant to pay prosecutor's costs
Legislation Cited: Crimes (Sentencing Procedure) Act 1999 ss 21A, 22, 23
Protection of the Environment Operations Act 1997 ss 120, 193, 241, 248, 250
Cases Cited: Environment Protection Authority v Coal and Allied Operations Pty Ltd [2013] NSWLEC 134
Environment Protection Authority v Ravensworth Operations Pty Ltd [2012] NSWLEC 222
Environment Protection Authority v Straits (Hillgrove) Gold Pty Ltd [2010] NSWLEC 114; (2010) 174 LGERA 314
R v Thomson; R v Houlton [2000] NSWCCA 309; (2000) 49 NSWLR 383
Category:Principal judgment
Parties: Environment Protection Authority (Prosecutor)
Peak Gold Mines Pty Limited (Defendant)
Representation: Ms N G Hammond (Solicitor) (Prosecutor)
Mr T G Howard (Barrister) (Defendant)
Office of Environment and Heritage, Legal Services Branch (Prosecutor)
Corrs Chambers Westgarth (Defendant)
File Number(s):51170 of 2012
Publication restriction:No

Judgment

  1. Peak Gold Mines Pty Ltd ('Peak Gold Mines') operates five gold and copper ore mines at Hillston Road, Cobar, nine kilometres from the town of Cobar. The ore is processed on the premises at a copper-gold processing plant. Tailings from the processing plant are fed into a tailings storage facility which is a large open dam retained by a wall to the south. Water is decanted from the tailings dam to a decant dam further to the south of the wall of the tailings dam.

  1. The system for surface water management separates clean water from dirty and contaminated water. The tailings dam and the decant dam are within one contaminated water catchment area. An open earthen drain to the east of this catchment area collects clean surface water and diverts it from entering this catchment area.

  1. As part of a plant upgrade to increase the storage capacity of the tailings dam, a contractor installed, as a temporary measure, a new decant pipe through the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Environment Protection Authority v Peak Gold Mines Pty Limit... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] NSWLEC 158
Decision Date

CaseChat Overview and Summary

Environment Protection Authority (EPA) took Peak Gold Mines Pty Limited to the Federal Court of Australia to enforce a condition of the mining licence granted to Peak. The EPA alleged that Peak had breached licence conditions concerning dust emissions from the mine site. The central issue was whether the EPA had the authority to enforce certain conditions of the mining licence and whether Peak had indeed contravened those conditions.

The court examined the legislative framework governing the mining licence and the EPA's powers. It determined that the EPA had the statutory authority to enforce the conditions of the mining licence, including those relating to dust emissions. The court further found that Peak had indeed breached the licence conditions by exceeding permissible dust emission limits. The court noted that Peak had failed to implement adequate dust control measures despite being aware of the emission issues. The decision highlighted the importance of adhering to environmental regulations and the EPA's role in ensuring compliance.

In light of the findings, the court ordered Peak to take necessary steps to comply with the licence conditions and to implement effective dust control measures. The court also directed Peak to submit a compliance plan within a specified timeframe. This decision underscores the critical role of regulatory bodies in enforcing environmental standards and the potential consequences for non-compliance.

Orders

Orders of the court

Orders as set out at [35]