Environment Protection Authority v Cut and Fill Pty Limited

Link copied
Case Copied 12 min read

NEW SOUTH WALES LAND AND ENVIRONMENT COURT

CITATION:     Environment Protection Authority v Cut and Fill Pty Limited [2005]  NSWLEC 401

PARTIES:
PROSECUTOR:
Environment Protection Authority

DEFENDANT:
Cut and Fill Pty Limited
ACN 005 412 466

CASE NUMBER:     50077 of        2004

CATCH WORDS:     Environmental Offences

LEGISLATION CITED:
Protection of the Environment Operations Act 1997 s 120, s 241(1) and s 241(2)

CORAM:        Lloyd J

DATES OF HEARING:        27/04/2005

EX TEMPORE DATE:          27/04/2005

LEGAL REPRESENTATIVES

PROSECUTOR:
J Walshe (solicitor)
SOLICITOR:
Stephen Garrett

DEFENDANT:
B Neild (barrister)
SOLICITORS:
N/A

JUDGMENT:

- 9 -

IN THE LAND AND
ENVIRONMENT COURT
OF NEW SOUTH WALES

Lloyd J

Wednesday, 27 April 2005

LEC No. 50077 of 2004

ENVIRONMENT PROTECTION AUTHORITY v CUT AND FILL PTY LIMITED [2005] NSWLEC 401

EX TEMPORE JUDGMENT

  1. HIS HONOUR: The defendant, Cut and Fill Pty Limited, has pleaded guilty to an offence against s 120(1) of the Protection of the Environment Operations Act 1997 (“the POEO Act”), in that it polluted waters.  The offence carries a maximum penalty of $250,000 in the case of a corporation.

  2. The relevant facts have been agreed to in the form of a statement of agreed facts which has been tendered in evidence.  Those facts may be briefly described as follows.

  3. The defendant was contracted by the Roads and Traffic Authority (“the RTA”) to undertake a road works some 10 kilometres north of Armidale on the New England Highway.  The works included the re-alignment of part of the highway and the installation of a new bridge over Duval Creek. 

  4. The defendant arranged for a subcontractor to clear, grub and strip topsoil from an area of land of about 10,000 square metres adjacent to the creek.  A 15 metre buffer zone of vegetation leading down to the creek was retained as a natural filter in respect of sediment contained in any runoff from the works.

  5. There is no doubt that the defendant was on the site and caused the contractor to carry out the works.  It had full control and management of the cleared area, which included the placement of appropriate sediment control measures to protect the environment.  As part of its contract with the RTA the defendant’s responsibilities included the design and installation of appropriate sediment and erosion controls for the cleared area.  Also as part of that contract, the defendant was to comply with the specifications in the contract documents relating to erosion control and sediment control.  The defendant was required to place sediment and erosion control devices in various locations so as to prevent sediment pollution. 

  6. On the afternoon of 13 January 2004 officers of the Department of Environment and Conservation were returning to Armidale on the New England Highway and passing over the Duval Creek Bridge.  It was raining at the time and had been raining heavily for the past day.  They observed the cleared area; they observed loose soil on the cleared area; and saw no sediment or erosion control works from the car.  The officers saw substantial sediment runoff…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Environment Protection Authority v Cut and Fill Pty Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2005] NSWLEC 401
Decision Date

CaseChat Overview and Summary

Cut and Fill Pty Limited, a road works contractor, pleaded guilty to an offence under section 120(1) of the Protection of the Environment Operations Act 1997, which prohibits the pollution of waters. The defendant had been contracted by the Roads and Traffic Authority to carry out road works, including the re-alignment of part of the New England Highway and the installation of a new bridge over Duval Creek. As part of the contract, Cut and Fill Pty Limited was required to implement sediment and erosion controls to protect the environment. However, on 13 January 2004, officers from the Department of Environment and Conservation observed substantial sediment runoff and erosion from the cleared area, with neither discharge point having sediment control and erosion controls in place. The water being discharged was of a brown colour, obviously turbid with a muddy or fine silty appearance. The defendant was required to place sediment and erosion control devices in various locations so as to prevent sediment pollution. It was found that approximately 266,000 litres of sediment-laden water flowed into the creek on 13 January 2004, carrying an estimated 470 kilograms of sediment. The total suspended solid values measured in the creek on that day downstream of the observed discharge were, on average, 1300 milligrams per litre. The defendant was found to be in breach of its contract and the POEO Act for failing to implement the necessary sediment and erosion controls. The court considered various factors in determining the appropriate penalty, including the harm caused, the practical measures that could have been taken to prevent the harm, the extent to which the defendant could reasonably have foreseen the harm, and the extent to which the defendant had control over the causes of the offence. The court found that the defendant had failed to implement the necessary sediment and erosion controls, despite being required to do so by its contract with the Roads and Traffic Authority. The court also noted that the defendant had taken steps to mitigate the harm after the incident, but these controls were not put in place prior to the work being done. The court imposed a penalty of $7,800, taking into account the mitigating factors such as the defendant's cooperation with the Environmental Protection Authority, its unblemished record, and the fact that it pleaded guilty at the earliest opportunity. The court also ordered the defendant to pay the prosecutor's costs in accordance with section 253 of the Criminal Procedure Act 1996. The court retained Exhibit A and allowed Exhibit 1 to be returned.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.