Energy Legislation Amendment Regulation (No. 1) 2016 (Qld)
Part 1 Preliminary
1 Short title
This regulation may be cited as the Energy Legislation Amendment Regulation (No. 1) 2016 .
2 Commencement
This regulation commences on 1 July 2016.
Part 2 Amendment of Electricity Regulation 2006
3 Regulation amended
This part amends the Electricity Regulation 2006 .
4 Replacement of sch 7 (Fees payable to regulator)
Schedule 7—
omit, insert—Schedule 7 Fees payable to regulator
section 226(1)
$
1
Application for generation authority (Act, s 179)
1578.50
2
Application for transmission authority (Act, s 188)
1578.50
3
Application for distribution authority (Act, s 196)
1578.50
4
Application for special approval (Act, s 209)
461.05
5
Application for transfer of a generation authority, transmission authority, distribution authority or special approval (Act, s 184A, 193A, 201A or 212A)
146.50
6
Application for registration of an item of prescribed electrical equipment (s 138)
203.40
7
Application for approval of a change to an energy efficiency label (s 144)
203.40
8
Application for approval of transfer of registration of an item of prescribed electrical equipment (s 147)
67.75
9
Inspection of the register (s 154)
13.25
10
Copy of 1 entry in the register (s 154)
26.90
5 Amendment of sch 8 (Maximum fees payable to electricity entity)
Schedule 8, parts 1 to 3— omit, insert—Part 1 Meter reading and testing
$
1
Special meter reading by Energex
35.85
2
Special meter reading by Ergon Energy
41.65
3
Testing of a meter by a distribution entity
19.30
Part 2 Disconnection and reconnection
$
1
Disconnection of supply of electricity to premises
nil
2
Reconnection of supply of electricity to a customer’s (the current customer’s) premises after disconnection at a customer’s request or under the National Energy Retail Rules, rule 119(1)(g) to (i)—
(a) if the reconnection is made during ordinary business hoursnil
(b) if the reconnection is made outside ordinary business hours at the current customer’s request116.85
3
Reconnection of supply of electricity to a customer’s premises other than as mentioned in item 2—
(a) if the reconnection is made during ordinary business hours48.50
(b) if the reconnection is made outside ordinary business hours at the customer’s request116.85
Part 3 Temporary connections
$
1
Temporary connection of a supply of electricity to a building site by Ergon Energy during ordinary business hours (single-phase or multi-phase)
438.70
2
Temporary connection of a supply of electricity by Energex during ordinary business hours (current transformer or no current transformer)
438.70
Part 3 Amendment of Gas Supply Regulation 2007
6 Regulation amended
This part amends the Gas Supply Regulation 2007 .
7 Amendment of s 51 (Annual distribution fee—Act, s 40)
(1)Section 51(2), ‘$692.80’— omit, insert—$717.00(2)Section 51(3), formula, ‘57,765.35’— omit, insert—59,787.10
8 Replacement of sch 1 (Other fees for distribution authorities)
Schedule 1— omit, insert—Schedule 1 Other fees for distribution authorities
section 53
$
1
Application for distribution authority (Act, s 28)
359.40
2
Application to amend distribution authority, other than to amend a condition imposed under chapter 2, part 1, division 2 of the Act or to correct a clerical or formal error (Act, s 55)
107.55
3
Application to renew distribution authority (Act, s 64)
nil
4
Application to transfer distribution authority (Act, s 68)
359.40
5
Application for approval of surrender of distribution authority (Act, s 73)
nil
6
Late payment fee for an annual distribution fee payable under section 51, paid after the day on which payment is required under section 51(6) (Act, s 323)
107.55
0
0