Energy Efficiency Opportunities Amendment Regulations 2011 (No. 2) (Cth)
Energy Efficiency Opportunities Amendment Regulations 2011 (No. 2) 1
Select Legislative Instrument 2011 No. 156
I, QUENTIN BRYCE, Governor-General of the Commonwealth of Australia, acting with the advice of the Federal Executive Council, make the following Regulations under the
Energy Efficiency Opportunities Act 2006 .Dated 17 August 2011
QUENTIN BRYCE
Governor-General
By Her Excellency’s Command
MARTIN FERGUSON
Minister for Resources and Energy
These Regulations are the
Energy Efficiency Opportunities Amendment Regulations 2011 (No. 2) .
These Regulations commence on the day after they are registered.
3 Amendment of Energy Efficiency Opportunities Regulations 2006 Schedule 1 amends the
Energy Efficiency Opportunities Regulations 2006 .
(regulation 3)
substitute
assessment cycle means each of the following periods:
(a) the period of 5 years beginning on 1 July in the financial year after the trigger year;
(b) each subsequent five year period after the end of the period mentioned in paragraph (a).
baseline energy means the amount of total energy use of a controlling corporation’s group, identified for the purpose of paragraph 201 (1) (a) of Schedule 3.
baseline year , for an assessment cycle relating to a controlling corporation, means the period of 12 months identified as the ‘baseline year’ in the controlling corporation’s approved assessment plan for the assessment cycle.
Note See items 101, 201 and 202 of Schedule 3.
[ 2 ] Regulation 1.3, definition of energy-mass balance
substitute
facility has the meaning given by section 9 of theNational Greenhouse and Energy Reporting Act 2007 .
financial control has the meaning given by section 22R of theNational Greenhouse and Energy Reporting Act 2007 .
insert
indicator means a measure of the energy use of a controlling corporation’s group, or a part of a controlling corporation’s group, that is expressed by reference to a unit of production or service that is reasonably relevant to an industry, its energy use, or both.
Examples 1 GJ per tonne of product produced.
2 GJ per square metre of floor space.
3 Litre per kilometre travelled.
Note It is intended that, if a particular indicator is used in providing data about baseline energy use in an assessment plan, corporations should also use the indicator when carrying out assessments and providing energy use data in reports to the Secretary. This will allow meaningful comparisons to be made between baseline indicators provided in the assessment plan and the indicators provided during later reporting milestones in the course of the assessment cycle.
[ 4 ] Regulation 1.3, after definition of key activity
insert
operational control has the same meaning as it has in section 11 of theNational Greenhouse and Energy Reporting Act 2007 .
substitute
(1) The entity that has operational control over a facility in which energy is consumed is the
user of energy at the facility unless another user is identified in accordance with regulations 1.4A to 1.4C.(2) If an entity:
(a) is the user of energy; and
(b) is a trustee of a trust on behalf of which the trustee may, or may be considered to be, using the energy;
the user of energy is taken to be the trustee, and not the trust or the beneficiaries of the trust.
1.4A User of energy — reporting transfer certificate issued
(1) An entity to which a reporting transfer certificate has been issued under subsection 22L (2) of the
National Greenhouse and Energy Reporting Act 2007 may ask the Secretary, in writing, to treat the entity as the user of energy to which the reporting transfer certificate relates at a facility.(2) The Secretary must accept the request as soon as practicable.
(3) The entity becomes the user of the energy at the facility, in accordance with the request, when the request is accepted.
(4) If the reporting transfer certificate ceases to be in effect in accordance with the
National Greenhouse and Energy Reporting Act 2007 :
(a) the entity ceases to be the user of energy at that time; and
(b) the entity that has operational control over the facility becomes the user of energy.
1.4B User of energy — reporting transfer certificate not issued (registered corporation or member of registered corporation’s group)
(1) An entity (the
second entity ):
(a) that is a registered corporation or a member of a registered corporation’s group; and
(b) for which a reporting transfer certificate has not been issued under subsection 22L (2) of the
National Greenhouse and Energy Reporting Act 2007 ;may ask the Secretary, in writing, to treat the second entity as the user of energy to which the request relates at the facility to which the request relates.
(2) The second entity must have financial control over the facility.
(3) The second entity must make the request as part of:
(a) the submission of an assessment plan; or
(b) the submission of a variation to an approved assessment plan.
(4) The second entity must make the request no later than 18 months before the end of the current five year assessment cycle that applies to the second entity.
Note The five year assessment cycle is mentioned in paragraph 15 (2) (b) of the Act.
(5) The request must be accompanied by a statement, in writing, that:
(a) the entity that has operational control over the facility; or
(b) if that entity is a member of a group — the controlling corporation of the group;
agrees to the request.
(6) If:
(a) the second entity complies with subregulations (1) and (2); and
(b) the request complies with subregulations (3) to (5); and
(c) the Secretary is satisfied that the second entity would be required to be registered under Part 4 of the Act if it became the user of the energy;
the Secretary must accept the request as soon as practicable.
(7) If the Secretary accepts a request in relation to a facility, the entity becomes the user of the energy to which the request relates when the request is accepted.
(8) If the entity that has operational control over the facility notifies the Secretary, in writing, that it no longer wants the second entity to be the user of energy:
(a) the second entity ceases to be the user of energy when the Secretary receives the notice; and
(b) the entity that has operational control over the facility becomes the user of energy.
(9) If the second entity notifies the Secretary, in writing, that it no longer wants to be the user of energy:
(a) the second entity ceases to be the user of energy when the Secretary receives the notice; and
(b) the entity that has operational control over the facility becomes the user of energy.
1.4C User of energy — reporting transfer certificate not issued (not registered corporation or member of registered corporation’s group)
(1) An entity (the
second entity ):
(a) that is not a registered corporation or a member of a registered corporation’s group; and
(b) for which a reporting transfer certificate has not been issued under subsection 22L (2) of the
National Greenhouse and Energy Reporting Act 2007 ;may ask the Secretary, in writing, to treat the second entity as the user of energy to which the request relates at the facility to which the request relates.
(2) The second entity must have financial control over the facility.
(3) The second entity must make the request as part of an application under section 9 of the Act to be registered in relation to the facility.
(4) The request must be accompanied by a statement, in writing, that:
(a) the entity that has operational control over the facility; or
(b) if that entity is a member of a group — the controlling corporation of the group;
agrees to the request.
(5) If:
(a) the second entity complies with subregulations (1) and (2); and
(b) the request complies with subregulations (3) and (4); and
(c) the Secretary is satisfied that the second entity would be required to be registered under Part 4 of the Act if it became the user of the energy;
the Secretary must accept the request as soon as practicable.
(6) If the Secretary accepts a request in relation to a facility, the entity becomes the user of the energy to which the request relates when the request is accepted.
(7) If the entity that has operational control over the facility notifies the Secretary, in writing, that it no longer wants the second entity to be the user of energy:
(a) the second entity ceases to be the user of energy when the Secretary receives the notice; and
(b) the entity that has operational control over the facility becomes the user of energy.
(8) If the second entity notifies the Secretary, in writing, that it no longer wants to be the user of energy:
(a) the second entity ceases to be the user of energy when the Secretary receives the notice; and
(b) the entity that has operational control over the facility becomes the user of energy.
substitute
1.6 Energy use — accuracy, calculation requirements and changed group members
insert
When entity is taken to have satisfied calculation requirements
omit at subregulation 1.6 (1)
insert in subregulation (1)
omit transfer;
insert transfer.
omit
omit
substitute
(1) This regulation sets out principles relating to:
(a) how an assessment plan is to provide for the assessment of the baseline energy of the parts of the controlling corporation’s group to which the plan applies; or
(b) if there are parts of an assessment plan — how each part is to provide for the assessment of the baseline energy of the parts of the controlling corporation’s group to which the part applies.
(2) For the first assessment cycle:
(a) the assessment plan must include a plan to assess at least 80% of the baseline energy of the controlling corporation’s group; or
(b) each part of the assessment plan must include a plan to assess at least 80% of the baseline energy of the parts of the controlling corporation’s group to which the part applies.
(3) For each assessment cycle after the first assessment cycle:
(a) the assessment plan must include a plan to assess at least 90% of the baseline energy of the controlling corporation’s group; or
(b) each part of the assessment plan must include a plan to assess at least 90% of the baseline energy of the parts of the controlling corporation’s group to which the part applies.
(4) If energy use exceeded 0.5 PJ at a site during the baseline year:
(a) the controlling corporation’s group must assess the site; and
(b) subregulation (5) or (7) applies.
(5) If the controlling corporation does not act under subregulation (7), it may omit from the assessment of the site a maximum of 0.01 PJ of energy (
non-integral energy ) used at the site for the purposes of a process, system or activity that is not part of, or integral to, the main energy-using activity or activities conducted at the site.
Examples of processes, systems and activities that are not part of, or integral to, the main business activity or activities that are conducted at a site 1 The operation of lights, information and communication technology or heating, ventilation and air conditioning systems in an on-site office of a mining or manufacturing site.
2 The operation of an on-site kitchen or bathroom.
3 The operation of an appliance in an on-site kitchen or bathroom.
(6) Subregulation (7) applies if the controlling corporation reasonably believes that the estimated cost of assessing the amount of non-integral energy for its processes, systems and activities is likely to be greater than the savings that would be derived from opportunities for improving energy efficiency that would be identified in the assessment in relation to the use of that energy.
(7) For subregulation (6), the controlling corporation:
(a) does not have to consider that use of energy in the assessment of the site; and
(b) may omit from the assessment of the site the lowest of:
(i) the amount of non-integral energy used at the site during the period mentioned in item 202 of Schedule 3; and
(ii) 2% of the amount of energy used at the site during the period mentioned in item 202 of Schedule 3; and
(iii) 0.1 PJ of energy; and
(c) must include in the assessment plan that relates to the relevant part of the controlling corporation’s group:
(i) a statement the controlling corporation reasonably believes that the estimated cost of assessing the amount of non-integral energy is likely to be greater than the savings that would be derived from opportunities for improving energy efficiency that would be identified in the assessment in relation to the use of that energy; and
(ii) information explaining how it formed the belief.
Note Comparing amounts of energy in accordance with paragraph (b) to work out the lowest amount ensures that all of the energy that may be omitted from an assessment will be non-integral energy.
(8) In addition to subregulation (4), the controlling corporation must assess a site if:
(a) a member of the group has built or acquired the site up to 18 months before the end of the assessment cycle; and
(b) the site uses more than 0.5 PJ during a financial year.
(9) An assessment of a site mentioned in subregulation (8) may be an assessment undertaken during the design phase of the construction of the site.
substitute
5.5 Documents that registered corporation must give Secretary — reporting transfer certificate
(1) This regulation applies if:
(a) a registered corporation gives the Secretary:
(i) an assessment plan under section 15 of the Act; or
(ii) a proposed variation to an approved assessment plan under subsection 19 (1) of the Act; and
(b) the plan or proposed variation includes a proposal to define the energy use of the registered corporation in accordance with a reporting transfer certificate issued to the registered corporation in accordance with section 22L of the
National Greenhouse and Energy Reporting Act 2007 .(2) The registered corporation must give the Secretary the information and documents included in the table.
1 | A certified copy of the reporting transfer certificate |
2 | Evidence that the controlling corporation that is to transfer the obligation to assess and report the energy use of the group or part of the group to which the reporting transfer certificate relates has agreed to the transfer |
3 | Evidence that the controlling corporation that is assuming the obligation to assess and report the energy use of the group or part of the group to which the reporting transfer certificate relates has agreed to the transfer |
5.6 Variation of percentage of baseline energy to be assessed
(1) This regulation applies if a controlling corporation wants:
(a) to assess a different percentage of the baseline energy for the first assessment cycle than the percentage mentioned in subregulation 5.3 (2); or
(b) to assess a different percentage of the baseline energy for a subsequent assessment cycle than the percentage mentioned in subregulation 5.3 (3).
(2) The controlling corporation must include the proposed percentage in a proposed variation to the approved assessment plan or the relevant part of the assessment plan.
(3) The controlling corporation must also give the Secretary the following information:
(a) an explanation of why it is not reasonable or appropriate in the circumstances of the group, or the part of the group, to use the percentage mentioned in subregulation (2) or (3);
(b) an explanation of the proposed percentage that the controlling corporation proposes to use, and why it is reasonable and appropriate in the circumstances of the group;
(c) other information or documents relating to the proposed percentage.
Examples for paragraph (c) 1 Information about, or documents relating to, the divestiture of a group member, site, business unit or key activity, and any assessments that have already been undertaken in relation to the divested member, site, unit or activity.
2 Information about, or documents relating to, the acquisition of a new group member, site, business unit or key activity.
3 Information about, or documents relating to, operational requirements (including health and safety requirements) that prevent the assessment of a particular part of a group.
4 Information about, or documents relating to, an assessment that has already been undertaken by the controlling corporation during the assessment cycle that is consistent with the Assessment Framework requirements.
(4) The Secretary is not required to accept the proposed percentage as part of making a decision on the proposed variation.
5.7 Proposal for assessing opportunities for improving energy efficiency of controlling corporation’s group
(1) For paragraph 18 (8) (a) of the Act, this regulation sets out requirements relating to a proposal under section 18 of the Act for assessing the opportunities for improving the energy efficiency of a controlling corporation’s group.
Note The proposal must be set out in the controlling corporation’s assessment plan.
(2) The proposal must include a timeframe for assessments that requires the completion of:
(a) at least one assessment of opportunities for improving energy efficiency for:
(i) each member of the controlling corporation’s group for which an assessment is planned to be undertaken; and
(ii) each business unit for which an assessment is planned to be undertaken; and
(iii) each key activity for which an assessment is planned to be undertaken;
before the end of the first 2 years of the assessment cycle; or
(b) an assessment or assessments of opportunities for improving energy efficiency for at least 40% of the energy use of the controlling corporation’s group before the end of the first 2 years of the assessment cycle.
(3) The controlling corporation may apply to the Secretary for an extension of time for the completion of the assessment or assessments mentioned in the proposal.
(4) An application under subregulation (3) must be made in the form of a variation to the controlling corporation’s assessment plan.
(5) The Secretary may grant an extension of time if the Secretary is satisfied that it is appropriate, having regard to:
(a) the length of the extension; and
(b) the details of the plans to complete the assessment or assessments within the extended time; and
(c) the objectives of the Act.
(6) If the proposal states that an assessment is intended to be completed within the first 2 years of the first assessment cycle:
(a) the assessment may commence before the commencement of the first assessment cycle; but
(b) the proposal is not satisfactory for the purposes of the approval of the assessment plan if the assessment commenced more than 2 years before the commencement of the first assessment cycle.
Note The central component of the Energy Efficiency Opportunities program is the undertaking of a comprehensive and rigorous assessment of energy use across a controlling corporation and its group members, to identify cost-effective energy saving and efficiency opportunities with a payback period of up to 4 years.Companies will need to meet the intent and requirements of the key elements that form the basis of a comprehensive and rigorous assessment. The key elements are set out in Schedule 7.
Companies will also be required to keep evidence that they have done so for verification purposes.
omit
substitute
(1) For subsection 22 (2) of the Act, this regulation sets out reporting periods for a registered corporation.
Note A registered corporation must make reports available to the public after the end of its reporting periods. There are a number of reporting periods within an assessment cycle
First reporting period
(2) Unless subregulation (3) or (5) applies, the first reporting period in the first assessment cycle for the registered corporation:
(a) commences when the first assessment cycle commences; and
(b) ends 2 years after the first assessment cycle commences.
(3) The registered corporation may elect to have a first reporting period in the first assessment cycle that:
(a) commences 2 years before the first assessment cycle commences; and
(b) ends 2 years after the first assessment cycle commences.
(4) If the registered corporation makes an election under subregulation (3), the first reporting period in the first assessment cycle commences and ends in accordance with the election.
Subsequent reporting periods
(5) The period of 12 months that commences at the end of the registered corporation’s first reporting period is a reporting period.
(6) Each period of 12 months that commences on an anniversary of the end of the registered corporation’s first reporting period is a reporting period.
omit For paragraph 22 (3) (d)
insert
(1) For paragraph 22 (3) (d)
insert
(2) For Schedule 4, if, under regulation 7.4, the time at which a report is to be made available to the public is after the end of the assessment cycle to which it relates (the
completed cycle ):
(a) the report must include updated information that relates to activities that have been undertaken in accordance with the assessment plan for the completed cycle; and
(b) it is not necessary for the report to include information relating to activities undertaken for the purposes of an assessment plan (if any) relating to an assessment cycle after the completed cycle.
Note The first reporting period in the first assessment cycle is identified using subregulations 7.1 (2) to (5). The period is at least 2 years. All subsequent reporting periods in the first assessment cycle are one year.Reports for periods towards the end of an assessment cycle may be made available to the public after the end of that assessment cycle. They will be part of a cumulative reporting process covering that assessment cycle, with each new public report replacing the previous one, and are not intended to deal with matters for any other reporting period.
substitute
(1) For paragraph 22 (5) (a) of the Act, a first report under section 22 of the Act must be made available to the public by a registered corporation, or a member or a group, no later than 30 months after the commencement of the first assessment cycle.
Note The first assessment of opportunities for improving the energy efficiency of the registered corporation’s group must be conducted in accordance with the requirements of the Assessment Framework mentioned in regulation 6.1. The requirements will include an explanation of when the first assessment will be completed.
(2) For paragraph 22 (5) (a) of the Act, each report subsequent to the first report must be made available to the public by a registered corporation, or a member or a group, no later than 12 months after the previous report was made available to the public.
(1) For paragraph 22 (5) (b) of the Act, a registered corporation must make a report under section 22 of the Act available to the public in a manner that ensures that the report is:
(a) readily available to the public; and
(b) accessible by the public.
(2) The registered corporation may also make a summary of the report available in a form that is directed particularly to investors, shareholders and other key stakeholders.
Note Reports should be readily available to investors, shareholders, other key stakeholders, and interested members of the public. Registered corporations are encouraged to publish these reports in existing public reports published in Australia, such as an annual report, a sustainability report or an environment report.If the registered corporation does not publish reports of those kinds in Australia, it should publish the report on its website or in other suitable media.
In some cases, space requirements may not allow a registered corporation to meet the minimum reporting requirements of the Energy Efficiency Opportunities Program in an annual report, a sustainability report or an environment report. In those cases, the corporation is encouraged to make a short statement in that report that summarises its involvement in the Program and refers readers to another publication or its own website for a complete public report.
substitute
(1) For subsection 23 (2) of the Act, this regulation sets out reporting periods for a registered corporation in an assessment cycle.
Note A registered corporation must give reports to the Secretary after the end of its reporting periods. The reports must be given to the Secretary in accordance with regulation 7.9.
First reporting period
(2) Unless subregulation (3) applies, the first reporting period in the assessment cycle for the registered corporation:
(a) commences when the assessment cycle commences; and
(b) ends 2 years after the assessment cycle commences.
(3) If the registered corporation proposes to include an assessment or assessments that commenced before the commencement of the assessment cycle, the first reporting period in the assessment cycle:
(a) commences 2 years before the first assessment cycle commences; and
(b) ends 2 years after the assessment cycle commences.
Subsequent reporting period
(4) The full period of the assessment cycle is a reporting period.
omit trigger year
insert baseline year
substitute
(f) the energy use of the relevant group or part of the group, presented as follows:
(i) the use may be expressed using the indicator used in the summary of energy use mentioned in paragraph 201 (1) (c) of Schedule 3;
(ii) if the energy use of the relevant group or part of the group is expressed using another indicator, the information must be accompanied by the energy use for the baseline year, expressed using the other indicator; and
substitute
(2) For the first report, the time is no later than 30 months after the commencement of the first assessment cycle.
Note This is the same as the time specified in subregulation 7.4 (1) for providing the first report to the public.
renumber as subregulation 7.9 (3)
substitute
2 A statement that:
(a) identifies the trigger year; and
(b) says that the controlling corporation’s group used more than 0.5 PJ of energy in the trigger year.
substitute
4 A declaration by the Chief Executive Officer (or equivalent officer) or authorised representative, signing for the controlling corporation, that the information included in the application is, to the best of the officer’s knowledge, correct and in accordance with the Act and these Regulations.
5 For a controlling corporation in respect of which the contact or corporate structure information has changed — a statement at any time providing the amended information.
substitute
101 The baseline year.
substitute
201 (1) A summary of:
(a) total energy use; and
(b) total energy use, having regard to the kinds of energy and energy sources mentioned in subregulation 1.5 (3); and
(c) energy use, expressed using an indicator.
substitute
202 (1) The assessment plan must state the accuracy of the energy use data.
(2) The data about energy use that is to be provided for item 201 must relate to a period of 12 months chosen by the controlling corporation, and identified in its assessment plan, as the baseline year for the assessment cycle.
(3) The period chosen by the controlling corporation must occur within the period:
(a) commencing 24 months before the commencement of the assessment cycle; and
(b) ending 12 months after the commencement of the assessment cycle.
(4) The period chosen by the controlling corporation must also be a period:
(a) that is reasonably representative of the normal annual energy use of the controlling corporation’s group; and
(b) that has ended before the time when the controlling corporation submits its assessment plan; and
(c) for which energy use data is able to be identified and supplied by the controlling corporation at an appropriate level of disaggregation to allow meaningful comparison of key energy use and energy efficiency statistics.
(5) However, if the controlling corporation believes that there is no period of 12 months available in accordance with subitems (2) to (4) that would be reasonably representative of the normal annual energy use of the controlling corporation’s group:
(a) the energy use data provided for the first assessment cycle must relate to a period:
(i) commencing 36 months before the commencement of the assessment cycle; and
(ii) ending 12 months after the commencement of the assessment cycle; and
(b) the controlling corporation must include in its assessment plan:
(i) an explanation of why it is appropriate for that period to be the corporation’s baseline year; and
(ii) any other information that would explain why that period is reasonably representative of the normal annual energy use of the controlling corporation’s group.
omit The total
insert For each assessment cycle, the total
omit the final year of the first five year assessment cycle
insert the final year of the assessment cycle
omit trigger year energy use and production levels
insert energy use and production levels in the year before the commencement of the assessment cycle
substitute
Note Regulation 5.6 provides that a controlling corporation must include in its assessment plan a proposal for assessing the opportunities for improving the energy efficiency of a controlling corporation’s group. The proposal must include a timeframe for the assessment of opportunities that requires the completion of at least one of the activities mentioned in the regulation before the end of the first 2 years of the assessment cycle.
omit
omit Act; and
insert Act.
omit
omit trigger year
insert baseline year
omit A statement of the amounts of energy savings (in the form mentioned in Schedule 6, expressed in GJ), for each group member, or each business unit, or each key activity, according to the time periods set out in the table in Schedule 6, that:
(a) have been identified by the corporation; and
(b) that have been evaluated using costs and benefits, including energy savings, that are certain to an accuracy to within ±30%.
insert A statement of the amounts of energy savings, expressed in GJ, for each group member, or each business unit, or each key activity, that:
(a) have been identified by the corporation; and
(b) are identified per annum by a payback period of less than 2 years; and
(c) are identified per annum by a payback period of at least 2 years and less than 4 years; and
(d) have been evaluated using costs and benefits, including energy savings, that are certain to an accuracy to within ±30%.
Note If energy savings are identified per annum by a payback period of more than 4 years, and are cost-effective to the registered corporation’s group, those savings should also be reported.
substitute
7 (1) Either:
(a) for the part of the controlling corporation’s group to which the report relates — at least 3 examples of significant opportunities for improving the energy efficiency of the group that have been mentioned in the assessment of energy efficiency opportunities; or
(b) for each group member, or business unit, or key activity to which the report relates — at least one example of a significant opportunity for improving energy efficiency that has been identified in the report, to a total of at least 3 examples.
Note For paragraph (b), if a report relates to only 2 group members, business units or key activities, at least 3 examples of significant opportunities will be required (if 3 or more significant opportunities have been mentioned in the energy efficiency opportunities assessment). See also subitem (4).(2) For each example, the report must include a brief description of the opportunity, using commonly understood terminology.
(3) For each example, the report may also include any of the following:
(a) a description of the type of equipment involved in the significant opportunity, using commonly understood terminology;
(b) a statement of the energy use before the significant opportunity was implemented, expressed as a total, using an indicator, or both;
(c) a statement of:
(i) the energy saved by the implementation of the significant opportunity; and
(ii) the effect of the saving on the indicators used to assess the significant opportunity;
(d) the cost of implementing the significant opportunity and the amount of money saved by the implementation of the significant opportunity;
(e) the payback period (if any) for the implementation of the significant opportunity, the net present value of the implementation of the significant opportunity, or both;
(f) the reduction in the volume of greenhouse gases achieved by the implementation of the significant opportunity;
(g) any opinions or comments expressed by the relevant business or industry about the implementation of the significant opportunity.
(4) Despite subitem (1):
(a) if fewer than 3 significant opportunities have been mentioned in the energy efficiency opportunities assessment, each significant opportunity must be identified in the way mentioned in subitems (2) and (3); and
(b) if no significant opportunities have been mentioned in the energy efficiency opportunities assessment, the report must include a statement to that effect.
substitute (b) energy use data, expressed using an indicator; and
substitute
(regulation 6.1)
1 In this Schedule:
energy‑mass balance means a method of accounting for:
(a) the materials and energy entering and leaving a site or fleet and its processes, systems and equipment; and
(b) the energy and material flows, energy conversions and energy use within the site or fleet and its processes, systems and equipment.
Note 1 To enable an appropriate coverage, generally an energy‑mass balance should define, to an accuracy of ±5%, at least 80% of a site’s energy use and all processes not already included in the 80% that use at least 0.1 PJ of energy per year.
Note 2 There is scope for error margins wider than ±5% for some flows or items of equipment at a site, provided the overall assessment data accuracy requirement is met. Wider error margins will typically apply for those energy and material flows that cannot be accurately measured and therefore may require engineering calculations or estimates. For example, data on the heat released from furnaces, grinding mills and boilers might have higher error margins. Accuracy requirements should not be seen as a disincentive to detailed investigation of processes in the energy-mass balance or similar technique.
Note 3 An energy‑mass balance should provide a thorough understanding of:(a) the material flows and energy use through a site, its processes and systems, and items of equipment including items such as pipes, ducts and heat transfers through the building envelope; and
(b) the specific services and products the energy use delivers; and
(c) the energy conversion processes within a system, and identification of conversions that are essential and efficient; and
(d) the identification of energy waste and energy efficiency opportunities.
energy efficiency opportunity , oropportunity , means a potential change to a system, process, activity, technology or piece of equipment that may result in improvements in energy performance with a payback period of 4 years or less.
Note Energy efficiency opportunities are not intended to include potential changes that would be in breach of relevant legal obligations that relate to the system, process, activity, technology or piece of equipment, including (but not limited to) building regulations and occupational health and safety requirements.
energy performance means measurable results related to energy efficiency, use and consumption, in a form that enables comparisons against a corporation’s energy policy, objectives, targets and other energy performance requirements.
idea means an idea for a potential change to a system, process, activity, technology or piece of equipment that:
(a) is intended to improve energy performance; and
(b) has not yet undergone technical or whole-of-business evaluation.
whole-of-business evaluation means the financial evaluation of an energy efficiency opportunity to consider all relevant quantifiable business costs and benefits, including:
(a) direct energy-related costs and savings; and
(b) other quantifiable financial costs and benefits, for example:
(i) capital costs or avoided capital investment; or
(ii) reductions or increases in costs of maintenance, waste disposal, water usage or occupational health and safety; or
(iii) changes in productivity, the quality of outputs or the quantity of outputs.
Note A whole-of-business evaluation is used to determine net costs and benefits in order to calculate payback periods for energy efficiency ideas and opportunities.
Key Element 1
|
1.1 | Senior management and operational management establish and communicate energy assessment and energy performance objectives to all personnel who are responsible for, or have an influence on, energy use and the energy assessment. | Evidence showing the existence and communication of energy assessment and energy performance objectives, e.g.:
|
1.2 | Resources (people, time and money) are made available to meet energy assessment and energy performance objectives. | Evidence that identifies the appropriate personnel, e.g.:
Evidence showing allocation of people, time and money, e.g.:
|
Key Element 2
|
2.1 | Personnel with appropriate skills and expertise are involved in the collection and analysis of energy and process data. | Evidence showing the involvement of appropriately skilled personnel in the analysis of data, e.g.:
|
2.2 | The energy efficiency opportunity identification, evaluation and business case development process involves a broad cross‑section of people, including:
|
Evidence showing the involvement of people in the opportunity identification and evaluation process, e.g.:
| ||
| ||
| ||
| ||
2.3 | Clear roles, responsibilities and accountabilities are attributed to people involved in the assessment and the business response. | Evidence showing the allocation of roles and responsibilities for people involved in the assessment and the business response, e.g.: |
|
Key Element 3
|
3.1 | Business contextual information that influences energy use and returns on energy efficiency investments is analysed for its impact on current and future energy use during the assessment, including:
| Evidence showing that key background information has been collected and analysed for its impact on energy use, e.g.:
|
| 3.2 | Data collection processes are identified, documented and implemented to provide:
| A documented data collection process, including assumptions and uncertainties. Evidence of the implementation of the data collection process, e.g.:
Evidence showing the measures undertaken to improve the accuracy and completeness of data, and to reduce data gaps and uncertainties, e.g.:
|
3.3 | An energy analysis process to assist in the identification, quantification and evaluation of energy efficiency opportunities, using data from Key Requirement 3.2, is undertaken and documented, including:
| A documented energy analysis process. Evidence of the implementation of an energy analysis process, e.g.:
|
| ||
|
Key Element 4
|
4.1 | A process to identify ideas is implemented and documented. The process should involve a review of the contextual information and data that are collected and analysed as part of Key Element 3 and include the appropriate people as stipulated in Key Element 2. The process as implemented should result in a comprehensive list of ideas. | Evidence showing the implementation of a process to identify opportunities, e.g.:
| |
| |||
| |||
| |||
4.2 | Ideas are examined to determine if they are feasible and have a potential payback of less than 4 years. The examination process should result in the feasible ideas with a potential 4 year payback being categorised as either ‘for implementation’ or ‘for further investigation’. These are potential opportunities. Reasons why ideas will not be further investigated are documented. | Evidence showing the outcomes of a process, including:
| |
4.3 | Detailed investigation is undertaken (including sub-metering or real time metering) to quantify the energy use, and energy and financial costs and savings of potential opportunities, to an accuracy of within ±30% If ±30% cannot be achieved, providing an indication in 5.3 of how the accuracy level will be achieved, including further investigation and sub‑metering. A | A list of opportunities and associated recommendations, including criteria used to make recommendations. | |
The costs and benefits for those ideas categorised in 4.2 as ‘for implementation’ need not be evaluated to within ±30%, if they are believed to have immediate business benefits or do not warrant detailed investigation. Detailed investigation to reach an accuracy of ±30% is also not required for those ideas for which it can be shown that a payback period of 4 years or less is not possible, or those that prove to be infeasible for technical, safety or other genuine reasons. | |||
| 4.4 | For all opportunities with a payback period of 4 years or less, recommendations, based on appropriate business criteria, are made to the decision-maker/s responsible for resource allocation and investment. Recommendations should include whether the opportunities should undergo further investigation, be implemented, or not be implemented. Reasons for not pursuing opportunities are documented. | A list of opportunities and associated recommendations, including criteria used to make recommendations. | |
Key Element 5
|
5.1 | Management responsible for decisions about investment and resource allocation is presented with key background information and the relevant outcomes of the assessment. Information presented to management includes:
| Evidence showing presentation of required information to management, e.g.:
|
5.2 | Management responsible for decisions about investment and resource allocation decide the business response, including the opportunities that are to be implemented, to be further investigated (including improvements in data and evaluation accuracy), or not to be implemented. | Evidence showing decisions by management, e.g.:
|
5.3 | The appropriate decision-maker allocates timelines, resources and accountabilities for the business response to the assessment, covering all energy efficiency opportunities that the corporation decides to implement or investigate further (including improvements in data and evaluation accuracy). This includes processes for reviewing and monitoring to learn from experience and support public reporting. | Evidence of allocation of timelines, resources and accountabilities, e.g.:
· Monitoring and feedback mechanisms. |
Key Element 6
|
6.1 | For each relevant business unit or key activity, the board and the senior officer responsible for signing the public report are presented with the public report and: | Evidence of presentation to the board. |
| ||
(d) recommendations for major investments; and
| ||
6.2 | The board reviews and notes the information to be included in the public report. | Evidence of board review and noting, e.g.:
|
6.3 | A clear message about the outcomes of the assessments, in the context of the objectives set by the organisation’s leadership, is to be communicated by senior management and operational management to relevant staff in the organisation. | Evidence of the communication of the outcomes of assessments and progress against objectives, including who has provided the information and to whom the information has been provided, e.g.:
|
1. All legislative instruments and compilations are registered on the Federal Register of Legislative Instruments kept under the
Legislative Instruments Act 2003. See
0
0
0