PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND
CITATION:
Emzay Pty Ltd (ACN 010 659 097) v Bundaberg Regional Council [2023] QPEC 20
PARTIES:
EMZAY PTY LTD (ACN 010 659 097)
(Appellant)v
BUNDABERG REGIONAL COUNCIL
(Respondent)FILE NO/S:
2280/21
DIVISION:
Planning & Environment
PROCEEDING:
Appeal
ORIGINATING COURT:
Planning & Environment Court, Brisbane
DELIVERED ON:
2 June 2023
DELIVERED AT:
Brisbane
HEARING DATES:
11-14 & 17 April 2023
JUDGE:
McDonnell DCJ
ORDER:
THE APPEAL IS DISMISSED AND THE DECISION OF THE RESPONDENT IS CONFIRMED.
CATCHWORDS:
PLANNING AND ENVIRONMENT – APPEAL – COUNCIL APPROVAL – EXTENSION OF APPROVAL - where development approval was granted in 2009 – where four-year extension was granted to 2020– where further extension was granted to 2021 – where the application to extend the currency period for a further five years was refused – appeal against refusal – whether satisfactory explanation for delay – where discretionary considerations included need, bushfire, community awareness, and dedication of land
CASES:
Room2Move v Western Downs Regional Council [2019] QPELR 1010
LEGISLATION:
Planning Act 2016 (Qld) s 87, s88
Planning and Environment Court Act 2016 (Qld) s 43, s 45, s 47
COUNSEL:
M Batty with M Rodgers for the Appellant
B Job KC with K Buckley for the Respondent
SOLICITORS:
Clinton Mohr Lawyers for the Appellant
Connor O’Meara for the Respondent
Introduction
This appeal is against the respondent’s refusal of an application, pursuant to s 86 of the Planning Act 2016 (Qld) (‘Planning Act’), to extend the currency period of a development approval to reconfigure a lot (1 lot into 28 rural lots and balance area) in rural Goodwood within the Bundaberg Local Government Area.
The development application was made on or about 11 February 2009.[1] It was assessed as a Development Application Superseded Planning Scheme against a scheme which took effect on 11 October 1980 and was the subject of a number of amendments up to and including 31 August 2001. Public notification occurred in 2010.[2] One or two submissions were received. The respondent approved the application on 14 December 2012.[3] On 3 July 2017 the respondent granted a four-year extension until 14 December 2020.[4] The development approval was extended until 9 June 2021 as a consequence of the State Government automatic extension granted by the Minister for Planning on 21 July 2020.
[1]Ex. 4, CEO Certificate and Common Material – Vol. 1, 11.
[2]Ex. 4, CEO Certificate and Common Material – Vol. 1, 266.
[3]Ex. 4, CEO Certificate and Common Material – Vol. 1, 491, 1[3].
[4]Ex. 5, CEO Certificate and Common Material – Vol. 2, 37.
On 9 June 2021, the appellant applied to extend the currency period of the approval by five years to 14 June 2026. The council refused that application on 3 August 2021. The appellant appeals against that decision.
If this application for extension is refused the development approval will lapse.[5] However, it is not the case that the proposal can never proceed. To the extent…
Keep reading for free
Create a free CaseChat account to read Emzay Pty Ltd (ACN 010 659 097) v Bundaberg Regional Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2023] QPEC 20
- Decision Date
CaseChat Overview and Summary
The central legal issue for the court was whether the appellant had provided a satisfactory explanation for the delay in proceeding with the development, and if the Council's decision was unreasonable in light of the discretionary considerations it had made. The appellant argued that the delay was due to a combination of factors including difficulties in obtaining finance, the impact of the global financial crisis, and the need to carry out additional environmental studies. The Council, on the other hand, considered that the appellant had failed to demonstrate a satisfactory explanation for the delay and had not shown that the development was still necessary or in the public interest.
The court found that the appellant had not provided a satisfactory explanation for the delay, and that the Council's decision was not unreasonable. The court considered the discretionary factors such as the need for the development, the impact of bushfires, community awareness, and the dedication of land. The court found that the appellant had not demonstrated that the development was still necessary or in the public interest, and that the Council had properly exercised its discretion in refusing the extension. The court held that the Council's decision was reasonable and that the appellant had not demonstrated that it was wrong.
The appeal was dismissed, and the decision of the Bundaberg Regional Council was confirmed. The court found that the Council had properly exercised its discretion in refusing the extension, and that the appellant had not demonstrated that the decision was unreasonable. The appellant was ordered to pay the Council's costs of the appeal.
Orders
Orders of the court
THE APPEAL IS DISMISSED AND THE DECISION OF THE RESPONDENT IS CONFIRMED.