SUPREME COURT OF QUEENSLAND
CITATION:
Emprja Pty Ltd v Red Engine Group Pty Ltd [2017] QSC 33
PARTIES:
EMPRJA PTY LTD CAN 135 384 039
(applicant)
v
RED ENGINE GROUP PTY LTD ACN 006 338 941
(respondent)
FILE NO:
BS7790/16
DIVISION:
Trial Division
PROCEEDING:
Originating Application
DELIVERED ON:
13 March 2017
DELIVERED AT:
Brisbane
HEARING DATE:
6 October 2016
JUDGE:
Jackson J
ORDER:
The order of the court is that:
1. An injunction is granted and the respondent is restrained from berthing or mooring Pelicans in berth 029 at the applicant’s marina from 10 April 2017.
2. The respondent pay the applicant’s costs of the proceeding.
CATCHWORDS:
TORTS – TRESPASS – TRESPASS TO LAND AND RIGHTS OF REAL PROPERTY – WHAT CONSTITUTES TRESPASS AND DEFENCES THERETO – where the applicant was the registered lessee of a marina under a head lease of crown land from the state – where the respondent was the registered sublessee of a marina berth from the applicant – where the respondent’s boat was moored in the subleased berth and the outer side of its hull protruded over the boundary of the sublease – whether the respondent thereby trespassed on the applicant’s land
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – INTERPRETATION OF MISCELLANEOUS CONTRACTS AND OTHER MATTERS – where the respondent was the registered sublessee of a marina berth from the applicant – where the sublease provided that a vesselmoored in the berth must have dimensions appropriate to the berth - where the repondent’s boat was moored in the subleased berth and the outer side of its hull protruded beyond the width of the berth– whether the respondent thereby breached the provision of the sublease
TORTS – TRESPASS – TRESPASS TO LAND AND RIGHTS OF REAL PROPERTY – REMEDIES – INJUNCTION – where the respondent trespassed on the applicant’s land by mooring a boat such that its outer side of the hull protruded over the boundary of a subleased berth – where the applicant applies for an injunction to prevent the respondent from berthing the boat in the sublease – whether the injury to the applicant was small and disproportionate to the detriment to the respondent if an injunction were granted – whether damages should be awarded instead of an injunction
Civil Proceedings Act 2011 (Qld), s 8
Break Fast Investments Pty Ltd v PCH Melbourne Pty Ltd (2007) 20 VR 311, considered
Jaggard v Sawyer [1995] 1 WLR 269, considered
Lawrence v Fen Tigers [2014] AC 822, considered
Mount Bruce Mining Pty Limited v Wright Prospecting Pty Limited (2015) 256 CLR 104, applied
Plenty v Dillon (1991) 171 CLR 635, consideredShelfer v City London Electric Lighting Co [1895] 1 Ch 287, discussed
COUNSEL:
G Beacham QC and M Long for the applicant
P Hastie QC for the respondent
SOLICITORS:
Tresscox Lawyers for the applicant
WMB Lawyers for the respondent
JACKSON J: This is an application for injunctive relief either to require the respondent…
Continue reading Emprja Pty Ltd v Red Engine Group Pty Ltd
Sign in free to access the full text
- AGLC
- Emprja Pty Ltd v Red Engine Group Pty Ltd [2017] QSC 33
- Case
- [2017] QSC 33
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether Red Engine’s actions constituted a trespass to land and whether they breached the sublease agreement. The court also had to consider whether an injunction should be granted instead of damages. In relation to the trespass claim, the court found that Red Engine’s actions constituted a trespass as they intentionally entered Emprja’s land without permission. The court also found that Red Engine breached the sublease agreement by mooring a vessel that did not have dimensions appropriate to the berth. The court considered whether an injunction was the appropriate remedy, and whether damages should be awarded instead. The court found that the injury to Emprja was not small and disproportionate to the detriment to Red Engine if an injunction were granted.
The court granted an injunction and restrained Red Engine from berthing or mooring the boat in the subleased berth from 10 April 2017. The court also ordered Red Engine to pay Emprja’s costs of the proceeding. The court found that Emprja was entitled to an injunction as the injury to them was not trivial and the detriment to Red Engine if an injunction were granted was not disproportionate. The court did not award damages in lieu of an injunction.
Orders
Orders of the court
The order of the court is that:
1. An injunction is granted and the respondent is restrained from berthing or mooring Pelicans in berth 029 at the applicant’s marina from 10 April 2017.
2. The respondent pay the applicant’s costs of the proceeding.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.