Eminent Forms Pty Ltd v Formosa

Link copied
Case Copied 19 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Miscellaneous Appeal: Application)

EMINENT FORMS PTY LTD v FORMOSA & ANOR

Judgment of The Honourable Justice Gray

29 July 2005

ARBITRATION - COSTS - GENERALLY

Ex parte application for leave to appeal pursuant to section 38 of the Commercial Arbitration Act 1986 (SA) against costs award of arbitrator - building contract dispute - consideration of section 34 of the Commercial Arbitration Act - consideration of arbitrator's discretion to award costs - no error of law or fact demonstrated - requirements for leave pursuant to section 38 not fulfilled - held: application refused.

Commercial Arbitration Act 1986 (SA) s 34, s 38, referred to.
Eminent Forms Pty Ltd v Formosa & Anor [2004] SASC 192; Formosa & Anor v Eminent Forms Pty Ltd (2005) 91 SASR 6; Badge Constructions Pty Ltd v Penbury Coast Pty Ltd [1999] SASC 6, considered.

EMINENT FORMS PTY LTD v FORMOSA & ANOR
[2005] SASC 282

GRAY J.

  1. This is an ex parte application for leave to appeal against a costs order of an arbitrator. The applicant seeks leave to appeal pursuant to section 38 of the Commercial Arbitration Act 1986 (SA).

    Background

  2. The applicant is a builder who entered into a building contract with the respondents on 23 October 2002 for the purposes of making alterations and additions to the respondents’ home.  The contract sum was $125,694.00.  Pursuant to the contract, the applicant was to be paid the contract price by progress payments at the completion of various stages of work.  During February 2003, the applicant sought payment of the first progress payment.  The respondents denied the obligation to pay on the basis that the stage 1 works were not completed.  The respondents requested that the applicant place the works on hold until the issue of the progress payment had been resolved.  The applicant issued a notice of termination, asserting breaches by the respondents.  The respondents claimed that the purported termination constituted an unlawful repudiation.

  3. The respondents served notice of dispute pursuant to an arbitration clause in the building contract.  The dispute was referred to an arbitrator on 2 April 2003.   An interim award was published on 17 November 2003 in favour of the respondents in the sum of $22,164.00.  No allowance was made for the work undertaken by the applicant.

  4. The applicant was granted leave to appeal in respect to the interim award.  The appeal was heard by a Judge of this Court on 26 February 2004.  On 1 July 2004 the appeal was allowed and the interim award set aside.   The Judge observed:[1]

    [1] Eminent Forms Pty Ltd v Formosa & Anor [2004] SASC 192 at [45], [60]-[62], [77] – [79].

    It is convenient to state my conclusions to this point. It was a term of the Contract that the respondents pay the appellant the sum of $31,423.50 on completion of the Stage 1 work. The application of two slurry coats of xypex to the cellar walls was part of the Stage 1 work and…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Eminent Forms Pty Ltd v Formosa and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2005] SASC 282
Decision Date

CaseChat Overview and Summary

Eminent Forms Pty Ltd has applied for leave to appeal an award of costs made by an arbitrator under section 38 of the Commercial Arbitration Act 1986 (SA). The application concerns a building contract dispute between the applicant and the respondents. The applicant, a builder, entered into a contract with the respondents for the purpose of making alterations and additions to the respondents’ home. The dispute arose from an issue regarding the first progress payment and culminated in a notice of termination by the applicant and a claim for damages by the respondents. The dispute was referred to an arbitrator, and an interim award was published in favour of the respondents. The applicant was granted leave to appeal this award, which was subsequently allowed. The matter has now returned to the arbitrator, who made an award of costs in favour of the respondents. The applicant has sought leave to appeal this costs award.

The central legal issue in this case is whether the applicant has fulfilled the requirements for leave to appeal as set out in section 38(5) of the Commercial Arbitration Act. The applicant must demonstrate a manifest error of law on the face of the award or strong evidence that the arbitrator made an error of law. The applicant must also demonstrate that the determination of any question of law could substantially affect the rights of one of the parties. Strong evidence must be identified that the arbitrator made an error of law, and the determination of the question must add, or be likely to add, substantially to the certainty of commercial law.

The court held that the applicant had failed to demonstrate a manifest error of law on the face of the award or strong evidence that the arbitrator made an error of law. The court found that the applicant had not demonstrated that the determination of any question of law could substantially affect the rights of one of the parties. Strong evidence had not been identified that the arbitrator made an error of law, and the determination of the question may not add, or be likely to add, substantially to the certainty of commercial law. As a result, the requirements necessary for a grant of leave to appeal as set out in section 38(5) of the Commercial Arbitration Act had not been fulfilled. The application for leave to appeal was refused.

In conclusion, the court found that the applicant had not met the necessary criteria for leave to appeal the arbitrator’s costs award. The court held that the applicant had failed to demonstrate a manifest error of law or strong evidence of an error of law. The application for leave to appeal was accordingly refused.

Background

Background to the litigation

This is an ex parte application for leave to appeal against a costs order of an arbitrator. The applicant seeks leave to appeal pursuant to section 38 of the Commercial Arbitration Act 1986 (SA).Background The applicant is a builder who entered into a building contract with the respondents on 23 October 2002 for the purposes of making alterations and additions to the respondents’ home. The contract sum was $125,694.00. Pursuant to the contract, the applicant was to be paid the contract price by progress payments at the completion of various stages of work. During February 2003, the applicant sought payment of the first progress payment. The respondents denied the obligation to pay on the basis that the stage 1 works were not completed. The respondents requested that the applicant place the works on hold until the issue of the progress payment had been resolved. The applicant issued a notice of termination, asserting breaches by the respondents. The respondents claimed that the purported termination constituted an unlawful repudiation. The respondents served notice of dispute pursuant to an arbitration clause in the building contract. The dispute was referred to an arbitrator on 2 April 2003. An interim award was published on 17 November 2003 in favour of the respondents in the sum of $22,164.00. No allowance was made for the work undertaken by the applicant. The applicant was granted leave to appeal in respect to the interim award. The appeal was heard by a Judge of this Court on 26 February 2004. On 1 July 2004 the appeal was allowed and the interim award set aside. The Judge observed:[1][1] Eminent Forms Pty Ltd v Formosa & Anor [2004] SASC 192 at [45], [60]-[62], [77] – [79].It is convenient to state my conclusions to this point. It was a term of the Contract that the respondents pay the appellant the sum of $31,423.50 on completion of the Stage 1 work. The application of two slurry coats of xypex to the cellar walls was part of the Stage 1 work and that was not done by the appellant. The appellant was not entitled to the first progress payment. As at 24th January 2003 the respondents were not in breach of cl 10 of the Contract. I did not understand the appellant to dispute that if I reached these conclusions, there was no proper basis for its notice of termination which constituted a repudiation of the Contract which was accepted by the respondents.…… The amount of the first progress payment was $31,423.50 and the arbitrator found that the cost to apply the two slurry coats of xypex was $2,340.00. The appellant was not refusing to carry out the work, but rather was saying that it was not required to do it at that stage. It is true that the appellant’s mistaken assertion that he was not required to apply two slurry coats of xypex to the cellar walls as part of the Stage 1 work led it to claim the first progress payment and that the respondents correctly denied that they were liable to make the first progress payment. That denial by the respondents and other alleged breaches of the Contract by the respondents which were without substance formed the basis of the appellant’s notice of termination which was a repudiation of the Contract. However, in my opinion it is not appropriate in the circumstances of this case to look at the ultimate repudiation of the Contract by the appellant in considering the doctrine of substantial performance. In considering whether the appellant’s breach went to the root of the Contract, the act to be considered is the appellant’s failure to complete the Stage 1 work in that it did not apply two slurry coats of xypex to the cellar walls. That conduct did not go to the root of the Contract.The same conclusion follows from the application of the second approach. The nature of the defects and the proportion between the cost of rectifying them ($2,340.00) and the first progress payment ($31,423.50) leads to the conclusion that the Stage 1 works were substantially performed.In my opinion, the appellant was entitled to recover the first progress payment minus an allowance for the application of xypex. At the same time, the respondents were entitled to damages for the subsequent wrongful repudiation of the Contract by the appellant.…There is a question as to whether leave to appeal should be granted in relation to this complaint, and I would have to say that the answer to that question is fairly described as borderline. However, having regard to the approach taken in Angela Kinnane v Zee Homes Pty Ltd (above), I am prepared to grant leave.The appeal must be allowed and the award made by the arbitrator must be set aside. The appellant is entitled to claim from the respondents the first progress payment ($31,423.50) minus the cost of applying two slurry coats of xypex ($2,340.00) giving a total of $29,083.50.The respondents are entitled to recover from the appellant the cost to make good other defective works ($6,291.00), the various sundry items ($894.00) and the compensation for inconvenience and stress ($9,500.00) giving a total of $16,685.00. This leaves a balance in favour of the appellant of $12,398.50.

Decision

Reasons for decision

GRAY J
The proper approach to the issue of costs was fully canvassed by Bleby J in the decision earlier referred to.[6][6] (2005) 91 SASR 6.Conclusion It is of some concern that this matter, involving what might be said to be a relatively modest sum, has been before an arbitrator on at least three occasions and before this Court also on three occasions. There appears to be a pressing need for the issue to be finally resolved. In the present case, having regard to all the circumstances, the applicant has failed to demonstrate a manifest error of law on the face of the award or strong evidence that the arbitrator made an error of law. The applicant has not demonstrated that the determination of any question of law could substantially affect the rights of one of the parties. Strong evidence has not been identified that the arbitrator made an error of law and the determination of the question may add, or may be likely to add substantially to the certainty of commercial law. As a result, the requirements necessary for a grant of leave to appeal as set out in section 38(5) of the Commercial Arbitration Act have not been fulfilled. The application is refused.

Ratio Decidendi

Legal principle established

Established by: GRAY J