Elite Home Builders Pty Ltd v Gould

Link copied
Case Copied 38 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Elite Home Builders Pty Ltd v Gould [2023] QCAT 232

PARTIES:

ELITE HOME BUILDERS PTY LTD
ABN 34 163 123 377

(applicant)

v

JULIE GOULD

(respondent)

APPLICATION NO/S:

BDL 029-22

MATTER TYPE:

Building matters

DELIVERED ON:

26 June 2023

HEARING DATE:

10 November 2022

23 January 2023

HEARD AT:

Cairns

DECISION OF:

Member Taylor

ORDERS:

1.     The applicant’s claim is dismissed.

2.     The respondent’s claim by her counter-application is dismissed.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – where builder claimed payment of an asserted designated stage under the contract – where the owner refused to pay the claim - where the amount claimed exceeded the permitted value entitled to be claimed – where the builder purported to terminate the contract for the owner’s asserted breach – where the builder terminated the contract for the owner’s repudiation – where the builder did not have an accrued right to payment under the contract at the time of termination – where the builder did not press any claim outside of the contract

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – REMEDIES FOR BREACH OF CONTRACT – DAMAGES – where the builder claimed payment of an asserted designated stage under the contract – where the owner refused to pay the claim – where the owner asserted the work was defective and/or incomplete – where the owner asserted the builder was in breach of the contract – where the owner purported to terminate the contract – where the owner repudiated the contract in a purported act of termination

Queensland Building and Construction Commission Act 1991 (Qld), s 77, sch 1B s 4, s 34

Koompahtoo Council v Sanpine P/L (2007) 233 CLR 115

Laurinda Pty Ltd v Capalaba Shopping Centre Pty Ltd (1988) 166 CLR 623
McDonald & Anor v Dennys Lascelles Limited (1933) 48 CLR 457

William George Carlsen t/as W& E Carlsen Builders v Tressider [2015] QCAT 260

APPEARANCES & REPRESENTATION:

Applicant:

W. Mawer – Director

Respondent:

A. Lima

REASONS FOR DECISION

Overview

  1. The applicant presses a claim for payment of what it says is effectively the ‘enclosed stage’ payment in its contract with the respondent. It does so in the confines of what it says is a terminated contract, that termination have been effected by itself.

  2. The respondent argues the applicant is not, and has never been, entitled to that payment in that the work never reached the completion of the ‘enclosed stage’. In contrast to the applicant’s assertion of termination, she asserts that she was the terminating party and accordingly she presses a claim for damages. That claim is the cost to her of completing the construction, alternatively that cost less the unpaid balance of the contract.

  3. Both parties fail in this proceeding to obtain the relief they each seek. The reason for this is that, whilst I have found the applicant was the party which lawfully terminated the contract thus denying the respondent her claim in…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Elite Home Builders Pty Ltd v Gould and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] QCAT 232
Decision Date

CaseChat Overview and Summary

In Elite Home Builders Pty Ltd v Gould, the Queensland Civil and Administrative Tribunal (QCAT) dismissed both parties' claims in a dispute arising from a residential building contract. Elite Home Builders, the applicant, sought payment for an asserted designated stage under the contract, while Julie Gould, the respondent, sought damages for the applicant's alleged defective and incomplete work, and termination of the contract. The tribunal found that the applicant's claim for payment exceeded the permissible value under the contract and the Queensland Building and Construction Commission Act 1991 (Qld). Additionally, the tribunal held that the respondent's termination of the contract was invalid, while the applicant's termination was lawful, as it was based on the respondent's repudiation of the contract. Consequently, both the applicant's claim for payment and the respondent's claim for damages were dismissed.