Electricity Regulation 2006 (QLD)
Electricity Regulation 2006
Chapter 1 Preliminary
1 Short title
This regulation may be cited as the Electricity Regulation 2006.
2 Commencement
This regulation commences on 1 September 2006.
3 Definitions
The dictionary in schedule 9 defines particular words used in this regulation.
4 Purposes
The main purposes of this regulation are to—(a)ensure a secure, efficient and economic supply of electricity to customers on fair and reasonable terms; and(b)ensure customers’ interests are adequately protected; and(c)provide for the proper measurement of the energy efficiency and performance of electrical equipment; and(d)inform the public about the energy efficiency and performance of electrical equipment; and(e)prescribe particular conditions of employment for employees in the GOE industry.
5 How purposes are to be achieved
The purposes of this regulation are to be achieved mainly by—(a)prescribing standards and procedures for the design, building and maintenance of electric lines and works; and(d)prescribing standards and procedures for measuring energy efficiency and the performance of electrical equipment; and(e)providing for the registration and labelling of electrical equipment; and(f)providing for continuity of service for leave purposes for employees transferring within the GOE industry; and(g)providing for long service leave and locality allowance entitlements for GOE industry employees; and(h)providing for award conditions and entitlements of employment for State electricity entities and their electricity industry employees.
6 Words have the same meaning as in wiring rules
(1)Words and expressions used in the wiring rules have the same respective meanings in this regulation.(2)However, for this regulation, the expression ‘point of supply’ in the wiring rules has the same meaning as ‘consumers terminals’ has in this regulation.
7 Way of describing electrical articles and appliances
An electrical article or appliance or type of electrical article or appliance may be described by reference to its model or in any other way.
Chapter 2 Technical requirements
Part 1 Preliminary
8 Application of ch 2
(1)This chapter does not apply to—(a)an electric line or works within the limits of a mine; or(b)petroleum plant.(2)In this section—mine means—(a)a coal mine within the meaning of the Coal Mining Safety and Health Act 1999; or(b)a mine within the meaning of the Mining and Quarrying Safety and Health Act 1999.petroleum plant means private plant or an electrical installation, subject to inspection under the Petroleum and Gas (Production and Safety) Act 2004.private plant means generating plant not used by an electricity entity or special approval holder in accordance with an authority or special approval.
Part 2 Design, building and maintenance of electric lines and works
Division 1 Compliance with part
9 Compliance with this part
A person who designs, builds, maintains or operates an electric line or works must ensure the provisions of this part relevant to the line or works are complied with.Maximum penalty—20 penalty units.
Division 2 Earthing, frequency and voltage
10 Systems of earthing
The system of earthing used by an electricity entity for low voltage supply to customers must be the multiple earthed neutral system, or, if that system is not effective, another suitable system that complies with the wiring rules.
11 Supply at low voltage
(1)Electricity for general supply must be alternating current having a nominal frequency of 50Hz.(2)The standard voltage for the supply, before 27 October 2018, of electricity at low voltage from a 3-phase system is—(a)between a phase conductor and a neutral conductor—(i)the nominal voltage stated for the system in AS 60038; or(ii)240V; and(b)between 2 phase conductors—(i)the nominal voltage stated for the system in AS 60038; or(ii)415V.(3)The standard voltage for the supply, before 27 October 2018, of electricity at low voltage from a single phase system is—(a)between a phase conductor and a neutral conductor—(i)the nominal voltage stated for the system in AS 60038; or(ii)240V; and(b)between the phase conductors—(i)the nominal voltage stated for the system in AS 60038; or(ii)480V.(4)The standard voltage for the supply, on or after 27 October 2018, of electricity at low voltage from a 3-phase system or a single phase system is the nominal voltage stated for the system in AS 60038.
12 Supply at high voltage
If an electricity entity agrees with a customer to supply electricity to the customer at high voltage, the agreed voltage is the standard voltage for the supply.
13 Changes of voltage at customer’s consumers terminals
(1)Supply of electricity by an electricity entity to a customer must be maintained at the standard voltage for the supply mentioned in section 11 or 12.(2)For the supply of electricity at low voltage before 27 October 2018, the supply is taken to be maintained at the standard voltage for the supply if the voltage at a customer’s consumers terminals—(a)for the standard voltage mentioned in section 11(2)(a)(i) or (b)(i) or (3)(a)(i) or (b)(i)—does not differ from the standard voltage by more than the percentage stated for the supply voltage range in AS 60038; or(b)for the standard voltage mentioned in section 11(2)(a)(ii) or (b)(ii) or (3)(a)(ii) or (b)(ii)—is no more than 6% more or less than the standard voltage.(3)For the supply of electricity at low voltage on or after 27 October 2018, the supply is taken to be maintained at the standard voltage for the supply if the voltage at a customer’s consumers terminals—(a)for supply before 1 July 2020—does not differ from the standard voltage by more than the percentage stated for the supply voltage range in AS 60038; or(b)otherwise—(i)is within the minimum preferred steady state median voltage and the maximum preferred steady state median voltage stated in AS 61000; or(ii)if the voltage can not be maintained under subparagraph (i)—does not differ from the standard voltage by more than the percentage stated for the supply voltage range in AS 60038.(4)The supply of electricity at high voltage is taken to be maintained at the standard voltage for the supply if the voltage at a customer’s consumers terminals is—(a)for the supply of electricity at a voltage of 22,000V or less—no more than 5% more or less than the standard voltage; or(b)for the supply of electricity at a voltage more than 22,000V—within the margin agreed between the electricity entity and the customer.(5)For measuring the voltage at a customer’s consumers terminals for subsection (2), (3) or (4), the methodology for the measurement of steady state voltage stated in AS 61000 must be used.(6)In this section—AS 61000 means AS 61000.3.100 (Limits—Steady state voltage limits in public electricity systems) as in force from time to time.
Division 3 Service lines
14 Service lines on customer’s premises—electricity entity’s obligations
(1)An electricity entity must, in accordance with recognised practice in the electricity industry—(a)decide the route, termination point, number of phases, lengths, type and size of its service lines; and(b)provide and install or arrange for the provision and installation of its service lines.(2)The electricity entity must—(a)if requested by a customer to connect a service line that is a standard control service—meet the cost of providing and installing the service line to the customer’s premises; or(b)if requested by a customer to provide and install or arrange for the provision and installation of a service line that is not a standard control service—provide and install or arrange for the provision and installation of the service line to the customer’s premises at the customer’s expense.(3)However, the maximum length of a service line required to be provided and installed within a customer’s premises by an electricity entity at the electricity entity’s cost is—(a)20m for an overhead service line; or(b)7m for an underground service line.(4)Also, subsections (1)(b), (2)(a) and (3) apply only to the provision and installation of 1 initial service line that is a standard control service at particular premises, whether before or after the commencement of this section.Example—
Subsection (1)(b) does not apply if a customer requires an additional service line, or the upgrading of the existing service line, at the customer’s premises to operate 3-phase air-conditioning equipment.(5)For subsections (1) and (3), a service line must be measured from the customer’s property alignment or, if the line does not cross the property alignment, the point of origin of the service line.
15 Service lines on customer’s premises—customer’s obligations
(1)A customer must provide and maintain, free of cost to an electricity entity, the facilities the entity reasonably decides are necessary to attach an overhead service line to the customer’s premises or for the entrance, support, protection and termination of an underground service line.Examples of facilities that may be provided by a customer—
•a service riser bracket•timber backing for the electricity entity’s ‘J’ hook(2)The customer must provide access for the entity to install, test, maintain or take away its service line without hindrance or obstruction.(3)The customer must pay the reasonable cost of a service line provided, unless—(a)the service line is a standard control service; and(b)the line is an initial service line to the customer’s premises.
Division 4 Maintenance of works
16 Maintenance of works
An electricity entity must, in accordance with recognised practice in the electricity industry, periodically inspect and maintain its works to ensure the works remain in good working order and condition.
17 Clearing, lopping and pruning of trees on non-freehold land
(1)An electricity entity may clear, lop or prune trees growing on non-freehold land if—(a)it is necessary to do so to build, maintain or operate an electric line or works on the land; and(b)the entity holds the benefit of an easement, licence or other agreement in relation to the line or works.(2)Subsection (1) applies—(a)whether or not the easement, licence or agreement authorises the clearing, lopping or pruning; and(b)subject to—(i)the conditions of the easement, licence or agreement; and(ii)section 18.(3)To the extent a local planning instrument or a local law is inconsistent with subsection (1), the local planning instrument or local law is of no effect.(4)In this section—local planning instrument means a local planning instrument under the Planning Act 2016.trees see the Forestry Act 1959.
Division 5 Works on publicly controlled places
18 Notice to be given to public entity
(1)This section applies if an electricity entity intends to take action mentioned in subsection (2) in a publicly controlled place unless—(a)the action is an action authorised under sections 140 to 141 of the Act; and(b)the entity complies with the section in relation to the entry to the place and the taking of the action.(2)The action is—(a)opening or breaking up the soil or pavement of the place; or(b)clearing, lopping or pruning a tree or other vegetation growing in or over the place, other than for routine maintenance; or(c)opening or breaking up a sewer, drain or tunnel in or under the place; or(d)temporarily stopping or diverting traffic on or from the place; or(e)building a drain, excavation, subway or tunnel in or under the place.(3)The electricity entity must give at least 14 days written or oral notice of its intention to the public entity that has control of the publicly controlled place unless the notice is given in accordance with another period of notice agreed between the entities.(4)However, subsection (5) applies if, in the electricity entity’s opinion, there is an emergency in which—(a)there is an actual or a potential danger to persons or property; or(b)the supply of electricity to a customer has been interrupted.(5)If this subsection applies, the electricity entity may act under section 101 of the Actto remedy a defect, eliminate an actual or potential danger or restore the supply of electricity to a customer, without first giving the notice under subsection (3).(6)If the electricity entity acts under subsection (5), it must give the notice mentioned in subsection (3) as soon as practicable.
19 Electricity entity must comply with public entity’s requirements
(1)If an electricity entity goes on a publicly controlled place to take action for which notice must be given under section 18, the public entity that has control of the place may require the electricity entity to act on the days and at the times the public entity reasonably requires.(2)The electricity entity must comply with a reasonable requirement by the public entity under subsection (1).
20 Guarding of work on publicly controlled place
(1)An electricity entity that has opened or broken up a publicly controlled place must, at all times while the place is opened or broken up, ensure—(a)it is barricaded and guarded; and(b)signs and lights sufficient for the warning and guidance of traffic, including pedestrians, are set up and maintained against or near the place where it is opened or broken up.(2)If required by the public entity, the electricity entity must also set up and maintain additional warning or protection devices to safeguard the public whether before or during the work.
21 Restoration of publicly controlled place
(1)An electricity entity that has opened or broken up a publicly controlled place must—(a)with all convenient speed, finish the work; and(b)on finishing the work, take away from the place all plant, materials and equipment not built into the work; and(c)restore, as far as practicable, the place where the work was carried out and leave it tidy.(2)The way action under subsection (1) is to be carried out by or for the electricity entity is as agreed between the electricity entity and the public entity controlling the place and in accordance with reasonable conditions and requirements stated by the public entity.
22 Electricity entity to keep publicly controlled place in good repair after work
(1)An electricity entity must keep a publicly controlled place that has been opened or broken up and restored by it in good repair—(a)for 3 months after restoring the place; and(b)if the ground subsides and continues to subside—for up to a further 9 months.(2)The way maintenance work is to be carried out by or for the electricity entity is as agreed between the electricity entity and the public entity that controls the place.
23 Warning signs on roads
If an electricity entity or its contractor is building or maintaining an electric line or other works on a road, signs and lights set up and maintained by the entity and its contractor to safeguard the public must be the appropriate official traffic signs under the Transport Operations (Road Use Management) Act 1995.
Part 3 Customers’ electrical installations
24 Installation and operation of electric line beyond person’s property
(1)A person may install and operate, on a place beyond the person’s property (including on a publicly controlled place), a low voltage electric line forming part of the person’s electrical installation if—(a)the person has consulted with all entities who may have an interest in the proposed location of the electric line; and(b)the entities have stated in writing that they have no objection to the installation or operation of the electric line; and(c)the installation and operation of the electric line is not likely to cause a fire or a person to suffer an electric shock.(2)The entities to be consulted include—(a)the relevant supplier; and(b)for a publicly controlled place—the local government or other entity with responsibility for the place; and(c)for a place other than a publicly controlled place—the owner and each lessee or occupier of the place.(3)The electric line must be installed in accordance with—(a)the wiring rules; and(b)any requirement or condition imposed by an entity consulted.(4)If an electric line forming part of a person’s electrical installation is installed on a place contrary to this section, the regulator may direct the person to take away the electric line, at the person’s expense.(5)The regulator must give the person a QCAT information notice about the decision to give the direction.(6)If the person does not comply with the direction, the regulator may take away the electric line and recover the cost of the removal from the person as a debt payable to the State.(7)A person who complies with subsections (1) to (3) about an electric line does not need an authority or special approval under the Act to install or operate the line.
25 Power factor
A customer must comply with any requirement of its supplier made of the customer under section 36 about the power factor of an electrical installation.Note—
See section 37 for what action the distribution entity may take if the customer does not comply with the requirement.
26 Prevention of interference by motor installations and associated starting devices
A person may connect a motor installation or associated starting device only if it is designed and operated to comply with any requirements of the regulator to prevent interference with supply of electricity to other customers.Note—
See sections 36 and 37 for what action a distribution entity may take if the distribution entity considers the installation or device interferes, or is likely to interfere, with the supply of electricity to other customers.
27 Interference with supply of electricity
A customer must not use electricity or an electrical article so the supply of electricity to other customers of the supplier who supplies the electricity is unreasonably interfered with.Note—
See sections 36 and 37 for what action a distribution entity may take if the distribution entity considers the installation or device interferes, or is likely to interfere, with the supply of electricity to other customers.
28 Customer’s generating plant for interconnection to supply network
(1)A customer must not install generating plant for interconnection with a supplier’s supply network without the supplier’s agreement.Maximum penalty—20 penalty units.
(2)The agreement must include the conditions for securing safe and stable parallel operation of the supply network and the generating plant.
29 Requirement for circuit-breaker
(1)If required by the relevant supplier, a customer must ensure the customer’s electrical installation has a circuit-breaker as a main switch or a circuit-breaker instead of a fuse as part of the installation.Maximum penalty—20 penalty units.
(2)However, the customer may choose whether to have a circuit-breaker as a main switch or a circuit-breaker instead of a fuse if the relevant supplier does not state which is required.
30 Coordination of customer’s protection devices with electricity entity’s protection system
(1)An electricity entity may cause the characteristics of a customer’s protection device to be changed and tested to maintain discrimination between the customer’s protection equipment and the electricity entity’s protection system.(2)The electricity entity may seal the adjusted protection equipment.(3)A person must not unlawfully break or otherwise interfere with the seal.Maximum penalty for subsection (3)—20 penalty units.
Part 4 Qualifying customers’ small photovoltaic generators
30AA Prescribed credit amount for credit for electricity produced by small photovoltaic generators
(1)For section 44A(1)(b) of the Act, the prescribed credit amount for a qualifying customer for a premises who, before 10 July 2012, lodged with a distribution entity a completed application to connect 1 qualifying generator at the premises to its supply network is $0.44 for each kilowatt hour.(2)A qualifying customer mentioned in subsection (1) is a category 1 qualifying customer.
30AB When a qualifying customer stops being entitled to be credited with prescribed credit amount for a category 1 qualifying customer
(1)A qualifying customer stops being entitled to be credited with the prescribed credit amount under section 44A(1)(b) of the Actfor a category 1 qualifying customer in relation to a qualifying generator that is connected to a distribution entity’s supply network if the name on the electricity account for the premises is changed to another person.
Example of when the name on an electricity account may be changed—
The premises are sold or rented out.(2)Subsection (1) does not apply if the qualifying customer’s spouse was a category 1 qualifying customer for the premises immediately before the qualifying customer became a qualifying customer for the premises.(3)A qualifying customer also stops being entitled to be credited with the prescribed credit amount under section 44A(1)(b) of the Actfor a category 1 qualifying customer if—(a)no qualifying generator has been connected at the qualifying customer’s premises to a distribution entity’s supply network by the end of 30 June 2013; or(b)no qualifying generator is ready to be connected at the qualifying customer’s premises to a distribution entity’s supply network by the end of 30 June 2013.
30AC [Repealed]
Chapter 3 Electricity supply and sale to customers
Part 1A [Repealed]
Division 1 [Repealed]
Subdivision 1 [Repealed]
30A [Repealed]
30B [Repealed]
Subdivision 2 [Repealed]
30C [Repealed]
30D [Repealed]
30E [Repealed]
Subdivision 3 [Repealed]
30F [Repealed]
30G [Repealed]
30H [Repealed]
Subdivision 4 [Repealed]
30I [Repealed]
30J [Repealed]
30K [Repealed]
30L [Repealed]
30M [Repealed]
Subdivision 5 [Repealed]
30N [Repealed]
30O [Repealed]
30P [Repealed]
30Q [Repealed]
30R [Repealed]
30S [Repealed]
30T [Repealed]
Division 2 [Repealed]
30U [Repealed]
30V [Repealed]
30W [Repealed]
30X [Repealed]
30Y [Repealed]
30Z [Repealed]
31 [Repealed]
32 [Repealed]
33 [Repealed]
34 [Repealed]
35 [Repealed]
Part 1 Distribution entities and metering coordinators
Division 1 Obligations of distribution entities and customers
36 Regulating customer’s use etc. of electricity
(1)This section applies if, in the distribution entity’s opinion—(a)the use or intended use of an electrical article by a customer unreasonably interferes, or is likely to unreasonably interfere, with the entity’s supply of electricity to other customers; or(b)a customer uses or deals with electricity so the supply of electricity to other customers is, or is likely to be, unreasonably interfered with; or(c)a customer’s motor installation or associated starting device interferes, or is likely to interfere, with supply of electricity to other customers; or(d)it is necessary to regulate the power factor of a customer’s electrical installation.(2)The entity may, by written notice to the customer, require the customer to—(a)regulate the use of the electrical article; or(b)use or deal with electricity supplied in a stated way; or(c)ensure a motor installation or starting device connected to a source of electricity supply complies with the requirements of the regulator under section 26; or(d)ensure the power factor of an electrical installation measured over any 30 minutes at the customer’s consumers terminals—(i)for low voltage supply to the customer—(A)is at least 0.8 lagging; and(B)is not a leading power factor unless the entity agrees; or(ii)for high voltage supply to the customer—is within the range stated in the National Electricity Rules, schedule 5.3.5.Editor’s note—
National Electricity Rules, schedule 5.3.5 (Power factor requirements)(3)The notice must state when it must be complied with.(4)The notice must be accompanied by or include an information notice about the decision.
37 Action if notice not complied with
If a customer does not comply with a notice under section 36, the distribution entity may—(a)refuse to provide customer connection services to the customer’s electrical installation until the customer complies with the notice; or(b)if the customer agrees to comply with the entity’s requirements—provide the service.
Division 2 Meter and control apparatus requirements for premises
38 Application of div 2
This division applies to the supply of electricity to a particular customer’s premises.
39 Who is the metering coordinator
In this division, the metering coordinator is the person who, under the National Electricity Rules or a distribution network code, is the party responsible for the metering installation for the premises.
40 Customer to change electrical installation for meter connection
(1)The metering coordinator may require the customer to make changes to the customer’s electrical installation at the premises that are necessary to allow connection of a meter at the premises.(2)Subsection (1) does not apply if—(a)the meter is a replacement meter proposed to be installed as part of a new meter deployment by the metering coordinator and the customer has opted out of the new meter deployment under the National Energy Retail Rules, rule 59A; or(b)the meter is part of a new or replacement type 4 metering installation proposed to be installed by the metering coordinator and the customer has communicated the customer’s refusal of the installation under the National Electricity Rules, rule 7.8.4(e).(3)In this section—new meter deployment has the meaning given by the National Energy Retail Rules.type 4 metering installation has the meaning given by the National Electricity Rules.
41 Customer to provide links connecting meter to incoming supply
(1)If the metering coordinator so requires, the customer must provide suitable links for connecting meters to an incoming electricity supply to the premises.(2)However, the requirement may be made for a single meter only if—(a)the meter is being, or is proposed to be, installed; or(b)the customer is making, or is proposing to make, a substantial change to the meter or a substantial change to the premises that relates to the meter.Examples—
•relocation of the meter•replacement of the mounting for the meter•rewiring of the premises(3)The metering coordinator may seal the links.
42 No breaking or interfering with meter seal
(1)This section applies if the metering coordinator has provided a meter or links for the premises and there is a seal on the meter or links.(2)A person (the first person) must not break or interfere with the seal unless the metering coordinator has permitted the first person to do so.Maximum penalty—20 penalty units.
43 No breaking or interfering with network device seal
(1)This section applies if a distribution entity for the premises has provided a network device for the premises and there is a seal on the device.(2)A person must not break or interfere with the seal unless the distribution entity has permitted the person to do so.Maximum penalty—20 penalty units.
44 Placing meter or network device on customer’s premises
(1)The customer must, at the customer’s expense—(a)provide at the premises space, housing, mounting and connecting facilities for each meter and network device provided by the metering coordinator or distribution entity for the premises; and(b)maintain the facilities in a safe and sound condition.(2)The facilities must be in a position that meets the reasonable requirements of—(a)for a meter—the metering coordinator; or(b)for a network device—the distribution entity for the premises.
45 Change of placement if building changes or works
(1)This section applies if, because of building changes or similar works, the position of a meter or a network device at the premises no longer meets requirements made under section 44(2).(2)The customer must, at the customer’s expense—(a)provide space, housing, mounting and connecting facilities in another position at the premises that meets the reasonable requirements of—(i)for the meter—the metering coordinator; or(ii)for the network device—the distribution entity for the premises; and(b)arrange for relocation to the other position by—(i)for the meter—the metering coordinator; or(ii)for the network device—the distribution entity.
46 Customers to provide safe access
(1)This section applies if the customer does not provide safe access at any reasonable time to read a meter and install, test, maintain or take away the supplier’s works without hindrance or obstruction to—(a)the distribution entity for the premises, a special approval holder, the metering coordinator or the customer’s retailer (the relevant entity); or(b)an electricity officer of a relevant entity; or(c)a person authorised by a relevant entity.(2)The relevant entity may, by written notice to the customer, require the customer to provide the access within a stated period of at least 1 month.(3)If the customer does not comply with the notice, the relevant entity may install alternative metering or other equipment to enable consumption to be measured by remote or other suitable ways.(4)Subsection (3) does not limit or otherwise affect another remedy the relevant entity has against the customer.(5)The relevant entity may recover from the customer as a debt its costs reasonably incurred in acting under subsection (3).
47 [Repealed]
48 [Repealed]
49 [Repealed]
50 [Repealed]
51 [Repealed]
52 [Repealed]
53 [Repealed]
54 [Repealed]
55 [Repealed]
56 [Repealed]
Division 3 Substations on customers’ premises
57 Application of div 3
(1)This division applies if the supply of electricity required by customers in premises is more than, or is reasonably estimated by the distribution entity to be more than, a total maximum demand of 100kV.A worked out under the wiring rules.(2)This division also applies to supply of electricity to customers in premises if the regulator, in special circumstances, approves its application.
58 Meaning of owner in div 3
In this division—owner, of premises, includes a person who is the proprietor, lessee or occupier of the premises or part of the premises.
59 Owner to provide space for substation
(1)This section applies if, to meet an existing or likely demand for supply of electricity by customers who are, or in the future may be, in premises, the distribution entity reasonably considers it is necessary to install a substation on the premises.(2)The entity may require the owner of the premises to—(a)provide, free of cost to the entity, the space for a substation; and(b)give a right of way to the entity for its electric lines and cables to and from the substation; and(c)provide to the entity, or persons authorised by it, access to the entity’s equipment on the premises at all times to allow the entity to install, maintain or take away its equipment without hindrance or obstruction.(3)The owner must also provide permanent handling facilities, segregated access passageways or ventilating ducts if they are needed because of the location the owner proposes to provide for the substation.(4)An owner who provides space for a substation under this section must—(a)maintain the floor or foundation, walls or enclosure, ceiling and access door of the space in sound condition; and(b)repair damage to or deterioration of the space, other than damage or deterioration directly attributable to the use of the space by the entity.(5)Repairs must be done within the time and to the extent reasonably directed by the entity.(6)If the owner does not comply with subsection (4), the entity may—(a)do anything necessary to carry out the maintenance or repair; and(b)recover from the owner as a debt the reasonable costs of anything done by the entity under paragraph (a).(7)In this section—space, for a substation, means—(a)necessary or suitable floor or foundation, walls or enclosure, ceiling and access doors in the part of the premises where the substation is to be located and installed, with the walls or enclosure, ceiling and access doors being suitably painted; and(b)necessary or suitable places for entry and exit of electric lines and cables for the substation; and(c)if required by the distribution entity—suitable lighting and general power outlets.
60 Supply to other customers from substation
(1)A distribution entity may only use an electric line or equipment installed by it on premises under this division for providing customer connection services to customers outside the premises if the owner of the premises agrees.(2)If the agreement is given, it continues in force while the substation is still being used to supply electricity to the premises.(3)Subsection (2) applies even if the total maximum demand for the electricity is less than the amount mentioned in section 57(1).
61 Limitation of compensation
Unless agreed between the owner and the distribution entity, an owner of premises for a substation is not entitled to compensation from the distribution entity for—(a)the installation of the substation; or(b)complying with a requirement under section 59; or(c)carrying out an obligation imposed on the owner under section 59; or(d)agreeing under section 60 for the substation to be used for the purpose of supplying customers outside the premises, other than reasonable compensation for any additional space, over and above the space used to supply customers on the premises, occupied by the substation for that purpose.
62 Taking away distribution entity’s equipment
(1)If supply of electricity to an owner’s premises is no longer needed, the distribution entity must, within a reasonable period, take away, at its own cost, its electric lines, cables and equipment from the premises if the owner asks.(2)Subsection (3) applies if the electric lines, cables and equipment are, under section 60, used to supply electricity to customers not on the premises.(3)In deciding what is a reasonable period for subsection (1), regard must be had to whether the period is enough to allow the distribution entity to provide an alternative supply of electricity to the customers mentioned in subsection (2).
Division 4 [Repealed]
63 [Repealed]
64 [Repealed]
65 [Repealed]
66 [Repealed]
Part 2 [Repealed]
67 [Repealed]
68 [Repealed]
69 [Repealed]
70 [Repealed]
71 [Repealed]
Part 3 [Repealed]
Division 1 [Repealed]
Subdivision 1 [Repealed]
72 [Repealed]
73 [Repealed]
74 [Repealed]
Subdivision 2 [Repealed]
75 [Repealed]
76 [Repealed]
76A [Repealed]
Subdivision 3 [Repealed]
77 [Repealed]
Division 1A [Repealed]
77A [Repealed]
77B [Repealed]
77C [Repealed]
Division 2 [Repealed]
Subdivision 1 [Repealed]
78 [Repealed]
79 [Repealed]
80 [Repealed]
Subdivision 2 [Repealed]
81 [Repealed]
Subdivision 3 [Repealed]
82 [Repealed]
83 [Repealed]
84 [Repealed]
85 [Repealed]
Subdivision 4 [Repealed]
86 [Repealed]
87 [Repealed]
Division 3 [Repealed]
87A [Repealed]
87B [Repealed]
87C [Repealed]
87D [Repealed]
87E [Repealed]
87F [Repealed]
Division 3A [Repealed]
Subdivision 1 [Repealed]
87FA [Repealed]
87FB [Repealed]
Subdivision 2 [Repealed]
87FC [Repealed]
87FD [Repealed]
Division 4 [Repealed]
87G [Repealed]
87GA [Repealed]
Part 4 Disputes about what is fair and reasonable
88 Dispute resolution
(1)This section applies if—(a)the Act or this regulation requires an electricity entity to do something on—(i)fair and reasonable terms; or(ii)a fair and reasonable basis; and(b)there is a dispute about fairness or reasonableness; and(c)the dispute is not—(i)an access dispute under the Queensland Competition Authority Act 1997, section 112(2); or(ii)a dispute that may be the subject of a dispute referral to the energy and water ombudsman under the Energy and Water Ombudsman Act 2006.(2)A party to the dispute may ask QCA to resolve the dispute.(3)QCA may—(a)give instructions about procedures the parties must follow to attempt to resolve the dispute before QCA takes steps to resolve it; or(b)require a party to give QCA information QCA considers necessary to enable the dispute to be resolved.(4)QCA must give each party a reasonable opportunity to make representations before making the decision.(5)After considering any representations, QCA must decide the issue in dispute.(6)QCA must give the parties a QCAT information notice about the decision.
89 QCA may seek advice or information
(1)This section applies if, under section 88(2), QCA has been asked to resolve a dispute.(2)To help resolve the dispute, QCA may seek advice or information from any other person.(3)QCA may take the advice or information into account in resolving the dispute.(4)If QCA seeks information or advice or takes into account advice or information QCA has been given for any other dispute, QCA must—(a)if the advice or information is written—give a copy of it to the parties; or(b)if the advice or information is oral—disclose the substance of the advice to the parties.
90 Parties to maintain secrecy of advice or information
(1)This section applies if under section 89(4) QCA gives advice or information, or discloses the substance of advice or information, to a person who is a party to the dispute.(2)The person must not disclose the advice or information to another person unless the person has a reasonable excuse.Maximum penalty—20 penalty units.
(3)It is a reasonable excuse for a person to disclose the advice or information if the disclosure is for—(a)the resolution of the dispute; or(b)an external review of QCA’s decision on the dispute.
Part 5 [Repealed]
91 [Repealed]
Part 6 Electricity restrictions
Division 1 Preliminary
92 Purpose of pt 6
The purpose of this part is ensure a regular, economically efficient and constant supply of electricity within the available supply capacity of particular supply networks, or parts of them.
Division 2 Restrictions in Ergon Energy distribution area
93 Where restrictions apply
The electricity restrictions under section 94 apply to electricity supplied by Ergon Energy in the localities mentioned in schedule 1 through its supply network.
94 Restrictions
(1)The use of the following electrical articles by customers is prohibited—(a)electric motors with a rating greater than—(i)the rating stated for the relevant locality in schedule 1; and(ii)if the motor is not installed and operated in accordance with the guidelines published by Ergon Energy—1.5kW;Editor’s note—
The guidelines are available from the Ergon Energy offices at 109 Lake Street, Cairns, 34–46 Dalrymple Road, Garbutt, Townsville and the corner of Fitzroy Street and Alma Street, Rockhampton.(b)instantaneous water heaters with a rating of more than 2.4kW;(c)welding power sources.(2)Subsection (1) does not apply—(a)to the following welding power sources—(i)415V, 3-phase input light industrial welding power sources;(ii)250V, single-phase limited input welding power sources; or(b)to electric motors that are part of a public water supply system or a community sewerage system installed and operated in the way required by Ergon Energy; or(c)to electrical articles at Mapoon installed before 1 December 1998; or(d)if the customer satisfies Ergon Energy, by the written advice of a doctor, that a stated electrical article must be used to reduce a threat to a person’s life.(3)In this section—instantaneous water heater means an instantaneous water heater described in—(a)AS/NZS 3350.2.35:1999—Safety of household and similar electrical appliances, part 2.35—Particular requirements— Instantaneous water heaters; or(b)AS/NZS 60335.2.35:2004—Household and similar electrical appliances—Safety, part 2.35—Particular requirements for instantaneous water heaters.welding power source means an electric arc welding power source that has—(a)a transformer for alternating current welding; or(b)a transformer-rectifier unit for direct current, or alternating current and direct current, welding.
Part 7 [Repealed]
Division 1 [Repealed]
95 [Repealed]
96 [Repealed]
97 [Repealed]
98 [Repealed]
99 [Repealed]
100 [Repealed]
101 [Repealed]
102 [Repealed]
103 [Repealed]
Division 2 [Repealed]
104 [Repealed]
105 [Repealed]
106 [Repealed]
107 [Repealed]
Division 3 [Repealed]
108 [Repealed]
109 [Repealed]
110 [Repealed]
111 [Repealed]
112 [Repealed]
Division 4 [Repealed]
113 [Repealed]
114 [Repealed]
115 [Repealed]
116 [Repealed]
Division 5 [Repealed]
117 [Repealed]
Chapter 4 Market and system arrangements
Part 1 System and network control
Division 1 Operating electrical installations
118 National Electricity Rules to be followed
A person must comply with the National Electricity Rules in operating an electrical installation if the installation—(a)is connected directly to a transmission grid that is part of the Queensland system; or
(b)is connected to a part of a supply network stated by AEMO or the System Operator for Queensland to be relevant to the security and reliability of the Queensland system; or(c)includes facilities for the provision of ancillary services stated by AEMO or the System Operator for Queensland to be relevant to the security and reliability or the economic operation of the Queensland system.Maximum penalty—20 penalty units.
Division 2 Network control
119 Network operation not to interfere with Queensland system
(1)A distribution entity must not operate its supply network in a way that interferes with the performance of the Queensland system without the agreement of AEMO or the System Operator for Queensland.Maximum penalty—20 penalty units.
(2)In this section—operate includes providing network control.
120 National Electricity Rules to be followed
A person must comply with the National Electricity Rules in operating an electrical installation if the installation—(a)is connected directly to a supply network that is part of the Queensland system; or(b)includes facilities for the provision of ancillary services to the supply network.Maximum penalty—20 penalty units.
121 Dealings to be impartial
An electricity entity, in carrying out network control, must be impartial in its dealings with all other electricity entities, special approval holders and customers.
122 Confidentiality
(1)An electricity entity may publish or release to a person information acquired by the entity in carrying out network control, and that gives or is likely to give the person a material commercial advantage over anyone else, only if—(a)the giving of the information is for another lawful purpose; and(b)any commercial advantage is only incidental to the purpose.(2)Subsection (1) does not apply to the giving to a person information about—(a)the person; or(b)with another person’s written permission, the other person.
123 Reasonable charges for services
An electricity entity may charge customers for the reasonable cost of carrying out its network control functions.
Part 2 Conditions of authorities and special approvals
Division 1 General provisions
124 Separation of distribution and retail sectors
It is a condition of a distribution authority that its holder must not hold a retailer authorisation.
125 Compliance with National Electricity Rules instruments
(1)This section applies to the holder of an authority or special approval if the holder is a Registered participant.(2)It is a condition of an authority or special approval that its holder must comply with any National Electricity Rules instrument applying to the activities authorised by the authority or special approval.(3)In this section—authority means a generation authority, transmission authority or distribution authority.National Electricity Rules instrument means a guideline, power system operating procedure or other procedure, protocol or standard made under the Rules.
125A [Repealed]
126 [Repealed]
127 Prescribed special approval holder—Act, s 61B
Essential Energy, in relation to special approval no. SA01/11, is prescribed for the Act, section 61B.
Division 2 Demand management plans
127A Definitions for div 2
In this division—approved demand management plan means a demand management plan approved by the regulator under this division.demand management, by a distribution entity, means any activity in which the entity is involved that reduces demand on the entity’s supply network or part of the supply network.demand management plan, for a financial year, means a plan for the year that complies with section 127C(2).strategy see section 127C(2)(a).
127B Condition of distribution authority
It is a condition of a distribution authority that its holder must comply with this division.
127C Preparing demand management plan
(1)A distribution entity must, for each financial year, prepare a demand management plan.(2)The distribution entity must include in the plan—(a)the entity’s long-term strategy for demand management (the strategy), including the following—(i)the principles intended to guide the achievement of the strategy;(ii)a description of existing and planned programs for demand management for the next 5 financial years;(iii)any identified opportunities to achieve the strategy; and(b)the entity’s proposed initiatives to be carried out under the strategy in the financial year, including the following—(i)a description of the initiative;(ii)a forecast of the capital and operating costs for the initiative that the entity reasonably considers will be the likely costs for the year;(iii)the entity’s performance targets for the initiative.(3)Subsection (2) does not limit the matters that may be included in the plan.(4)The distribution entity must, on or before each 30 April in the preceding financial year, give the regulator a copy of the entity’s plan for the financial year.
127D Approving demand management plan
The regulator must, on or before 31 May in the preceding financial year—(a)approve the distribution entity’s demand management plan for the financial year; or(b)make recommendations under section 127E(1) to amend the plan.
127E Recommendations by regulator
(1)Before approving the distribution entity’s demand management plan for a financial year, the regulator may—(a)return the plan to the entity; and(b)make recommendations to amend the plan by asking the entity to—(i)consider or further consider any matter; and(ii)amend the plan in the light of its consideration or further consideration.(2)The distribution entity must comply with a request under subsection (1)(b).(3)If the distribution entity does not implement any or all of the regulator’s recommendations, the entity must give the regulator written reasons for not implementing the recommendations.(4)The distribution entity must give a copy of the plan to the regulator for approval.(5)The plan takes effect as the distribution entity’s approved demand management plan for the financial year only when it is approved by the regulator.
127F Amending approved demand management plan
(1)The distribution entity may, at any time in a financial year, amend its approved demand management plan for the year.(2)However, the plan may be amended only if a change in circumstances happens that indicates the carrying out of a proposed initiative, or the carrying out of a proposed initiative in the way described in the plan, is no longer feasible or practical to achieve the entity’s strategy.(3)If, in amending the plan, a proposed initiative, or the way a proposed initiative is to be carried out under the plan, is not changed, the entity’s performance targets for the proposed initiative must not be changed in the amended plan.(4)The distribution entity must give the regulator a copy of the amended plan.(5)The plan, as amended, takes effect as the distribution entity’s approved demand management plan for the financial year only when it is approved by the regulator.
127G Complying with approved demand management plan
The distribution entity must use its best endeavours to comply with its approved demand management plan.
127H Reporting requirements
(1)The distribution entity must, for each financial year, prepare a report comparing details of the following—(a)the proposed initiatives stated in the entity’s approved demand management plan for the year;(b)the actual initiatives the entity carried out in the year.(2)The distribution entity must give the regulator a copy of the report on or before 31 August in the following financial year.
Part 3 Special approvals
128 Approval to connect for generation plant of particular State electricity entities installed immediately before 1 January 1995
(1)Ergon Energy has a special approval authorising it to connect the generating plant installed before 1 January 1995 and vested in Capricornia Electricity Corporation, Far North Queensland Electricity Corporation or North Queensland Electricity Corporation as at 1 January 1995 to the transmission grid or supply network to which the generating plant was connected on 1 January 1995.(2)Section 27(a) and (c) of the Act applies to Ergon Energy acting under the special approval as if it were a generation entity.
129 Approval to connect for mobile generating plant for emergency or maintenance work by distribution entities
(1)A distribution entity has a special approval to connect mobile generating plant to its supply network to supply electricity during an emergency or maintenance work on the supply network.(2)Section 27(a) and (c) of the Act applies to a distribution entity acting under the special approval as if the supplier were a generation entity.
130 Approval to connect particular generating plant with 30MW or less capacity
(1)A person who operates generating plant with a capacity of 30MW or less has a special approval to connect the generating plant to a transmission grid or supply network.(2)Section 27(a) and (c) of the Act applies to the person acting under the special approval as if the person were a generation entity.
131 Special approval holders treated as electricity entities—Act, s 59(2)
(1)A special approval holder stated in schedule 3, column 1, is to be treated as an electricity entity for the provisions of the Act stated in schedule 3, column 2, opposite the special approval holder.(2)To remove any doubt, it is declared that if a special approval holder is mentioned in more than 1 item in schedule 3, each of the items in which the holder is mentioned applies to the holder.
132 Special approval for QETC
QETC has a special approval to generate electricity for a purpose or function mentioned in section 33(2) of the Act.
Chapter 5 Prohibited interests
133 Distribution authorities
Holding a retailer authorisation is a prohibited interest for a distribution entity.
Chapter 6 [Repealed]
Part 1 [Repealed]
134 [Repealed]
134A [Repealed]
135 [Repealed]
Part 2 [Repealed]
136 [Repealed]
137 [Repealed]
Chapter 7 Energy efficiency and performance of electrical equipment
Part 1 Minimum energy efficiency and performance
Division 1 Registration
138 Application for registration
(1)An application for registration of an item of prescribed electrical equipment must be made to the regulator in the approved form, or if there is no approved form, a form acceptable to the regulator.(2)The application must be accompanied by each of the following—(a)subject to subsection (7), the prescribed fee;(b)the test results and calculations mentioned in the relevant standard;(c)the other test results mentioned in the relevant standard, in the form for the results set out in the standard;(d)for an item mentioned in schedule 4, part 1—a sample of a label for the item;(e)for an item mentioned in schedule 4, part 3, that is to be labelled—a sample of a label for the item;(f)if required by the regulator, a sample of the equipment;(g)any other relevant information the regulator requires to decide the application.(3)The application may specify a range of models of the 1 brand in the same application if each of the models has the same relevant physical characteristics, energy efficiency and performance characteristics.(4)If a person other than the applicant signs the application, the application must be accompanied by the applicant’s written authority for the person to sign the application.(5)If the application is made by electronic communication, subsection (4) is taken to be complied with if—(a)a method is used to identify the applicant and to indicate the applicant’s authority; and(b)having regard to all the relevant circumstances when the method was used, the method was as reliable as was appropriate for the purposes for which the authority was communicated; and(c)the regulator consents to the requirement being met by using the method mentioned in paragraph (a).(6)The regulator may waive the requirement under subsection (2)(b) and (c).(7)If the application is made by electronic communication, the applicant must give the regulator the prescribed fee for the application before the regulator can register the item of prescribed electrical equipment.(8)If the application is made by electronic communication, the regulator—(a)may decide the application; but(b)can not register the item the subject of the application until the prescribed fee is paid.
139 Requirements for registration
(1)The regulator may register an item of prescribed electrical equipment only if the regulator considers—(a)the item complies with section 140; and(b)for equipment mentioned in schedule 4, part 1—the equipment’s label complies with section 152; and(c)for equipment mentioned in schedule 4, part 3, that is to be labelled—the equipment’s label complies with section 152.(2)If the regulator refuses to register the item, the regulator must give the applicant a QCAT information notice about the refusal.
140 Minimum energy efficiency and performance criteria
(1)This section states the requirements an item of prescribed electrical equipment must comply with for section 139(1)(a).(2)An item of prescribed electrical equipment mentioned in schedule 4, part 1 or 3, must, if tested in accordance with part 1 of the relevant standard, comply with the performance criteria for the item in the relevant standard.(3)An item of prescribed electrical equipment mentioned in schedule 4, part 2, must comply with the energy efficiency requirements for the item in the relevant standard.
141 Steps after registration
(1)Within 28 days after registering an item of prescribed electrical equipment, the regulator must—(a)fix the item’s maximum registration term; and(b)give the applicant a written notice stating the item’s date of registration and maximum registration term.(2)The maximum registration term can not be more than 5 years from the date of registration.(3)If the regulator decides to fix the maximum registration term at less than 5 years and the applicant has not agreed to the term, the written notice must include, or be accompanied by, a QCAT information notice about the decision.
142 Term of registration
(1)Registration of an item of prescribed electrical equipment continues in force until the earliest of the following to happen—(a)the end of the item’s maximum registration term;(b)the expiry of the relevant standard for the item;(c)the relevant standard for the item is amended and, under the amended standard, the item does not comply with the performance requirements or energy efficiency requirements for the item.(2)Subsection (1) is subject to section 149.
143 Change of name or address
(1)The holder of a registration of an item of prescribed electrical equipment whose name or address changes must, within 14 days after the change, give written notice of it to the regulator.Maximum penalty—8 penalty units.
(2)The regulator must enter details of the new name or address in the register.
144 Changing energy efficiency label identifying electrical equipment
(1)The holder of a registration of an item of prescribed electrical equipment with an energy efficiency label may apply to the regulator for approval of a change to the label to reflect a change in the way an item of electrical equipment of the type to which the label relates is identified.(2)The regulator may approve the change if the application—(a)is made in the approved form; and(b)is accompanied by—(i)subject to subsection (3), the prescribed fee; and(ii)a sample of the changed energy efficiency label.(3)If the application is made by electronic communication, the applicant must give the regulator the prescribed fee for the application before the regulator can approve the change.
145 Refusal to change energy efficiency label
If the regulator refuses to approve a change to an energy efficiency label for which an application is made, the regulator must give the applicant a QCAT information notice about the refusal.
146 Notice of change to energy efficiency label
Within 28 days after approving a change to an energy efficiency label, the regulator must give written notice of the change to the holder of the label.
146A Request for documents or information confirming compliance with relevant standard
(1)This section applies to the holder of a registration of an item of prescribed electrical equipment.(2)The regulator may, by written notice given to the holder, require the holder to give the regulator the documents or information that the holder has about whether the item continues to comply with the requirements under section 139 for the registration of the item.(3)The notice must state a period of at least 15 business days within which the holder must comply with the requirement.(4)The holder must comply with the requirement.Maximum penalty for subsection (4)—20 penalty units.
Division 2 Transfer and cancellation of registration
147 Transfer of registration
(1)If the holder of a registration of an item of prescribed electrical equipment proposes to transfer the registration to someone else (the proposed transferee), the proposed transferee may apply to the regulator for approval of the transfer.(2)The regulator must approve the transfer if the application—(a)is made in the approved form; and(b)is accompanied by—(i)subject to subsection (4), the prescribed fee; and(ii)the holder’s written agreement to the transfer.(3)If the regulator refuses to approve the transfer, the regulator must give the applicant a QCAT information notice about the refusal.(4)If the application is made by electronic communication, the applicant must give the regulator the prescribed fee for the application before the regulator can approve the change.
148 Notice of transfer
Within 28 days after approving the transfer, the regulator must give written notice of the transfer to the proposed transferee and the former holder of the registration.
149 Cancellation of registration
(1)The regulator may, subject to section 150, cancel the registration of an item of prescribed electrical equipment if—(a)the regulator considers that, because of an examination or test carried out on the item by the regulator or an approved testing entity, it does not comply with the relevant standard; or(b)the holder of the registration engages in conduct likely to mislead the public about the performance, rating, capacity or the characteristics of the item required by the relevant standard; or(c)the holder gave the regulator false or misleading information about the application for registration, or transfer of registration, of the item; or(d)the holder asks for the cancellation.(2)If registration of an item (the primary item) of prescribed electrical equipment is cancelled, the regulator may also cancel the registration of any other item of prescribed electrical equipment that the regulator is satisfied—(a)has the same relevant physical characteristics, energy efficiency and performance characteristics as the primary item; and(b)was registered on the basis of the same test results as the test results for the primary item.(3)If the regulator decides to cancel the registration, the regulator must give the holder a QCAT information notice about the decision.
150 Procedure before cancellation
(1)If the regulator considers a ground exists to cancel the registration of an item of prescribed electrical equipment, other than at the request of the registration holder, the regulator must, before taking the action, give the holder written notice—(a)stating the regulator is considering cancelling the registration; and(b)stating the grounds for the proposed cancellation; and(c)outlining the facts and circumstances forming the basis for the grounds; and(d)inviting the holder to show, within a stated time of at least 15 business days, why the registration should not be cancelled.(2)If, after considering all written representations made by the holder within the stated time, the regulator still considers a ground exists to cancel the registration, the regulator may cancel the registration.(3)Cancellation of the registration takes effect on the sixth business day after the holder is given a QCAT information notice under section 149(3).
151 Notice, by holder, of cancellation of registration
(1)Immediately on receipt of a QCAT information notice about cancellation of the registration of an item of prescribed electrical equipment, the holder of the registration must give written notice of the cancellation to each person to whom the holder has sold an item of the type that was registered.(2)Subsection (1) does not require the giving of a notice to a person to whom the type of item had been sold by retail or had been sold at least 1 year before the notice was received.
Division 3 Energy efficiency label
152 Energy efficiency label
(1)An energy efficiency label for an item of prescribed electrical equipment mentioned in schedule 4, part 1 or 3, must—(a)comply with the labelling requirements of the relevant standard for the item; and(b)not contain any figures, symbols or other words likely to mislead the public about the item’s comparative energy consumption, energy efficiency rating or performance characteristics; and(c)if the item is sold—accompany the item.(2)If the item is displayed for sale, the energy efficiency label for the item must—(a)be attached to the item—(i)in the way shown in the relevant standard; or(ii)in another way approved by the regulator; and(b)not be attached in a way that it is obscured from view.Note—
See part 3 (Offences) for when equipment must be labelled.
Division 4 Register
153 Register
(1)The regulator must keep a register of each item of prescribed electrical equipment registered by the regulator.(2)The regulator may enter in the register any particulars contained in an application for registration, or transfer of registration, of the item.(3)The register may be kept in a way the regulator considers appropriate.(4)The register may form part of a national register.
154 Inspection of register
The regulator must—(a)keep the register open for inspection, on payment of the prescribed fee, by members of the public during office hours on business days; and(b)on payment of the prescribed fee, give the person a copy of an entry in the register.
Part 2 Testing and test reports
Division 1 Preliminary
155 Testing of prescribed electrical equipment
(1)An item of prescribed electrical equipment mentioned in schedule 4, part 1 or 3, must be tested under this part in accordance with part 1 of the relevant standard to find out whether it complies with the performance criteria in the relevant standard.(2)An item of prescribed electrical equipment mentioned in schedule 4, part 2, item 1, must be tested under this part to find out whether it complies with the energy efficiency requirements in the relevant standard.(3)An item of prescribed electrical equipment mentioned in schedule 4, part 2, item 2, must be tested under this part in accordance with part 102.3 of the relevant standard to find out whether it complies with the minimum energy performance requirements in part 5 of the relevant standard.(4)An item of prescribed electrical equipment mentioned in schedule 4, part 2, items 3 to 18, must be tested under this part to find out whether it complies with the minimum energy performance requirements in the relevant standard for the item.(5)The testing may be done only by an approved testing entity.
156 Test reports
(1)The results of the test must be recorded in a test report.(2)The test report must be in the approved form, or if there is no approved form, a form acceptable to the regulator, and contain the following information about the test—(a)the provision of this regulation under which the testing was conducted;(b)the name of the entity that conducted the test;(c)the date of the test;(d)the date of the report;(e)the results of the test, in the form set out in the relevant standard;(f)other information required to be included in the report under this part.
Division 2 Check testing
157 Requirement by regulator to make available prescribed electrical equipment for testing
(1)The regulator may, by written notice given to the holder of the registration of an item of prescribed electrical equipment, require the holder to make an item of the type registered available for the testing (check testing) mentioned in section 155.(2)The requirement must state—(a)the period, of at least 1 month from the giving of the requirement, within which the item must be made available; and(b)the place where the item is to be made available; and(c)an amount estimated to cover the actual, reasonable cost of the check testing and when it is to be paid to the regulator.(3)The holder must make the item available and pay the amount as stated in the requirement.
158 What happens if check testing shows noncompliance
(1)This section applies if a check test shows that an item of prescribed electrical equipment does not comply with a performance criteria or energy efficiency requirement of the relevant standard.(2)If the actual cost of testing the item is greater than the amount paid under section 157(3) for the check test, the difference may be recovered by the regulator from the holder as a debt owing to the State.(3)This section does not affect section 149.
159 What happens if check testing shows compliance
(1)This section applies if a check test shows that an item of prescribed electrical equipment complies with the performance criteria or energy efficiency requirements of the relevant standard.(2)The regulator must refund to the holder the amount paid under section 157(3) for the check test.(3)The amount may be recovered by the holder from the regulator as a debt owing by the State to the holder.
160 Return of equipment made available to the regulator
(1)This section applies if, at the regulator’s request, a person makes available to the regulator free of charge an item of prescribed electrical equipment for testing or with an application under this chapter.(2)The regulator must give the person written or oral notice that the equipment is available for collection by the person at a stated place as soon as practicable after—(a)for an item made available for testing—(i)if the regulator believes, on reasonable grounds, that the item is required as evidence in a prosecution for an offence—the prosecution and any appeal from the prosecution; or(ii)if subparagraph (i) does not apply—the testing; or(b)for an item made available with an application—the regulator decides the application.(3)Despite subsection (2)(a)(i), the regulator must give the person written or oral notice immediately after the earlier of the following—(a)the regulator decides the equipment is not required as evidence;(b)a prosecution for an offence involving the type of equipment is not started within 6 months from when the notice would have been given if subsection (2)(a)(i) had not applied.(4)If, at the end of 6 months after the notice is given, the equipment has not been collected, the regulator may dispose of the item as the regulator considers appropriate and the person is not entitled to claim for the appliance or any loss or damage to it.
Part 3 Offences
161 Part does not apply to second-hand prescribed electrical equipment
This part does not apply to a second-hand item of prescribed electrical equipment.
162 Prescribed electrical equipment in sch 4, pt 1—labelling and registration
(1)A person must not display for sale or sell an item (the sale item) of prescribed electrical equipment mentioned in schedule 4, part 1, unless—(a)an item of the same type of prescribed electrical equipment as the sale item (an alike item)—(i)is registered under section 139; or(ii)was registered under that section at the time when the sale item was manufactured in or imported into the State (the relevant time); or(iii)was registered under a corresponding law at the relevant time; and(b)an energy efficiency label that complies with section 152 is attached to or accompanies the item in the way required by that section.Maximum penalty—20 penalty units.
(2)Subsection (1) does not apply if—(a)the sale item is registered under a corresponding law; and(b)an energy efficiency label is attached to or accompanies the sale item and the label complies with, and is attached or accompanies the item, in the way required by the corresponding law.(3)Also, subsection (1) does not apply if—(a)an alike item was registered under section 139 at the relevant time and—(i)an energy efficiency label is attached to or accompanies the sale item; and(ii)the label complies with section 152 in the way required by the relevant standard as it was in force at that time; or(b)an alike item was registered under a corresponding law at the relevant time and—(i)an energy efficiency label is attached to or accompanies the sale item; and(ii)the label complies with the corresponding law as it was in force at that time; or(c)an alike item was not mentioned in schedule 4, part 1 as it was in force at the relevant time.
163 Prescribed electrical equipment in sch 4, pt 2—registration
A person must not sell an item (the sale item) of prescribed electrical equipment mentioned in schedule 4, part 2, unless an item of the same type of prescribed electrical equipment as the sale item—(a)is registered under section 139; or(b)was registered under that section at the time when the sale item was manufactured in or imported into the State (the relevant time); or(c)was registered under a corresponding law at the relevant time; or(d)was not mentioned in schedule 4, part 2 as it was in force at the relevant time.Maximum penalty—20 penalty units.
164 Prescribed electrical equipment in sch 4, pt 3—registration
(1)A person must not sell an item (the sale item) of prescribed electrical equipment mentioned in schedule 4, part 3, unless—(a)an item of the same type of prescribed electrical equipment as the sale item (an alike item)—(i)is registered under section 139; or(ii)was registered under that section at the time when the sale item was manufactured in or imported into the State (the relevant time); or(iii)was registered under a corresponding law at the relevant time; and(b)if an energy efficiency label is attached to or accompanies the sale item—the label complies with, and is attached to or accompanies the item in the way required by, section 152.Maximum penalty—20 penalty units.
(2)Subsection (1) does not apply if—(a)the sale item is registered under a corresponding law; and(b)if an energy efficiency label is attached to or accompanies the sale item—the label complies with, and is attached to or accompanies the item in the way required by, the corresponding law.(3)Also, subsection (1) does not apply if—(a)an alike item was registered under section 139 at the relevant time and any energy efficiency label attached to or accompanying the sale item complies with section 152 in the way required by the relevant standard as it was in force at that time; or(b)an alike item was registered under a corresponding law at the relevant time and any energy efficiency label attached to or accompanying the sale item complies with that law as it was in force at the relevant time; or(c)an alike item was not mentioned in schedule 4, part 3 as it was in force at the relevant time.
165 Representations about 3-phase cage induction motors
A person must not represent that a 3-phase cage induction motor mentioned in schedule 4, part 2, item 2, is a high efficiency motor unless the motor complies with the high efficiency performance requirements for the item in part 5 of the relevant standard.Maximum penalty—20 penalty units.
165A Representations about digital television set-top boxes
A person must not represent that a digital television set-top box mentioned in schedule 4, part 2, item 6, is a high efficiency set-top box unless it complies with the high efficiency performance requirements for the item in section 3 of the relevant standard.Maximum penalty—20 penalty units.
165B Representations about external power supplies
A person must not represent that an external power supply mentioned in schedule 4, part 2, item 7, is a high efficiency power supply unless it complies with the high efficiency performance requirements for the item in section 3 of the relevant standard.Maximum penalty—20 penalty units.
166 Marking and labelling particular fluorescent lamp ballasts
(1)This section applies to a fluorescent lamp ballast, other than a ballast to which the standard mentioned in schedule 4, part 1, item 6, applies.(2)A person must not mark the ballast with an energy efficiency label unless the label—(a)complies with the labelling requirements of the standard mentioned in subsection (1); and(b)is marked on the ballast in the way shown in the standard.Maximum penalty—20 penalty units.
(3)If an energy efficiency label is marked on the ballast, a person must not sell the ballast unless it conforms with the energy efficiency rating shown on the label.Maximum penalty—20 penalty units.
166A [Repealed]
Chapter 8 Employment in government owned electricity industry
Part 1 Preliminary
167 Definitions for ch 8
In this chapter—employment entitlement, of an employee, means each of the following—(a)the employee’s leave entitlement;(b)the period of service that would be relevant for working out the redundancy payment to which the employee would be entitled if the employee was made redundant.future employer see section 168(2)(d).previous employer see section 168(2)(a).redundancy payment means a payment made to a person because the person became redundant.redundant see section 168(1).redundant employee see section 168(2).State electricity entity includes an entity declared to be a State electricity entity under section 224.suitable alternative employment see section 169.
168 Meaning of redundant and redundant employee
(1)An employee becomes redundant if the person’s employer no longer needs or has a substantially diminished need for services of a particular kind performed by the person.(2)A person is a redundant employee if—(a)the person was employed by a State electricity entity (the previous employer); and(b)the person’s employment ended because the person was redundant; and(c)the person has received, or is eligible to receive, a redundancy payment from the previous employer; and(d)the person has not been offered suitable alternative employment by the previous employer or another State electricity entity (each a future employer).
169 Meaning of suitable alternative employment
(1)Alternative employment offered to a person by a future employer is suitable alternative employment only if the following conditions are satisfied—(a)the person’s employment entitlements are continued under the alternative employment;(b)either—(i)the person and the previous employer have agreed the alternative employment is the same or substantially the same as the person’s previous employment with the employer; or(ii)the Industrial Relations Commission has decided the alternative employment is the same or substantially the same as the person’s previous employment;(c)if, on the offer day, the person is a member of a superannuation scheme and the future employer is a subsidiary of a GOC—(i)the person’s membership in the scheme is not affected; and(ii)the employer makes, or agrees to make, the superannuation contributions the employer is required to make for the person to the scheme for the benefit of the person.(2)Subsection (1)(c) does not apply if the person and future employer enter into an agreement about the superannuation arrangements for the person.(3)In this section—offer day, for a person to whom alternative employment is offered, means the day the alternative employment is offered to the person.
170 Industrial Relations Commission may decide particular matters
If a person and the person’s previous employer can not agree, after genuinely attempting to come to an agreement, whether alternative employment offered to the person is the same or substantially the same as the person’s previous employment with the employer—(a)the person and employer must—(i)treat the disagreement as an industrial dispute; and(ii)immediately give the registrar under the Industrial Relations Act a notice complying with section 229(3) of that Act for the dispute; and(b)chapter 7, part 2, of the Industrial Relations Act applies to the disagreement as if—(i)the disagreement were an industrial dispute; and(ii)the notice given under paragraph (a)(ii) were given under section 229(2) of that Act; and(c)without limiting section 230(3) and (4) of the Industrial Relations Act, the Industrial Relations Commission may decide whether or not the alternative employment is the same or substantially the same as the person’s previous employment.
Part 2 General employment conditions and entitlements
171 Definitions for pt 2
In this part—EGTS award means the Electricity Generation Transmission and Supply Award—State.industrial instrument means an industrial instrument under the Industrial Relations Act.
172 EGTS award is binding
The EGTS award binds a State electricity entity and each of its electricity industry employees.
173 Secondment does not affect employment in the GOE industry
A person employed by a State electricity entity is taken, while performing duties on secondment to another entity, to continue to be employed by the State electricity entity.
174 Continuous service
If an employee works, takes authorised leave, or is paid for an absence under the Workers’ Compensation and Rehabilitation Act 2003 for an injury sustained by the employee, a period when the employee is or would be rostered for work is a period of continuous service by the employee.Examples of continuous service—
1A full-time employee has a fortnight of continuous service, even though a rostered day off is taken in the fortnight.2A part-time employee has a fortnight of continuous service if the employee works the days rostered for the employee in the fortnight.
175 Calculation at a proportionate rate for particular employee
(1)If this chapter provides, for a part-time employee, a quantity or amount (the proportionate amount) to be a proportion of another quantity or amount relating to a full-time employee (the regular amount), the proportionate amount must be worked out as follows—(2)In subsection (1)—work hours means the period (in hours and, if necessary, a fraction of an hour) for which the part-time employee is scheduled to work.
176 Chapter 8 prevails over industrial instruments
If there is any inconsistency between this chapter and the EGTS award or another industrial instrument that applies to electricity industry employees of State electricity entities, this chapter prevails to the extent of the inconsistency.
Part 3 Transfer of employment within GOE industry
177 Application of pt 3
This part applies to a person who transfers employment within the GOE industry (the transferred employee).
178 When there is transfer of employment within GOE industry
(1)In this part, a person employed in the GOE industry transfers employment within the GOE industry if the person resigns from employment with a State electricity entity (the former employer) to be employed by another State electricity entity (the new employer).(2)For subsection (1), a person does not resign from employment with a State electricity entity if the person becomes a redundant employee for the entity.(3)The transfer is effective when the employee starts employment with the new employer (the transfer day).
179 When employment with former employer and new employer is taken to be continuous service
(1)This section applies if the transfer day is no more than 1 month after the transferred employee ends employment with the former employer.(2)To decide employment entitlements of the transferred employee as an employee of the new employer—(a)the employee’s continuous service in the GOE industry immediately before ending employment with the former employer is taken to be service continuous with service with the new employer from the transfer day; and(b)the employee’s leave entitlement is reduced by leave accrued (or a pro rata amount for leave not yet accrued) during the service and taken or paid for by an employer of the employee.
For clauses 9.32.1(a)(2) and 9.34.4(b) of the National Electricity Rules, a contestable customer is prescribed to be any customer other than an excluded customer.
Division 3 Transitional provision for Electricity Amendment Regulation (No. 4) 2007
239 Provision for new s 142
(1)New section 142 applies to an item of prescribed electrical equipment whether the item was registered before or after new section 142 commenced.(2)If the item was registered before new section 142 commenced, its maximum registration term is taken to be the term of registration stated in the notice of registration under section 141 as it was in force before the commencement.(3)In this section—new section 142 means section 142 as replaced under the Electricity Amendment Regulation (No. 4) 2007.
Division 4 Transitional provision for Electricity Amendment Regulation (No. 1) 2009
240 Demand management plans for 2009 financial year
(1)Section 127C(4) applies to a relevant plan as if the reference to each 30 April in the preceding financial year were a reference to 6 July 2009.(2)Section 127D applies to a relevant plan as if the reference to 31 May in the preceding financial year were a reference to 6 August 2009.(3)In this section—relevant plan means a distribution entity’s demand management plan for the financial year starting on 1 July 2009.
Schedule 1 Maximum permitted rating of electric motors
sections 93 and 94(1)
Locality | Maximum rating |
Aurukun | 16kW |
Badu Island | 13kW |
Bamaga | 46kW |
Boigu Island | 10kW |
Boulia | 16kW |
Burketown | 16kW |
Camooweal | 16kW |
Coconut Island | 10kW |
Coen | 13kW |
Darnley Island | 8kW |
Dauan Island | 7kW |
Doomadgee | 37kW |
Gununa | 37kW |
Hammond Island | 5kW |
Kowanyama | 37kW |
Lockhart River | 16kW |
Mabuiag Island | 7kW |
Mapoon | 12kW |
Moa Island (Kubin and St Pauls communities) | 10kW |
Murray Island | 13kW |
Palm Island | 38kW |
Pormpuraaw | 16kW |
Saibai Island | 8kW |
Stephens Island | 4kW |
Warraber Island | 7kW |
Wasaga | 37kW |
Yam Island | 10kW |
Yorke Island | 10kW |
Schedule 2 [Repealed]
Schedule 3 Special approval holders treated as electricity entities
section 131
Column 1 Special approval holder | Column 2 Provisions of Act | |
1 | the holder of a special approval authorising the holder to provide electricity to a customer | chapter 2, part 2 |
2 | each holder for the time being of special approval no. SA01/07 authorising the operation of an electric line | 116A |
3 | the holder of any special approval | section 120 chapter 5, part 4 |
4 | Essential Energy, under special approval no. SA01/11 | section 131A |
5 | RTA Weipa Pty Ltd, under special approval no. SA18/98 | chapter 2, part 9 |
Schedule 4 Prescribed electrical equipment and relevant standards
schedule 9, definitions prescribed electrical equipment and relevant standard
Part 1 Equipment requiring registration and labelling
Prescribed electrical equipment | Relevant standard | |
1 | clothes washing machines | AS/NZS 2040—Performance of household electrical appliances—clothes washing machines, part 1 Methods for measuring performance, energy and water consumption and part 2 Energy efficiency labelling requirements |
2 | dishwashers | AS/NZS 2007—Performance of household electrical appliances—dishwashers, part 1 Methods for measuring performance, energy and water consumption and part 2 Energy efficiency labelling requirements |
3 | refrigerating appliances | AS/NZS 4474—Performance of household electrical appliances—refrigerating appliances, part 1 Energy consumption and performance and part 2 Energy labelling and minimum energy performance standard requirements |
4 | single-phase non-ducted household air conditioners and heat pumps | AS/NZS 3823—Performance of electrical appliances—Air conditioners and heat pumps, part 2 Energy labelling and minimum energy performance standard (MEPS) requirements |
5 | rotary clothes dryers | AS/NZS 2442—Performance of household electrical appliances—Rotary clothes dryers, part 1 Energy consumption and performance and part 2 Energy labelling requirements |
6 | fluorescent lamp ballasts | AS/NZS 4783—Performance of electrical lighting equipment—Ballasts for fluorescent lamps, part 1 Method of measurement to determine energy consumption and performance of ballasts lamp circuits, and part 2 Energy labelling and minimum energy performance standards requirements |
7 | televisions | AS/NZS 62087—Power consumption of audio, video and related equipment, part 2.2 Minimum energy performance standards (MEPS) and energy rating label requirements for television sets |
Part 2 Equipment requiring registration only
Prescribed electrical equipment | Relevant standard | |
1 | storage water heaters and heat exchange water heaters | AS/NZS 4692—Electric water heaters, part 1 Energy consumption, performance and general requirements and part 2 Minimum energy performance standard (MEPS) requirements and energy labelling |
2 | 3-phase cage induction motors | AS/NZS 1359—Rotating electrical machines—General requirements, part 5 High efficiency and minimum energy performance standards requirements |
3 | double-capped fluorescent lamps | AS/NZS 4782—Double-capped fluorescent lamps—Performance specifications, part 1 General and part 2 Minimum energy performance standard (MEPS) |
4 | refrigerated display cabinets | AS 1731—Refrigerated display cabinets, part 1 Terms and definitions and part 14 Minimum energy performance standard (MEPS) requirements |
5 | power transformers | AS 2374—Power transformers, part 1 General and part 1.2 Minimum energy performance standard (MEPS) requirements for distribution transformers |
6 | digital television set-top boxes | AS/NZS 62087—Power consumption of audio, video and related equipment, part 2.1 Minimum energy performance standards (MEPS) requirements for digital television set-top boxes |
7 | external power supplies | AS/NZS 4665—Performance of external power supplies, part 2 Minimum energy performance standard (MEPS) requirements |
8 | liquid-chilling packages | AS/NZS 4776—Liquid-chilling packages using the vapour compression cycle, part 2 Minimum energy performance standard (MEPS) and compliance requirements |
9 | close control air conditioners | AS/NZS 4965—Performance of close control air conditioners, part 2 Minimum energy performance standard (MEPS) requirements |
10 | incandescent general lighting service lamps | AS 4934.2—Incandescent lamps for general lighting services, part 2 Minimum energy performance standards (MEPS) requirements |
11 | extra low voltage halogen lamps (non-reflector) | AS 4934.2—Incandescent lamps for general lighting services, part 2 Minimum energy performance standards (MEPS) requirements |
12 | self-ballasted compact fluorescent lamps (non-reflector) | AS/NZS 4847—Self-ballasted lamps for general lighting services, part 2 Minimum energy performance standards (MEPS) requirements |
13 | mains voltage halogen lamps (non-reflector) | AS 4934.2—Incandescent lamps for general lighting services, part 2 Minimum energy performance standards (MEPS) requirements |
14 | extra low voltage halogen lamps (reflector) | AS 4934.2—Incandescent lamps for general lighting services, Part 2 Minimum energy performance standards (MEPS) requirements |
15 | candle lamps (>40W) | AS 4934.2—Incandescent lamps for general lighting services, Part 2 Minimum energy performance standards (MEPS) requirements |
16 | fancy round lamps (>40W) | AS 4934.2—Incandescent lamps for general lighting services, Part 2 Minimum energy performance standards (MEPS) requirements |
17 | decorative lamps (>40W) | AS 4934.2—Incandescent lamps for general lighting services, Part 2 Minimum energy performance standards (MEPS) requirements |
18 | transformers and voltage convertors for extra low voltage halogen lamps | AS/NZS 4879.2—Performance of transformers and electronic step-down convertors for ELV lamps—Minimum energy performance standards (MEPS) requirements |
Part 3 Equipment requiring registration that may be labelled
Prescribed electrical equipment | Relevant standard | |
1 | single-phase ducted household or commercial air conditioners and heat pumps | AS/NZS 3823—Performance of electrical appliances—Air conditioners and heat pumps, part 2 Energy labelling and minimum energy performance standard (MEPS) requirements |
2 | single-phase non-ducted commercial air conditioners and heat pumps | AS/NZS 3823—Performance of electrical appliances—Air conditioners and heat pumps, part 2 Energy labelling and minimum energy performance standard (MEPS) requirements |
3 | 3-phase household or commercial air conditioners and heat pumps | AS/NZS 3823—Performance of electrical appliances—Air conditioners and heat pumps, part 2 Energy labelling and minimum energy performance standard (MEPS) requirements |
Schedule 5 QCA review of decisions
section 208
Section | Description of decision |
15(1) | facilities electricity entity decides are necessary to attach an overhead service line to the customer’s premises or for the entrance, support, protection and termination of an underground service line |
36(2)(a) | requirement by distribution entity for customer to regulate the use of an electrical article |
36(2)(b) | requirement by distribution entity for customer to use or deal with electricity supplied in the stated way |
36(2)(c) | requirement by distribution entity for customer to ensure a motor installation or starting device connected to a source of electricity supply complies with the requirements of the regulator |
36(2)(d) | requirement by distribution entity for customer about the power factor of an electrical installation |
37 | refusal by distribution entity to provide customer connection services to customer’s electrical installation |
40 | decision to require changes to a customer’s electrical installation |
41 | decision to make requirement about provision of links for connecting meters to an incoming electricity supply to a customer’s premises |
45(2) | decision to make requirement about space, housing, mounting and connecting facilities for a meter or control apparatus for a customer’s premises |
46(2) | decision to make requirement about provision of safe access to a customer’s premises |
46(3) | decision to install alternative metering or other equipment on a customer’s premises |
59(2) | requirement by distribution entity for provision of space for a substation, a right of way or access to the supplier’s equipment |
Schedule 6 External reviews of administrative decisions by QCAT
section 212(b)
Section | Description of decision |
24(4) | direction by the regulator to a person to take away an electric line |
139(1) | refusal to register an item of prescribed electrical equipment |
141(1)(a) | decision to fix a maximum registration term for an item of prescribed electrical equipment of less than 5 years |
144 | refusal to change an energy efficiency label |
147(2) | refusal to approve transfer of registration of item of prescribed electrical equipment |
149(1) or (2) | decision to cancel a registration of item of prescribed electrical equipment other than at the request of the holder of the registration |
211 | decision by QCA on internal review |
Schedule 7 Fees payable to regulator
section 226(1)
Fee units | ||
1 | Application for generation authority (Act, s 179(1)(c)) | 1,790.00 |
2 | Application for transmission authority (Act, s 188(1)(c)) | 1,790.00 |
3 | Application for distribution authority (Act, s 196(1)(c)) | 1,790.00 |
4 | Application for special approval (Act, s 209(1)(c)) | 522.75 |
5 | Application for transfer of a generation authority, transmission authority, distribution authority or special approval (Act, s 184A(1)(b), 193A(1)(b), 201A(1)(b) or 212A(1)(b)) | 166.05 |
6 | Application for registration of an item of prescribed electrical equipment (s 138(2)(a)) | 230.65 |
7 | Application for approval of a change to an energy efficiency label (s 144(2)(b)(i)) | 230.65 |
8 | Application for approval of transfer of registration of an item of prescribed electrical equipment (s 147(2)(b)(i)) | 76.85 |
9 | Inspection of the register (s 154(a)) | 15.00 |
10 | Copy of 1 entry in the register (s 154(b)) | 30.45 |
Schedule 8 Maximum fees payable to electricity entity
section 226(2)
Part 1 Meter reading and testing
Fee units | ||
1 | Special meter reading by Energex | 40.60 |
2 | Special meter reading by Ergon Energy | 47.20 |
3 | Testing of a meter by a distribution entity | 21.85 |
Part 2 Disconnection and reconnection
Fee units | ||
1 | Disconnection of supply of electricity to premises | nil |
2 | Reconnection of supply of electricity to a customer’s (the current customer’s) premises, after disconnection at a customer’s request or under the National Energy Retail Rules, rule 119(1)(g) to (i)— | |
(a) if the reconnection is made during ordinary business hours | nil | |
(b) if the reconnection is made outside ordinary business hours at the current customer’s request | 132.40 | |
3 | Reconnection of supply of electricity to a customer’s premises other than as mentioned in item 2— | |
(a) if the reconnection is made during ordinary business hours | 54.90 | |
(b) if the reconnection is made outside ordinary business hours at the customer’s request | 132.40 |
Part 3 Temporary connections
Fee units | ||
1 | Temporary connection of a supply of electricity to a building site by Ergon Energy during ordinary business hours (single-phase or multi-phase) | 497.40 |
2 | Temporary connection of a supply of electricity by Energex during ordinary business hours (current transformer or no current transformer) | 497.40 |
Part 4 Other services
$ | |
1 | Service to a customer conducted by Ergon Energy that is an excluded service, other than a service mentioned in part 1, 2 or 3, if— |
(a) the service is for premises connected to a long rural feeder or an isolated feeder; and | |
(b) QCA has not approved for the service a maximum charge that is stated by QCA to be “price on application” | The maximum charge approved by QCA for the service for customers connected to urban feeders |
Schedule 9 Dictionary
section 3
actual meter reading means an actual meter reading as defined under the metrology procedure made under the National Electricity Rules.
affected customer ...
apportioned amount ...
approved demand management plan, for chapter 4, part 2, division 2, see section 127A.
approved form means a form approved by the regulator under section 227.
approved testing entity, for a test or examination, means—
(a)a body accredited by the National Association of Testing Authorities, Australia ABN 59 004 379 74 (NATA) to perform the test or examination; or
(b)a body accredited by another body, operating under a reciprocal agreement with NATA, to perform the test or examination; or
(c)a body approved by the regulator to perform the test or examination.
AS 60038 means AS 60038 (Standard voltages) as in force from time to time.
AS/NZS means a joint Standards Australia and Standards New Zealand standard.
benchmark retail cost index ...
billing cycle ...
capital contribution ...
casual employee means a GOE industry employee mentioned in section 188.
category 1 qualifying customer see section 30AA(2).
category 1 small customer ...
category 2 small customer ...
check testing, for an item of prescribed electrical equipment, see section 157.
classification ...
closing day ...
competent person ...
consumers terminals means the point where a customer’s electrical installation is connected to the relevant supplier’s works.
consumption means consumption of electricity.
cooling-off period ...
corresponding law, for chapter 7, means 1 of the following laws—
•Electrical Products Act 2000 (SA)
•Energy and Utilities Administration Act 1987 (NSW)
•Electricity Safety Act 1998 (Vic).
decision maker, for chapter 9, part 2, division 2, means the entity whose decision is appealed against.
defaulting retailer ...
demand management, for chapter 4, part 2, division 2, see section 127A.
demand management plan, for chapter 4, part 2, division 2, see section 127A.
distribution entity ...
draft decision material ...
EGTS award see section 171.
electrical appliance means an appliance that uses electricity.
electrical installation includes part of an electrical installation.
Electricity Industry Code means the industry code of that name made by the Minister on 28 June 2007 under section 120B of the Actas in force immediately before the commencement of the Electricity Competition and Protection Legislation Amendment Act 2014, section 60.
electricity industry employee, for a State electricity entity, means a person—
(a)who is employed by the entity; and
(b)whose employment is—(i)in, or relates to, the electricity industry; and(ii)under a classification and salary level or point mentioned in the EGTS award.
employment entitlement, for chapter 8, see section 167.
Energex means Energex Limited ACN 078 849 055.
ESIE award ...
Essential Energy means Essential Energy established under the Energy Services Corporations Act 1995 (NSW).
excluded service means a service to a customer by a distribution entity that, under the National Electricity Rules, QCA decides is an excluded service for customers.
expression of interest ...
final consultation period, for chapter 10, part 1A, see section 222L(4)(c).
former employer, for chapter 8, part 3, see section 178(1).
former employment, for chapter 8, part 4, see section 184(1).
FRC day means the FRC day under section 310 of the Act.
future employer, for chapter 8, see section 168(2)(d).
GOE industry means all State electricity entities collectively, including entities declared to be State electricity entities under section 224.
GOE industry employee—
(a)means a person employed by a State electricity entity, including an entity declared to be a State electricity entity under section 224, in a full-time, part-time or casual capacity; and
(b)includes the chief executive officer of the entity.
high voltage means a voltage of more than 1,000V.
host retail entity ...
industrial instrument, for chapter 8, part 2, see section 171.
Industrial Relations Act means the Industrial Relations Act 1999.
Industrial Relations Commission means the Queensland Industrial Relations Commission continued in existence under section 255 of the Industrial Relations Act.
information notice, for an action or decision of the regulator or another entity, means a notice stating each of the following—
(a)the action or decision;
(b)for an action or decision of the regulator—the reasons for the decision;
(c)for an action or decision of another entity—that a person who may seek an internal review can ask the entity for a written statement of reasons for the action or decision;
(d)the rights of internal review under this regulation;
(e)the period in which any internal review under this regulation must be started;
(f)how rights of internal review under this regulation are to be exercised.
insolvency official ...
interim consultation period, for chapter 10, part 1A, see section 222H(2)(b).
isolated feeder see the Electricity Industry Code, section 10.1.1.
issues document see section 222H(2)(a).
jurisdictional regulator has the meaning given in the National Electricity Rules.
locality allowance means an allowance payable to an employee stationed in a centre distant from Brisbane to assist in offsetting the disadvantages associated with residence in the centre.
long rural feeder see the Electricity Industry Code, section 10.1.1.
loss factor has the meaning given in the National Electricity Rules.
lot ...
low voltage means a voltage of no more than 1,000V.
maximum registration term, for an item of prescribed electrical equipment, means its maximum registration term fixed under section 141(1)(a).
metering coordinator, for chapter 3, part 1, division 2, see section 39.
network device has the meaning given in the National Electricity Rules.
new employer, for chapter 8, part 3, see section 178(1).
new employment, for chapter 8, part 4, see section 184(1).
owner, for chapter 3, part 1, division 3, see section 58.
power factor has the meaning given in the National Electricity Rules.
prescribed electrical equipment means an item of electrical equipment stated in schedule 4, column 1, as defined in the relevant standard.
previous employer, for chapter 8, see section 168(2)(a).
proponent, for a proposed amendment of a distribution network code, see section 222A(1).
proportionate amount, for chapter 8, see section 175.
proposal, for a distribution network code amendment, see section 222A(1).
proposed transferee, for prescribed electrical equipment, see section 147.
reclassification application ...
recovery amount ...
redundancy payment, for chapter 8, see section 167.
redundant, for chapter 8, see section 168(1).
redundant employee, for chapter 8, see section 168(2).
register means the register the regulator keeps under section 153.
registered owner ...
relevant distribution entity ...
relevant distribution entity ...
relevant person ...
relevant retail entity ...
relevant standard, for an item of prescribed electrical equipment, means the standard stated in schedule 4 for the equipment item.
relevant supplier, for an electrical installation or premises or an electric line, means the distribution entity or the special approval holder who provides customer connection services to the electrical installation or premises or the line.
responsible person ...
retail cost view ...
retail entity ...
retailer authorisation means a retailer authorisation under the NERL (Qld).
retailer of last resort ...
ROLR ...
ROLR contract ...
ROLR event ...
scheduled meter reading ...
service line means an electric line that connects consumers terminals to the relevant supplier’s works or the works of another electricity entity.
single premises ...
special meter reading means an actual meter reading that happens at a time other than the time of a scheduled meter reading.
standard control service has the meaning given in the National Electricity Rules.
State electricity entity, for chapter 8, see section 167.
statutory customer contract ...
strategy, for chapter 4, part 2, division 2, see section 127C(2)(a).
suitable alternative employment, for chapter 8, see section 169.
supplier means a distribution entity or special approval holder who provides customer connection services to an electrical installation or premises.
supply point, for a premises, means—
(a)if the premises is connected to the national grid—the connection point for the premises; or
(b)if the premises is connected to a supply network that is not part of the national grid—the supply point for the delivery of electricity to the premises.
suspended retail entity ...
transfer day, for chapter 8, part 3, see section 178(3).
transferred employee, for chapter 8, part 3, see section 177.
urban feeder see the Electricity Industry Code, section 10.1.1.
website, for the pricing entity, means, if the entity is the Minister, the department’s website.
wiring rules means AS/NZS 3000—Electrical installations (known as the Australian/New Zealand Wiring Rules).
0