Electricity Industry Exemption Amendment Order (No. 2) 2022 (WA)
21 October 2022 GOVERNMENT GAZETTE, WA 4955 ENERGY
EN3O1
Electricity Industry Act 2004
Electricity Industry Exemption Amendment
Order (No. 2) 2022
SL 2022/171
Made by the Governor in Executive Council.
1. Citation
This order is the Electricity Industry Exemption Amendment
Order (No. 2) 2022.2. Commencement
This order comes into operation as follows
(a) clauses 1 and 2 on the day on which this order is published in the Gazette; (b) the rest of the order on the day after that day. 3. Order amended
This order amends the Electricity Industry Exemption
Order 2005.4. Clause 3 amended
(1) In clause 3(1) delete the definition of generation capacity. (2) In clause 3(1) in the definition of connection point:
system.
(a) delete "point" and insert: point, in relation to generating works,
(b) delete "system;" and insert:
4956 GOVERNMENT GAZETTE, WA 21 October 2022
(3) Delete clause 3(2) and insert:
(2) A person is exempt from the Electricity Industry
Act 2004 section 7(1) if —
(a)
in relation to the construction of generating works — the total generation capacity that the generating works will have is not more than 100 MW at each connection point after construction is completed; or
(b)
in relation to the operation of generating works — the generation capacity of the generating works is not more than 100 MW at each connection point.
Note: The heading to amended clause 3 is to read:
Exemption for generating works of 100 MW or less