Electricity Industry Exemption Amendment Order (No. 2) 2020 (WA)
| 3288 | GOVERNMENT GAZETTE, WA | 25 September 2020 |
ENERGY
EN3OI
Electricity Industry Act 2004
Electricity Industry Exemption Amendment
Order (No. 2) 2020
SL 2020/180
Made by the Governor in Executive Council.
1. Citation
This order is the Electricity Industry Exemption Amendment
Order (No. 2) 2020.2. Commencement
This order comes into operation as follows -
(a) clauses 1 and 2— on the day on which this order is published in the Gazette; (b) the rest of the order - on the day after that day. 3. Order amended
This order amends the Electricity Industry Exemption
Order 2005.4. Clause 3A amended
In clause 3A insert in alphabetical order:
L471859; Pilbara Energy Connection means the electricity infrastructure used, or to be used, for, or in connection with, or to control, the transportation of electricity between each of the following, through the Lambda Terminal located on mining tenement L45/474 -
(a)
the Chichester Hub located on mining tenement L45/456;
(b)
the Iron Bridge located on mining tenement L45/467;
(c) the Solomon Hub located on mining tenement
25 September 2020 GOVERNMENT GAZETTE, WA 3289 5. Clause 28 amended
Delete clause 28(1) and insert:
(1) In this clause —
Pilbara Energy Company means Pilbara Energy
Company Pty Ltd (ACN 624 732 878).
6. Clause 29 inserted
After clause 28 insert:
29. Exemption for generating works connecting to Pilbara Energy Connection
The following are exempt from the Electricity Industry
Act 2004 section 7(1) in relation to the construction and
operation of generating works that connect to, or will
connect to, the Pilbara Energy Connection —
(a)
Pilbara Energy (Generation) Pty Ltd (ACN 631 303 305);
(13) FMG Solomon Pty Ltd (ACN 128 959 179).
V. MOLAN, Clerk of the Executive Council.
0
0
0