Elcos Australia Pty Ltd v James Hardie Building Services & Technologies Ltd

Link copied
Case Copied 26 min read

IN THE SUPREME COURT
OF QUEENSLAND

Brisbane  No. 402 of 1995

[Elcos Australia Pty Ltd v James Hardie Building Services & Technologies Ltd]

BETWEEN:

ELCOS AUSTRALIA PTY LTD

A.C.N. 062 322 187

Plaintiff

AND:

JAMES HARDIE BUILDING SERVICES & TECHNOLOGIES

LIMITED

A.C.N. 000 067 541

Defendant

REASONS FOR JUDGMENT - CHESTERMAN J
  Judgment delivered 23 February 1999

  1. The plaintiff claims against the defendant moneys which it categorises as damages for breach of contract, or as due pursuant to contract or by way of restitution.  The plaintiff carried on business as an electrical contractor.  The defendant carried on business in a larger way as a builder and builder's supplier. 

  2. In 1994 Leda Design and Construction Pty Limited ("Leda") was developing two shopping centres, one at Capalaba and the other at Browns Plains, for an associated company.  It contracted with the defendant for the provision of fire, electrical, hydraulic and air-conditioning equipment, and services for the shopping centres.  The defendant in turn subcontracted the plaintiff to supply, deliver and install certain items of electrical work at the two shopping centres.  The plaintiff performed the work but claims that it has not been paid all that is due to it.  Not long before it went into liquidation in mid-1995 it issued proceedings in this court claiming $1,308,977 in respect of work done at the Capalaba Shopping Centre and $692,270 in respect of work at Browns Plains. 

  3. The action has been placed on the supervised case list and the parties are working towards  a mediated outcome.  The court has made directions to assist that process which recently came  to an impasse.  The plaintiff's claims are, principally, if not entirely, for amounts said to arise as variations to the work the specified subject matter of each contract.  The dispute between the parties concerns whether the claimed variations are in truth additional to the original scope of works or whether they, or some of them, were included in the original contracts.  To the extent that work additional to the contract has been done, the value of it is disputed.

  4. Part of the preparation for the mediation has been the compilation of reports by quantity surveyors dealing with each claimed variation and setting out the rival contentions in respect thereof.  This procedure broke-down in relation to some of the claimed variations for the Browns Plains Shopping Centre.  The defendant claimed that the parties had made a separate agreement by which the plaintiff had been paid an agreed amount of money by way of a compromise of its claim for variations.  Accordingly, the defendant contended the plaintiff could no longer pursue that part of its claim and that the respective experts should not have to undergo the tedium or incur the costs of preparing a report dealing with the variations which had been the subject of the compromise.

  5. The parties could not agree upon whether there had been a compromise or what they should do to prepare for the mediation in the absence of agreement on that issue.…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Elcos Australia Pty Ltd v James Hardie Building Services & T... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[1999] QSC 27
Decision Date

CaseChat Overview and Summary

In Elcos Australia Pty Ltd v James Hardie Building Services & Technologies Ltd, the plaintiff, an electrical contractor, claimed against the defendant, a builder and builder's supplier, for moneys allegedly due under a subcontract for work performed at two shopping centres. The dispute centred on whether certain work performed constituted variations to the original scope of the contract and, if so, the value of such variations. The court was required to decide several key issues, including whether a compromise agreement made between the parties on 3 October 1994 was binding, what the terms of that agreement were, and whether the defendant's failure to make payment by 10 October 1994 nullified the agreement. The court also had to consider whether the defendant's subsequent attempt to vary the agreement on 15 November 1994 constituted a repudiation of the original agreement or was induced by economic duress.

The court found that while an agreement to compromise was indeed reached on 3 October 1994, it did not include a term that payment would be made by 10 October 1994. Even if the notation regarding payment by 10 October were considered a term, it would not have been a condition precedent to the existence of the contract. Additionally, the court held that the defendant's attempt to vary the agreement on 15 November 1994 did not constitute a repudiation of the original agreement, as both parties continued to act in accordance with the October agreement. The court also found that the November agreement was unenforceable due to a lack of consideration.

The court declared that the agreement dated 3 October 1994 was valid and binding upon both parties, and that the payment of $450,000 compromised all variations claimed by the plaintiff in respect of site instructions given on or before 2 October 1994. The court ordered the defendant's solicitors to deliver a list of the variation claims it contended were compromised by the agreement, and directed the further hearing of the action to be adjourned to a later date. The defendant's costs of and incidental to the hearing on 15 and 16 February 1999 were to be taxed and paid by the plaintiff.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established