Eighty Eight Construction Pty Ltd v PPK Willoughby Pty Ltd

Case

[2015] NSWSC 847

26 June 2015

No judgment structure available for this case.

Supreme Court


New South Wales

Medium Neutral Citation: Eighty Eight Construction Pty Ltd v PPK Willoughby Pty Ltd [2015] NSWSC 847
Hearing dates:26 June 2015
Decision date: 26 June 2015
Jurisdiction:Equity Division - Technology and Construction List
Before: Stevenson J
Decision:

(1) The plaintiff/cross-defendant's summons dated 14 March 2014 and amended list statement dated 8 December 2014 be dismissed, pursuant to UCPR r 12.7.

(2) The plaintiff/cross-defendant's list response to the amended cross-claim dated 10 September 2014 be dismissed, pursuant to UCPR r 12.7.

(3) Judgment be entered forthwith in favour of the defendant on the plaintiff's summons dated 14 March 2014 and amended list statement dated 8 December 2014.

(4) Judgment be entered forthwith in favour of the cross-claimant on the cross-claimant's cross-summons dated 24 March 2014 and amended list cross-claim dated 24 March 2014, with damages to be assessed in accordance with UCPR r 30.1 by the Referee, pursuant to the order for reference made on 21 March 2014.

(5) The plaintiff/cross-defendant pay forthwith the defendant/cross-claimant's costs of and incidental to this notice of motion on an indemnity basis.

(6) That the plaintiff pay the defendant's costs of the proceedings.
Catchwords: PROCEDURE – summary disposal – whether proceedings should be dismissed for want of due despatch pursuant to Uniform Civil Procedure Rules r 12.7
Legislation Cited: Uniform Civil Procedure Rules 2005
Category:Principal judgment
Parties: Eighty Eight Construction Pty Ltd (Plaintiff/Cross-Defendant)
PPK Willoughby Pty Ltd (Defendant/Cross-Claimant)
Representation:

Counsel:
J P Redmond (Plaintiff/Cross-Defendant)
F P Hicks (Defendant/Cross-Claimant)

Solicitors:
Madison Marcus (Defendant/Cross-Claimant)
File Number(s):SC 2014/78684

EX TEMPORE Judgment (REVISED)

  1. By a contract dated 17 October 2012 (“the Contract”), the defendant, then the owner of a property in Willoughby, contracted the plaintiff to build 16 townhouses on that property.

  2. Disputes arose between the parties concerning the Contract. On 23 December 2013, the defendant purported to terminate the Contract. The plaintiff asserted that that purported termination was invalid and constituted a repudiation by the defendant of its obligations under the Contract. On 6 January 2014, the plaintiff purported to accept that repudiation and itself terminate the Contract.

  3. The plaintiff commenced proceedings on 14 March 2014, seeking a declaration that the defendant had repudiated the Contract and that it, the plaintiff, had validly terminated the Contract. The defendant then brought a cross-claim alleging various defects in the building work.

  4. Consequently, the matters for consideration in the proceedings are whether the plaintiff properly terminated the Contract, and whether there are defects arising from the plaintiff's building work for which the defendant should have compensation.

  5. On 21 March 2014, the Court made an order for reference pursuant to Uniform Civil Procedure Rules r 20.14, referring the whole of the proceedings out to Ms Janet Grey (“the Referee”) for determination.

  6. On 17 February 2015, the Referee fixed the hearing of the reference for 18 May 2015.

  7. Each side engaged engineering, building and window experts. The experts engaged by the plaintiff were: Mr Herbertson, an engineer; Mr Zakos, a builder; and Mr Karsai, a window and facade works specialist.

  8. On 2 April 2015, the plaintiff's then solicitors ceased to act. The plaintiff remains unrepresented by a solicitor. Mr Redmond of counsel has appeared before the Court on number of occasions, including today, on instructions from Mr Yuan, a director of the plaintiff.

  9. At around the time the plaintiff’s solicitors ceased to act, the plaintiff also ceased to retain its experts.

  10. In February 2015, the Referee made directions that the various experts confer and produce joint reports. By early May 2015, those reports had not been prepared as the Referee directed. The defendant's experts had not received any communication from their opposite number so far as concerns preparation of those reports; no doubt because they had ceased to be retained.

  11. In those circumstances, by notice of motion dated 6 May 2015 the defendant moved the Court for orders dismissing the proceedings for want of due despatch pursuant to UCPR r 12.7.

  12. Those matters came before Hammerschlag J on 15 May 2015. By consent, his Honour made the following orders:

“1.   The Summons and Amended List Statement of the Plaintiff/Cross Defendant is dismissed.

2.   The Plaintiff/Cross Defendant’s Cross Claim List Response is struck out and judgment is given in favour of the Defendant/Cross Claimant on its Cross Summons and Amended Cross Claim List Statement, with damages to be assessed.

3.   The Plaintiff/Cross Defendant is to pay the costs of the Defendant/Cross Claimant of the proceedings subject to specific costs orders made by these orders and in the course of the proceedings.

4.   The orders in paragraphs 1, 2 and 3 above are stayed until 5pm, Tuesday, 19 May 2015.

5.   The Plaintiff/Cross Defendant is to pay into Court by way of Bank Cheque in favour of the Defendant/Cross Claimant the sum of $42,458 as security for:

a.   the costs thrown away by the adjournment of the reference which is fixed to commence on Monday, 18 May 2015;

b.   the costs of the Notice of Motion filed on 6 May 2015;

by 4pm, Tuesday 19 May.

6.   If the Plaintiff/Cross Defendant complies with paragraph 5 of these orders, then the orders made in paragraphs 1, 2 and 3 shall be dissolved.”

  1. The plaintiff complied with order number 5. Accordingly, orders numbers 1, 2 and 3 made by Hammerschlag J were dissolved.

  2. Hammerschlag J also ordered that the commencement of the hearing of the reference be adjourned from 18 May 2015 to 13 July 2015.

  3. On 19 May 2015, the Referee directed that the parties procure that their experts produce joint reports by 30 June 2015. On 28 May 2015, the Referee directed that the parties each pay $35,000 as security for the costs of the Referee by 4 June 2015.

  4. Since then, the plaintiff has not done any of the following things:

  1. engaged a solicitor;

  2. caused an affidavit to be filed and served in compliance with UCPR r 7.2;

  3. complied with the Referee's directions to pay $35,000 as security for the costs of the Referee; or

  4. taken any steps to comply with the Referee's directions concerning joint reports, including engaging experts who might be parties to such report.

  1. The joint reports are not due until 30 June 2015. However, that is only two business days away.

  2. As Mr Hicks of counsel, who appeared for the defendant, submitted, the plaintiff has, in effect, abandoned the proceedings.

  3. In those circumstances, by notice of motion dated 19 June 2015, the defendant seeks the following orders:

“1. The Plaintiff/Cross-Defendant's Summons dated 14 March 2014 and Amended List Statement dated 8 December 2014 be dismissed, pursuant to Part 12, Rule 7 of the UCPR.

2. The Plaintiff/Cross-Defendant's List Response to the Amended Cross-Claim dated 10 September 2014 be dismissed, pursuant to Part 12, Rule 7 of the UCPR.

3.   Judgment be entered forthwith in favour of the Defendant on the Plaintiff's Summons dated 14 March 2014 and Amended List Statement dated 8 December 2014.

4. Judgment be entered forthwith in favour of the Cross-Claimant on the Cross-Claimant's Cross-Summons dated 24 March 2014 and Amended List Cross-Claim dated 24 March 2014, with damages to be assessed in accordance with Part 30, Rule 1 of the UCPR by the Referee, pursuant to the order for reference made on 21 March 2014.

5. In the alternative to prayers 1 to 4, the Plaintiff/Cross-Defendant provide security for the costs of the Referee’s fees for the Reference Hearing in the sum of $35,000.00 (plus GST), or such other amount that the Court may determine, pursuant to Part 42, Rule 21 of the UCPR.

6.   The Plaintiff/Cross-Defendant must comply with prayer 5 by 5.00pm on Wednesday, 1 July 2015.

7.   The security for costs to be provided by the Plaintiff/Cross-Defendant in the form of a payment into Court or payment to a trust account nominated by the Referee.

8.   If the Plaintiff/Cross-Defendant fails to comply with prayers 5 to 7 (inclusive):

a. The Plaintiff/Cross-Defendant’s Summons dated 14 March 2014 and Amended List Statement dated 8 December 2014 be dismissed, pursuant to Part 42, Rule 21(3) of the UCPR;

b. The Plaintiff/Cross-Defendant’s List Response to the Amended Cross-Claim dated 10 September 2014 be dismissed, pursuant to Part 42, Rule 21(3) of the UCPR;

c.   Judgment be entered forthwith in favour of the Defendant on the Plaintiff’s Summons dated 14 March 2014 and Amended List Statement dated 8 December 2014; and

d. Judgment be entered forthwith in favour of the Cross-Claimant on the Cross-Claimant’s Cross-Summons dated 24 March 2014 and Amended List Cross-Claim dated 24 March 2014, with damages to be assessed in accordance with Part 30, Rule 1 of the UCPR by the Referee, pursuant to the order for reference made on 21 March 2014.

9.   The Plaintiff/Cross-Defendant pay forthwith the Defendant/Cross-Claimant's costs of and incidental to this Notice of Motion on an indemnity basis. …”.

  1. Mr Redmond, who, as I have said, appeared before me today, informed me that Mr Yuan instructs him that the plaintiff would consent to orders 5, 6, 7, 8 and 9 as sought by the defendant, and that the plaintiff proposes to re-engage its experts with a view to compliance with the Referee's directions as to a joint report.

  2. However, one of those experts (Mr Zakos) is leaving Australia today until the end of July. Further, there is no evidence before me as to what steps the plaintiff has or could take to engage experts, nor as to the availability of the plaintiff's or the defendant's experts. Nor is any explanation offered for the failure of the plaintiff to comply with the Referee’s directions.

  3. It appears to me that in all those circumstances, the plaintiff has been given every opportunity to get its case ready for hearing before the Referee. The plaintiff has not conducted these proceedings with due despatch and the time has come to deal with the matter summarily pursuant to UCPR r 12.7.

  4. In those circumstances, I make the following orders:

  1. The plaintiff/cross-defendant's summons dated 14 March 2014 and amended list statement dated 8 December 2014 be dismissed, pursuant to UCPR r 12.7.

  2. The plaintiff/cross-defendant's list response to the amended cross-claim dated 10 September 2014 be dismissed, pursuant to UCPR r 12.7.

  3. Judgment be entered forthwith in favour of the defendant on the plaintiff's summons dated 14 March 2014 and amended list statement dated 8 December 2014.

  4. Judgment be entered forthwith in favour of the cross-claimant on the cross-claimant's cross-summons dated 24 March 2014 and amended list cross-claim dated 24 March 2014, with damages to be assessed in accordance with UCPR r 30.1 by the Referee, pursuant to the order for reference made on 21 March 2014.

  5. The plaintiff/cross-defendant pay forthwith the defendant/cross-claimant's costs of and incidental to this notice of motion on an indemnity basis.

  1. I also order that the plaintiff pay the defendant's costs of the proceedings.

**********

Decision last updated: 29 June 2015

Areas of Law

  • Civil Litigation & Procedure

Legal Concepts

  • Summary Judgment

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

0

Statutory Material Cited

1