CITATION: Eather & Anor v Rawson Homes & Anor [2003] NSWSC 439 HEARING DATE(S): 28 April 2003, 29 April 2003, 30 April 2003 JUDGMENT DATE:
26 May 2003JURISDICTION:
Common Law Division
Administrative Law ListJUDGMENT OF: Master Malpass DECISION: I set aside the orders made by the Tribunal on 18 April 2002. I remit the decision of this Court to the Tribunal and I order a rehearing of the proceedings by the Tribunal. The first defendant is to pay the costs of these proceedings. The Exhibits may be returned. If the first defendant is so entitled, it is to have a certificate under the Suitors' Fund Act 1951. CATCHWORDS: Appeal from Tribunal - scope of the appeal (a question with respect to a matter of law) - denial of procedural fairness - insufficiency of reasons - misdirection as to law - construction of provisions of Plain English Building Agreement - matter of law. LEGISLATION CITED: Commercial Tribunal Act 1984.
Consumer, Trader and Tenancy Tribunal Act 2001, s 67, s 67 (1).
Fair Trading Tribunal Act 1998, s 61.
Suitors' Fund Act 1951.CASES CITED: Life Insurance Co of Australia Ltd v Phillips (1925) 36 CLR 60. PARTIES :
Graham Anthony Eather and Helen Lynette Eather (Plaintiffs)
v
Rawson Homes Pty.Ltd. (First Defendant)
Registrar, Consumer Trader & Tenancy Tribunal (Second Defendant)
FILE NUMBER(S): SC 30046 of 2002 COUNSEL: Mr R Desiatnik (Plaintiffs)
Mr D Robertson (First Defendant)
N/A (Second Defendant)SOLICITORS: McKerns (Plaintiffs)
Doyles Construction Lawyers (First Defendant)
I V Knight - Crown Solicitor - Submitting Appearance (Second Defendant)
LOWER COURTJURISDICTION: Consumer, Trader & Tenancy Tribunal LOWER COURT FILE NUMBER(S): HB99/77038 LOWER COURT
JUDICIAL OFFICER :R Zikmann - Member
IN THE SUPREME COURT
OF NEW SOUTH WALES
COMMON LAW DIVISION
ADMINISTRATIVE LAW LISTMaster Malpass
Monday 26 May 2003
JUDGMENT30046 of 2002 Graham Anthony Eather & Anor v Rawson Homes Pty Ltd & Anor
1 MASTER: The plaintiffs and the first defendant were parties to a building contract (Plain English Building Agreement Edition 11). The contract was made on 22 April 1999. The first defendant was the builder. The plaintiffs were the owners of the subject property.
2 Construction commenced on 6 August 1999. Dispute arose between the parties concerning inter alia the colour of the brickwork. On, inter alia, 9 November 1999 the plaintiffs informed the first defendant that they intended to seek advice from the Department of Fair Trading concerning the brickwork. The first defendant responded by acting to suspend the works as per clause 6 of the building contract “until further advice is received” (see letter dated 10 November 1999).
3 The plaintiffs made application to the Fair Trading Tribunal (the Tribunal) seeking inter alia demolition. An interim decision was given by the Tribunal on 30 June 2000 dismissing that part of the claim that related to the colour of the brickwork.
4 There was a further hearing before the Tribunal. This saw the parties reaching agreement as to part of the plaintiffs’…
Keep reading for free
Create a free CaseChat account to read Eather v Rawson Homes and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2003] NSWSC 439
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the tribunal erred in law by misdirecting itself in its interpretation of the Plain English Building Agreement and whether the tribunal's decision was tainted by a denial of procedural fairness to Mr Eather. Additionally, the court examined whether the reasons provided by the tribunal were sufficient and whether the tribunal had properly considered all relevant legal principles.
In its judgment, the court found that the tribunal had indeed erred in law by misdirecting itself in its interpretation of the Plain English Building Agreement. The court noted that the tribunal had failed to properly apply the principles of contractual interpretation and had instead relied on an incorrect understanding of the agreement's terms. Furthermore, the court held that Mr Eather had been denied procedural fairness as the tribunal had not provided him with an adequate opportunity to respond to certain allegations. The court also found that the tribunal's reasons were insufficient as they did not adequately explain the basis for the tribunal's conclusions. Consequently, the court concluded that the tribunal's decision was flawed and remitted the matter back to the tribunal for reconsideration.
The court's final orders were to set aside the tribunal's decision and to remit the matter back to the tribunal for a fresh hearing, with directions to ensure that Mr Eather is afforded procedural fairness and that the tribunal provides comprehensive reasons for its decision.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi