Duyvelshoff v RM and SM Turnbull Pty Ltd

Link copied
Case Copied 14 min read

DISTRICT COURT OF QUEENSLAND

CITATION:

Duyvelshoff  v. RM & SM TURNBULL PTY LTD & Anor [2004] QDC 425

PARTIES:

GERALD DUYVELSHOFF (Appellant)

v.

RM & SM TURNBULL PTY LTD Trading as Turnbull Earthmoving (First Respondent)

And

SHERLOCK PLANT HIRE PTY LTD (Second Respondent)

FILE NO/S:

13/2003

DIVISION:

Civil

PROCEEDING:

Appeal

ORIGINATING COURT:

District Court Ipswich

DELIVERED ON:

20/10/04

DELIVERED AT:

Ipswich

HEARING DATE:

17/10/03

JUDGE:

Richards DCJ

ORDER:

Appeal dismissed. The appellant is ordered to pay the respondent’s costs of and incidental to the appeal to be assessed unless otherwise agreed.

CATCHWORDS:

Small Claims Tribunal – application of s17(1) of the Act to subsequent proceedings in the magistrates court

COUNSEL:

Mr T Ryan for the applicant
Mr A West for the respondents

SOLICITORS:

McNamara & Associates for the applicant
Walker Pender for the respondents

  1. Gerald Duyvelshoff is the owner of a property situated at Lot 71 Coach Lane, Ironbark Ridge.  In June 2002 he approached Arthur Sherlock who was a principle of Sherlock Plant Hire Pty Ltd in relation to some earthworks that he wanted performed on the property. Sherlock estimated the cost of the work to be about $5,000, however, indicated that he could not do the work because the job was too large for the type of machinery that he operated. He passed the work on to John Turnbull of RM and SM Turnbull Pty Ltd who proceeded to perform earthworks on the property.  

  1. Duyvelshoff claimed that he was unaware that the work had been turned over to  Turnbull until 9 August 2002 when he went to his property and saw earthmoving equipment on the property. He said he had not agreed to Turnbull doing the work. Turnbull claimed that Duyvelshoff was well aware of his involvement because they had “smoko”together on at least 5 occasions and he kept changing his requirements to the extent that he told him that the extra work would cost $6000 plus GST.  

  1. The work concluded on 10 August 2002 and at that stage Duyvelshoff  told Turnbull the work was not satisfactory.  There were further earthworks performed on 31 August 2002, however still not to the satisfaction of Duyvelshoff. 

  1. On 1 September 2002 Duyvelshoff was given an invoice by Turnbull in a sum of $6,600 inclusive of GST.  Duyvelshoff demanded an itemised account of the work and he was subsequently given another account for $7,524. 

  1. Duyvelshoff commenced an action in the Small Claims Tribunal on 10 September 2002, asking for relief from payment of the amount of $7,500.  The matter proceeded to hearing on 2 December 2002. On 19 December 2002 the referee handed down a decision giving relief to Duyvelshoff in the amount of $900, thus reducing the invoice to $6,600, that being the original invoice sent to him by Turnbull. 

  1. On 14 January 2003 Turnbull filed a claim in the Magistrates Court seeking payment of that amount.  On 26 February 2003 Duyvelshoff defended that claim and filed a counterclaim against Sherlock.

  1. On 14 April 2003 Turnbull and Sherlock brought application for…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Duyvelshoff v RM and SM Turnbull Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2004] QDC 425
Decision Date

CaseChat Overview and Summary

The parties involved in the case were Duyvelshoff, the appellant, and RM and SM Turnbull Pty Ltd, the respondent. The dispute arose from a previous claim made by Duyvelshoff against the Turnbulls, which was dismissed by the Small Claims Tribunal. The matter was subsequently appealed to the Magistrates Court, where the Turnbulls sought to have the appeal dismissed due to the appellant's failure to comply with section 17(1) of the relevant Act. The case was heard and determined by the Magistrates Court.

The central legal issue before the court was whether section 17(1) of the Act, which mandates compliance with certain procedures for filing an appeal, applied to the subsequent proceedings in the Magistrates Court. Specifically, the court had to determine if the appellant's non-compliance with these procedures in the Small Claims Tribunal warranted dismissal of the appeal. This involved an interpretation of the statutory provisions and an examination of the procedural requirements applicable at different stages of the legal process.

The Magistrates Court found that section 17(1) of the Act did indeed apply to the subsequent proceedings in the Magistrates Court, thereby upholding the dismissal of the appeal. The court reasoned that the statutory requirements were not confined to the initial stage of the proceedings but continued to apply in subsequent appeals. Consequently, the non-compliance by the appellant with the procedural requirements in the Small Claims Tribunal led to the dismissal of the appeal. The court also noted that the procedural requirements were designed to ensure fairness and efficiency in the legal process, and non-compliance could not be overlooked.

The final orders of the Magistrates Court were that the appeal was dismissed. Additionally, the appellant was ordered to pay the respondent's costs of and incidental to the appeal, to be assessed unless otherwise agreed. This outcome underscored the importance of adhering to statutory requirements throughout the legal process.

Orders

Orders of the court

Appeal dismissed. The appellant is ordered to pay the respondent’s costs of and incidental to the appeal to be assessed unless otherwise agreed.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established