Dura Constructions (Australia) Pty Ltd v SC Land Richmond Pty Ltd

Link copied
Case Copied 7 min read
IN THE SUPREME COURT OF VICTORIA Not Restricted

AT MELBOURNE

PRACTICE COURT

No. 9308 of 2006

DURA CONSTRUCTIONS (AUSTRALIA) PTY LTD Applicant
V
SC LAND RICHMOND PTY LTD Respondent

---

JUDGE:

WHELAN J

WHERE HELD:

Melbourne

DATE OF HEARING:

19, 23 October 2006

DATE OF RULING:

23 October 2006

CASE MAY BE CITED AS:

Dura Constructions (Australia) Pty Ltd v SC Land Richmond Pty Ltd

MEDIUM NEUTRAL CITATION:

[2006] VSC 428

---

BUILDING CONTRACT - owner purported to take over remaining works the subject of the contract – right of builder to be on land – appeal from decision of senior member of VCAT not to grant an interlocutory injunction.

INJUNCTION – Interlocutory – sought by builder until application for leave to appeal from decision of VCAT can be heard -  Whether error of law on serious question to be tried or on “balance of convenience” – relief refused.

Bradto v State of Victoria  [2006] VSCA 89
Porter v Hannah Builders [1969] VR 673

---

APPEARANCES: Counsel Solicitors
For the Applicant Mr M. Sifris S. C.
with Mr A. Herskope
Noble Lawyers
For the Respondent Dr C. Pannam Q.C.
with Mr A. Laird
Freehills

HIS HONOUR:

  1. The applicant, Dura Australia Constructions Pty Ltd (“Dura”), and the respondent, SC Land Richmond Pty Ltd (“SC Land”), are parties to a contract made on or about 15 December 2004.  The contract is to build some 29 apartments at 8 Lord Street, Richmond.  Dura is the builder and SC Land is the proprietor.

  1. Disputes have arisen between the parties and as a consequence of the matters the subject of those disputes, SC Land has purported to act under clause 44 of the contract and to take over all of the remaining work which is the subject of the contract.

  1. In response to that step Dura obtained an injunction from Senior Member Davis in VCAT on 21 September 2006, which injunction was then continued on 6 October 2006, and was eventually heard as a contested application by Senior Member Cremean on 12 and 13 October 2006.  Dr Cremean delivered his reasons and made orders on 19 October 2006.  He discharged the injunctions which had previously been made. 

  1. Dura then applied urgently in the Practice Court on the same day, 19 October 2006, for an injunction pending what was then foreshadowed as an application for leave to appeal on a question of law under s148 of the Victorian Civil and Administrative Appeals Tribunal Act 1998 (“the Act”).  I granted an injunction until 4.30pm today, in effect restraining SC Land from excluding Dura from possession of the site.  I made it clear, however, that the order was not intended to prevent SC Land from entering upon the site itself or from making such arrangements as it thought fit with a view to retaking possession.

  1. Dura has now issued an application for leave to appeal under s148 of the Act and that application is returnable before a Master on 8 November 2006. 

  1. It was common ground between the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Dura Constructions (Australia) Pty Ltd v SC Land Richmond Pt... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2006] VSC 428
Decision Date

CaseChat Overview and Summary

In the case of Dura Constructions (Australia) Pty Ltd v SC Land Richmond Pty Ltd, the dispute involves a building contract where the owner attempted to take over the remaining works of the contract, raising issues regarding the builder's right to be on the land. The case was heard in the Court of Appeal of the Supreme Court of Victoria. The builder, Dura Constructions, sought an interlocutory injunction to prevent the owner, SC Land Richmond, from taking over the works until the application for leave to appeal from a decision of the Victorian Civil and Administrative Tribunal (VCAT) could be heard. The primary issue for the court was whether the VCAT had erred in law on a serious question to be tried or on the balance of convenience when it declined to grant the injunction.

The court considered the principles established in Bradto v State of Victoria and Porter v Hannah Builders. It examined the discretion of the tribunal in assessing the balance of convenience and whether the VCAT had made an error in its assessment. The court found that the VCAT had correctly applied the relevant legal principles and had not erred in its decision. The court emphasised that the question of whether the VCAT had made an error of law on a serious question to be tried was distinct from the balance of convenience test, and the VCAT's decision fell within its discretion.

Ultimately, the court dismissed the application for an interlocutory injunction, affirming the VCAT's decision. The court held that there was no ground for the grant of leave to appeal, as the VCAT had not made an error of law. The builder's right to be on the land was not sufficient to warrant the grant of an interlocutory injunction without a clear error of law being demonstrated. The court's reasoning was based on the principle that the balance of convenience was a significant factor in such interlocutory applications, and the VCAT had appropriately exercised its discretion. The court declined to interfere with the VCAT's decision unless a clear error of law was established.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established