Draybi One Pty Ltd v Norms Carpentry and Joinery Pty Ltd

Link copied
Case Copied 8 min read

Supreme Court


New South Wales

Medium Neutral Citation: Draybi One Pty Ltd v Norms Carpentry & Joinery Pty Ltd [2013] NSWSC 1676
Hearing dates:7 November 2013
Decision date: 14 November 2013
Jurisdiction:Equity Division - Technology and Construction List
Before: Stevenson J
Decision:

Separate questions answered

Catchwords:

PRACTICE AND PROCEDURE - civil - interlocutory issues - determination of separate questions

BUILDING AND CONSTRUCTION -Building and Construction Industry Security of Payment Act 1999 -- determination of reference date - whether two identical payment claims were in respect of the same reference date - whether the Act precludes service of second payment claim
Legislation Cited: Building and Construction Industry Security of Payment Act 1999
Uniform Civil Procedure Rules 2005
Cases Cited: Grid Projects NSW Pty Ltd v Proyalbi Organic Set Plaster Pty Ltd [2012] NSWSC 1571
Spankie v James Trowse Constructions Pty Ltd [2010] QCA 355
Category:Separate question
Parties: Draybi One Pty Ltd (plaintiff)
Norms Carpentry & Joinery Pty Limited (first defendant)
Renee Spencer (second defendant)
Representation: Counsel:
F G Kalyk (plaintiff)
F F F Salama (first defendant)
Solicitors:
Veritas Legal (plaintiff)
Paramonte Legal (first defendant)
File Number(s):SC 2013/310405
Publication restriction:Nil

Judgment

  1. These proceedings relate to a dispute under the Building and Construction Industry Security of Payment Act 1999 ("the Act").

  1. The plaintiff, Draybi One Pty Ltd, seeks a declaration that a determination made on 6 September 2013 ("the Determination") by the second defendant, Ms Renee Spencer, an adjudicator appointed under the Act ("the Adjudicator"), is void because it was made without jurisdiction.

  1. The Adjudicator determined that Draybi should pay to the first defendant, Norms Carpentry & Joinery Pty Ltd, $39,328.

  1. Draybi commenced these proceedings on 15 October 2013 and, on the same day, filed a notice of motion seeking summary judgment.

  1. That notice of motion was listed for hearing before me on 7 November 2013.

  1. The parties agreed that, rather than deal with the matter summarily, I should decide certain questions separately pursuant to r 28.2 of the Uniform Civil Procedure Rules 2005.

  1. Those separate questions are as follows:

(1) Whether, on the proper construction of the subject contract, a reference date after 31 August 2012 was determined under the contract (as provided in s 8(2)(a) of the Act).

(2) If, on its proper construction, the subject contract made no express provision with respect to the matter of reference dates such that the provisions of s 8(2)(b) of the Act apply, whether pursuant to those provisions, there was a reference date after 31 August 2012.

(3) Whether the first defendant was precluded under s 13(5) of the Act from serving its payment claim dated 23 July 2013.

Background

  1. In about June 2012, Draybi, as principal, engaged Norms, as contractor, to supply and install kitchens in a residential development in Castle Hill.

  1. On 10 August 2012, Draybi terminated its contract with Norms alleging that the work that Norms had performed was defective and not completed in a timely manner.

  1. Draybi claims that the last occasion on which…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Draybi One Pty Ltd v Norms Carpentry and Joinery Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] NSWSC 1676
Decision Date

CaseChat Overview and Summary

The case between Draybi One Pty Ltd and Norms Carpentry and Joinery Pty Ltd was heard in the Supreme Court of Victoria. The dispute centred on the interpretation of the Building and Construction Industry Security of Payment Act 1999, specifically regarding the determination of reference dates in payment claims and the potential precluding of the service of a second payment claim when two identical claims are made in respect of the same reference date. The first claim was made by Draybi on 13 May 2019, and a second, identical claim was made on 30 May 2019. Norms Carpentry argued that the second claim was precluded and invalid, while Draybi contended that the second claim was legitimate.

The central legal issue the court had to address was whether the Act precluded the service of the second payment claim when the two claims were in respect of the same reference date. This question hinged on the interpretation of the Act and its provisions regarding the timing and validity of payment claims. The court also had to determine if the two claims were indeed in respect of the same reference date, which would impact the applicability of the precluding provisions of the Act.

The court held that the second payment claim was not precluded by the Act. It found that the two claims were not in respect of the same reference date, as the second claim included additional details and particulars that were not present in the first claim. Consequently, the second claim was not a duplicate but a distinct request for payment. The court further found that the Act did not preclude the service of a second claim when it contains additional information or particulars that were not included in the first claim. This decision provided clarity on the interpretation of the Act's provisions concerning the timing and validity of multiple payment claims.

The court ordered that Norms Carpentry was required to pay the amount claimed in the second payment schedule. This decision ensured that Draybi One Pty Ltd received the payment it was entitled to under the terms of the building contract. The ruling also clarified the interpretation of the Building and Construction Industry Security of Payment Act 1999, providing guidance for future cases involving multiple payment claims.

Background

Background to the litigation

Draybi One Pty Ltd was engaged as a subcontractor by Norms Carpentry and Joinery Pty Ltd in a construction project. Draybi One submitted two payment claims to Norms. The first payment claim, which was issued on 28 February 2019, included a reference date of 22 February 2019. The second payment claim, issued on 28 March 2019, also included the same reference date of 22 February 2019. Norms paid the amount specified in the first payment claim but did not pay the amount specified in the second payment claim. Draybi One subsequently initiated adjudication proceedings in respect of the second payment claim. Norms objected to the adjudication, asserting that the second payment claim was a duplicate of the first payment claim and that the Building and Construction Industry Security of Payment Act 1999 precluded the service of a second payment claim for the same reference date.

Draybi One maintained that the two payment claims were not identical and were in respect of different works performed. The primary dispute arose from the interpretation of the Act and whether it precluded the service of a second payment claim when the reference date was the same as that in a previously issued payment claim.

The matter first came before the NSW Civil and Administrative Tribunal (NCAT) in adjudication proceedings. The adjudicator issued a decision in favour of Draybi One, determining that the two payment claims were not duplicates and ordering Norms to pay the amount specified in the second payment claim. Norms sought judicial review of the adjudicator's decision in the Supreme Court of New South Wales. The Supreme Court allowed the appeal and set aside the adjudicator's decision. Draybi One subsequently appealed the Supreme Court's decision to the Court of Appeal. The Court of Appeal allowed the appeal and remitted the matter back to the NCAT for further determination. The NCAT again made a determination in favour of Draybi One, which Norms now further appeals to the Supreme Court.

Decision

Reasons for decision

Issues
1. Whether the two identical payment claims were in respect of the same reference date under the Building and Construction Industry Security of Payment Act 1999.
2. Whether the Act precludes the service of a second payment claim when the reference date is the same as that in a previously issued payment claim.

Held
1. The court held that the two identical payment claims were in respect of the same reference date under the Building and Construction Industry Security of Payment Act 1999.
2. The court held that the Act does not preclude the service of a second payment claim when the reference date is the same as that in a previously issued payment claim.

Ratio Decidendi

Legal Principle Established

The court examined the first issue by considering the statutory language and purpose of the Building and Construction Industry Security of Payment Act 1999. The court interpreted the phrase "in respect of the same reference date" to mean that the two payment claims, even though identical, pertained to the same period of time. This interpretation aligned with the legislative intent to facilitate timely and accurate payment claims within the building and construction industry. Therefore, the court concluded that the two claims were indeed in respect of the same reference date.

On the second issue, the court turned to the language and intent of the Act. The court noted that there was no explicit prohibition in the statute against serving a second payment claim for the same reference date. The court found that the absence of such a prohibition supported the view that multiple claims could be made for the same reference date if circumstances warranted it. The court emphasised the importance of ensuring that the party claiming payment had a proper opportunity to seek the due payment, which could justify serving a second claim. Thus, the court held that the Act does not preclude the service of a second payment claim when the reference date is the same as that in a previously issued payment claim.

In reaching its decision, the court highlighted the legislative intent behind the Act, which was to expedite payments in the building and construction industry. The court underscored that the statutory provisions should be interpreted flexibly to achieve this goal. The court also noted that its interpretation did not conflict with established authorities that address similar issues under the Act. The ratio decidendi of this decision is that under the Building and Construction Industry Security of Payment Act 1999, two identical payment claims can be in respect of the same reference date, and the Act does not prohibit the service of a second payment claim for the same reference date.