Medium Neutral Citation: Draybi One Pty Ltd v Norms Carpentry & Joinery Pty Ltd [2013] NSWSC 1676 Hearing dates: 7 November 2013 Decision date: 14 November 2013 Jurisdiction: Equity Division - Technology and Construction List Before: Stevenson J Decision: Separate questions answered
Catchwords: PRACTICE AND PROCEDURE - civil - interlocutory issues - determination of separate questions
BUILDING AND CONSTRUCTION -Building and Construction Industry Security of Payment Act 1999 -- determination of reference date - whether two identical payment claims were in respect of the same reference date - whether the Act precludes service of second payment claimLegislation Cited: Building and Construction Industry Security of Payment Act 1999
Uniform Civil Procedure Rules 2005Cases Cited: Grid Projects NSW Pty Ltd v Proyalbi Organic Set Plaster Pty Ltd [2012] NSWSC 1571
Spankie v James Trowse Constructions Pty Ltd [2010] QCA 355Category: Separate question Parties: Draybi One Pty Ltd (plaintiff)
Norms Carpentry & Joinery Pty Limited (first defendant)
Renee Spencer (second defendant)Representation: Counsel:
F G Kalyk (plaintiff)
F F F Salama (first defendant)
Solicitors:
Veritas Legal (plaintiff)
Paramonte Legal (first defendant)
File Number(s): SC 2013/310405 Publication restriction: Nil
Judgment
These proceedings relate to a dispute under the Building and Construction Industry Security of Payment Act 1999 ("the Act").
The plaintiff, Draybi One Pty Ltd, seeks a declaration that a determination made on 6 September 2013 ("the Determination") by the second defendant, Ms Renee Spencer, an adjudicator appointed under the Act ("the Adjudicator"), is void because it was made without jurisdiction.
The Adjudicator determined that Draybi should pay to the first defendant, Norms Carpentry & Joinery Pty Ltd, $39,328.
Draybi commenced these proceedings on 15 October 2013 and, on the same day, filed a notice of motion seeking summary judgment.
That notice of motion was listed for hearing before me on 7 November 2013.
The parties agreed that, rather than deal with the matter summarily, I should decide certain questions separately pursuant to r 28.2 of the Uniform Civil Procedure Rules 2005.
Those separate questions are as follows:
(1) Whether, on the proper construction of the subject contract, a reference date after 31 August 2012 was determined under the contract (as provided in s 8(2)(a) of the Act).
(2) If, on its proper construction, the subject contract made no express provision with respect to the matter of reference dates such that the provisions of s 8(2)(b) of the Act apply, whether pursuant to those provisions, there was a reference date after 31 August 2012.
(3) Whether the first defendant was precluded under s 13(5) of the Act from serving its payment claim dated 23 July 2013.
Background
In about June 2012, Draybi, as principal, engaged Norms, as contractor, to supply and install kitchens in a residential development in Castle Hill.
On 10 August 2012, Draybi terminated its contract with Norms alleging that the work that Norms had performed was defective and not completed in a timely manner.
Draybi claims that the last occasion on which…
Keep reading for free
Create a free CaseChat account to read Draybi One Pty Ltd v Norms Carpentry and Joinery Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2013] NSWSC 1676
- Decision Date
CaseChat Overview and Summary
The central legal issue the court had to address was whether the Act precluded the service of the second payment claim when the two claims were in respect of the same reference date. This question hinged on the interpretation of the Act and its provisions regarding the timing and validity of payment claims. The court also had to determine if the two claims were indeed in respect of the same reference date, which would impact the applicability of the precluding provisions of the Act.
The court held that the second payment claim was not precluded by the Act. It found that the two claims were not in respect of the same reference date, as the second claim included additional details and particulars that were not present in the first claim. Consequently, the second claim was not a duplicate but a distinct request for payment. The court further found that the Act did not preclude the service of a second claim when it contains additional information or particulars that were not included in the first claim. This decision provided clarity on the interpretation of the Act's provisions concerning the timing and validity of multiple payment claims.
The court ordered that Norms Carpentry was required to pay the amount claimed in the second payment schedule. This decision ensured that Draybi One Pty Ltd received the payment it was entitled to under the terms of the building contract. The ruling also clarified the interpretation of the Building and Construction Industry Security of Payment Act 1999, providing guidance for future cases involving multiple payment claims.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi