Medium Neutral Citation: Downer EDI Works Pty Ltd v Parsons Brinckerhoff Australia Pty Ltd [2011] NSWCA 78 Hearing dates: 1 April 2011 Decision date: 01 April 2011 Before: Giles JA at 1; Hodgson JA at 37; Sackville AJA at 40. Decision: Appeal dismissed with costs.
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
Catchwords: Building and construction - payment claim under Building and Construction Industry Security of Payment Act 1999 sent by facsimile - whether served in accordance with s 31(1)(c) by sending addressed to the person's ordinary place of business - multiple ordinary places of business - whether necessary that ordinary place of business be that with closest connection with relevant works - not necessary - Melbourne office was ordinary place of business. Legislation Cited: Building and Construction Industry Security of Payment Act 1999 Cases Cited: Emag Constructions Pty Ltd v Highrise Concrete Contractors (Aust) Pty Ltd [2003] NSWSC 903;
Falgat Constructions Pty Ltd v Equity Australia Corporation Pty Ltd [2006] NSWCA 259;
Hall v Jones (1942) SR (NSW) 203;
R v Young [1999] NSWCCA 166; (1999) 46 NSWLR 681;
Taylor v Centennial Newstan Pty Ltd [2009] NSWCA 276; (2010) NSWLR 379;
Taylor Projects Group Pty Ltd v Brick Dept Pty Ltd [2005] NSWSC 439;
Tokyo Mart Pty Ltd v Campbell (1982) 15 NSWLR 275.Category: Principal judgment Parties: Downer EDI Works Pty Ltd (Formerly Works Infrastructure Pty Ltd) - Appellant
Parsons Brinckerhoff Australia Pty Ltd - RespondentRepresentation: Counsel:
G Inatey SC & D R Sibtain - Appellant
S A Kerr SC - Respondent
Solicitors:
Blake Dawson - Appellant
Norton Rose Australia - Respondent
File Number(s): CA 2010/306867 Decision under appeal
- Citation:
- Parsons Brinckerhoff Australia Pty Ltd v Downer EDI Works Pty Ltd [2010] NSWSC 1295
- Date of Decision:
- 2010-11-12 00:00:00
- Before:
- Hammerschlag J
- File Number(s):
- 2010/00306867
Judgment
GILES JA : The appellant and the respondent were parties to a construction contract within the meaning of the Building and Construction Industry Security of Payment Act 1999 ("the Act"), under which the respondent was to provide design consultancy services in relation to the upgrade of a passenger rolling stock production facility at Glendale, New South Wales ("the Glendale project").
On 1 April 2010 the respondent sent to the appellant by facsimile a payment claim under the Act for $1,389,362.07. One facsimile was sent to the appellant's Melbourne office, the other to an office of the appellant at Broadmeadow in New South Wales. The respondent's employee had previously telephoned the appellant at the number given in the construction contract and asked "what fax should I…
Keep reading for free
Create a free CaseChat account to read Downer EDI Works Pty Ltd v Parsons Brinckerhoff Australia Pt... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2011] NSWCA 78
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the appellant's Melbourne office constituted an "ordinary place of business" for the purposes of section 31(1)(c) of the Act, given that the appellant had multiple places of business. Specifically, the court had to consider whether it was necessary for the ordinary place of business to be the one with the closest connection to the relevant works under the contract.
The Court of Appeal held that section 31(1)(c) does not require the ordinary place of business to be the one most closely connected with the relevant works. Instead, it is sufficient if the place of business is an ordinary place of business of the recipient. The court found that the Melbourne office was indeed an ordinary place of business for the appellant, and therefore, service by facsimile to that office was valid. Consequently, the appeal was dismissed with costs.
Orders
Orders of the court
Appeal dismissed with costs.
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi