Downer EDI Engineering Power Pty Ltd
[2016] FWCA 1339
•9 March 2016
[2016] FWCA 1339
DECISION
| Fair Work Act 2009 |
s.225 - Application for termination of an enterprise agreement after its nominal expiry date
Downer EDI Engineering Power Pty Ltd
(AG2016/358)
DOWNER EDI ENGINEERING SPRING GULLY PHASE 6 GAS
PROJECT UNION COLLECTIVE AGREEMENT 2010
Building, metal and civil construction industries
| SENIOR DEPUTY PRESIDENT RICHARDS | BRISBANE, 9 MARCH 2016 |
Application for termination of the Downer EDI Engineering Spring Gully Phase 6 Gas
Project Union Collective Agreement 2010.
[1] On 19 February 2016 Downer EDI Engineering Power Pty Ltd filed an application
pursuant to s.225 of the Fair Work Act 2009 (“the Act”) to terminate the Downer EDI
Engineering Spring Gully Phase 6 Gas Project Union Collective Agreement 2010 (“the
Agreement”).
[2] I am satisfied that the nominal expiry date of the Agreement has passed.
[3] In having regard to the requirements of s.226 of the Act and based on the material that
is before me, I am satisfied that:
it is not contrary to the public interest to terminate the Agreement; and
taking into account all the circumstances, it is appropriate to terminate the
Agreement.
[4] In accordance with s.227 of the Act, the termination will come into effect today.