Medium Neutral Citation: DIF III – Global Co-Investment Fund L.P v DIF Capital Partners Limited [2020] NSWCA 124
Hearing dates: 2 and 3 March 2020
Date of orders: 25 June 2020
Decision date: 25 June 2020
Before: Bathurst CJ at [1]; Bell P at [2]; Meagher JA at [150]
Decision:

Appeal dismissed with costs.

Catchwords:

CONTRACT – admitted breach of contract – causation of loss where alleged that, had proper due diligence been undertaken, an investment would not have been made – whether trial judge erred in holding that no damage was suffered by reason of breach of contract.

INSURANCE – whether professional indemnity policy responded to a claim – whether insured party became aware of any circumstances that could give rise to a third party claim during the policy period.

Legislation Cited:

Civil Liability (Third Party Claims Against Insurers) Act 2017 (NSW) s 4(1)

Insurance Contracts Act 1984 (Cth) s 54

Cases Cited:

Aristocrat Technologies Australia Pty Ltd v Global Gaming Supplies Pty Ltd [2009] FCA 1495

Australian Securities and Investments Commission (ASIC) v Rich (2009) 236 FLR 1; [2009] NSWSC 1229

Bonnington Castings Ltd v Wardlaw [1956] UKHL 1; [1956] AC 613

Commercial Union Assurance Company of Australia v Ferrcom Pty Ltd (1991) 22 NSWLR 389

Euro Pools Plc v Royal & Sun Alliance Insurance Plc [2019] EWCA Civ 808; Lloyd’s Rep IR 595

FAI General Insurance Co Ltd v Australian Hospital Care Pty Ltd (2001) 204 CLR 641; [2001] HCA 38

Fernandez v Tubemakers of Australia Ltd [1975] 2 NSWLR 190

Global Sportsman Pty Ltd v Mirror Newspapers Ltd (1984) 2 FCR 82; [1984] FCA 167

Gordon Martin Pty Limited v State Rail Authority of New South Wales [2008] NSWSC 343

Harris v Bellemore [2010] NSWSC 176

HLB Kidsons (a firm) v Lloyd’s Underwriters [2008] EWCA Civ 1206; [2009] Bus LR 759

Jones v Dunkel (1959) 101 CLR 298; [1959] HCA 8

Seltsam Pty Ltd v McGuiness; James Hardie & Coy Pty Ltd v McGuiness (2000) 49 NSWLR 262; [2000] NSWCA 29

Sigma Pharmaceuticals (Australia) Pty Ltd v Wyeth [2010] FCA 1211

St George Club Ltd v Hines (1961) 35 ALJR 106

Ta Ho Ma Pty Ltd v Allen (1999) 47 NSWLR 1; [1999] NSWCA 202

Tubemakers of Australia Ltd v Fernandez (1976) 50 ALJR 720

Category:Principal judgment
Parties: DIF III – Global Co-Investment Fund L.P (First Appellant)
DIF III GP Limited (Second Appellant)
DIF Capital Partners Limited (First Respondent)
Certain Underwriters, Subscribing to Lloyd’s Policy Numbered FD014280G (Seventh Respondent)
Certain Underwriters, Subscribing to Lloyd’s Policy Numbered BD0391FD014600G (Eighth Respondent)
Certain Underwriters, Subscribing to Lloyd’s Policy Numbered BD0391FD014610G (Ninth Respondent)
Certain Underwriters, Subscribing to Lloyd’s Policy Numbered B0391FD017580G (Tenth Respondent)
Representation:

Counsel:
I M Jackman SC, B A Ng (Appellants)
M A Jones SC, R P V Carey (First and Seventh to Tenth Respondents)

Solicitors:
Piper Alderman (Appellants)
Norton Rose Fulbright Australia (Seventh to Tenth Respondents)
File Number(s):
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read DIF III - Global Co-Investment Fund LP v DIF Capital Partner... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2020] NSWCA 124
Decision Date

CaseChat Overview and Summary

The appeal concerned a dispute between DIF III - Global Co-Investment Fund LP (the appellant) and DIF Capital Partners Ltd (the respondent). The appellant alleged a breach of contract by the respondent, claiming that had proper due diligence been undertaken, a particular investment would not have been made, thereby causing loss. The central question before the Court of Appeal of New South Wales was whether the trial judge erred in finding that the appellant had suffered no damage as a result of the alleged breach of contract. A secondary issue involved the respondent's professional indemnity insurance policy and whether it responded to the claim, specifically whether the insured party became aware of circumstances that could give rise to a third-party claim during the policy period.

The Court of Appeal was required to determine two primary legal issues. Firstly, it had to assess whether the trial judge's finding of no damage suffered by the appellant due to the alleged breach of contract was correct. This involved an examination of the causal link between the respondent's alleged failure to conduct proper due diligence and the appellant's purported loss. Secondly, the Court had to consider whether the respondent's professional indemnity insurance policy provided cover for the claim, focusing on the timing of the insured party's awareness of potential third-party claims within the relevant policy period.

In dismissing the appeal, the Court of Appeal upheld the trial judge's findings. The Court reasoned that the appellant had failed to establish a causal connection between the alleged breach of contract and any loss suffered. The evidence did not demonstrate that the investment would not have been made had proper due diligence been conducted, nor that the loss ultimately incurred was a direct consequence of the breach. Regarding the insurance issue, the Court found that the insured party had not become aware of circumstances that could give rise to a third-party claim during the policy period, meaning the professional indemnity policy did not respond. Consequently, the appeal was dismissed with costs.

Orders

Orders of the court

Appeal dismissed with costs.

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established