ACT CIVIL & ADMINISTRATIVE TRIBUNAL
DIETHELM & ORS v ACT PLANNING AND LAND AUTHORITY (Administrative Review) [2024] ACAT 25
AT 89/2023
Catchwords: ADMINISTRATIVE REVIEW – Whether the application for development approval is valid when letter of authorisation by the lessee of the land for the purposes of s 139(2)(b)(i) was executed at a time when the company was deregistered and the office of director vacated – effect of deregistration – consequences of reinstatement – ineffective letter of authorisation – failure of letter of authorisation is not determinative of the application’s validity
Legislation cited: Corporations Act 2001 (Cth) ss 128, 129, 601AB, 601AD, 601AH
Planning and Development Act 2007 s 139
Legislation Act 2001 ss 199, 255, dictionary
Electronic Transactions Act 2001 ss 8, 9
Cases cited:Allianz Australia InsuranceLtd v Viksne [2021] NSWCA 268
Attorney-General (SA) v Corporation of the City of Adelaide [2013] HCA 3
CGU Workers Compensation (NSW) Ltd v Rockwall Interiors Pty Ltd [2006] NSWSC 690
Danich Pty Ltd Re Cenco Holdings Pty Ltd [2005] NSWSC 293
White v Baycorp Advantage Business Information Services Ltd [2006] NSWSC 441
Tribunal:Senior Member P Spender
Date of Orders: 1 March 2024
Date of Reasons for Decision: 20 March 2024
Corrected under Section 63 of the ACT Civil and Administrative Tribunal Act 2008 on 20 March 2024
AUSTRALIAN CAPITAL TERRITORY )
CIVIL & ADMINISTRATIVE TRIBUNAL ) AT 89/2023
BETWEEN:
MARY-JULIA DIETHELM
First Applicant
FRANCES POWRIE
Second Applicant
BEN CHEUNG
Third Applicant
SANIE YMER
Fourth Applicant
WILLIAM TUCKER
Fifth Applicant
AND:
SABINE CLOSE PTY LTD ACN 608 430 726
Party Joined
AND:
ACT PLANNING AND LAND AUTHORITY
Respondent
TRIBUNAL:Senior Member P Spender
DATE:1 March 2024
CORRECTED ORDER
The Tribunal orders that:
Pursuant to the orders made by the tribunal on 17 January 2024, the preliminary question is answered in the affirmative: the application for development approval lodged on 23 May 2023 is valid.
The Party Joined is required by 8 March 2024 to make an application for interim orders pursuant to section 22P of the ACT Civil and Administrative Tribunal Act 2008 for an extension of time to decide the application.
The matter is listed for further directions at 10.00 am on Friday 22 March 2024.
………………………………..
Senior Member P Spender
REASONS FOR DECISION
In the reasons below, a reference to ‘ACAT’ or ‘tribunal’ refers to the ACT Civil and Administrative Tribunal generally, whereas ‘Tribunal’ refers to the presently constituted tribunal.
Summary of decision
The Tribunal has concluded that the application for development approval lodged on 23 May 2023 is valid. The preliminary question concerned section 139(2)(b)(i) of the Planning and Development Act 2007 (the Act). That provision states that an application for development approval must be signed by the lessee of the land to which the application relates. In this case, the lessee of the land was a company. The application for development approval attached a letter of authorisation which purported to be the company’s signature for the purposes of 139(2)(b)(i) of the Act. The…
Keep reading for free
Create a free CaseChat account to read Diethelm & Ors v ACT Planning and Land Authority (Administra... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] ACAT 25
- Decision Date
CaseChat Overview and Summary
The court was tasked with determining whether the DA complied with section 139 of the Act and whether the method used to convey the lessee's consent was sufficient. The Tribunal interpreted section 139 as a protective provision designed to ensure the lessee's consent to the application and to prevent "rogue applications." The court concluded that the crucial aspect of the subsection was the communication of the lessee's consent. The Tribunal held that the DA must be "signed by" the lessee, and this requirement was not negated by the ETA. The court also noted that in a public process of notification, it was necessary to interpret the requirements of section 139 to minimise uncertainties. Consequently, the Tribunal found that the DA did not comply with the Act because the letter of authorisation did not meet the necessary signature requirement.
In summary, the court determined that the DA did not meet the requirements of section 139 of the Act because the letter of authorisation did not constitute a valid signature. The court held that the mandatory language of the subsection, which required the application to be "signed by" the lessee, was not satisfied by the form of the DA submitted. As a result, the DA was deemed non-compliant with the Act, and the Tribunal ruled in favour of the applicants on this point. The final orders of the Tribunal would likely address the non-compliance of the DA and may include directives for the respondent to accept a validly signed DA or further instructions on how the Company can properly submit a compliant application.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Stated briefly, the party joined argued that section 139 of the Act had been satisfied by the form of the DA that had been submitted by the Architect on behalf of the Company.[5] These arguments were based upon a combination of the form of the DA which contained declarations rather than requiring a signature and the relevant provisions of the Legislation Act 2001 (LA), and the Electronic Transactions Act 2001 (ETA). The party joined argued there was ostensible authority at all times for the Architect to lodge the DA on behalf of the Company. The respondent does not require signed hard copies of the DA to be lodged so the requisite authority can be taken to be present at all times. In the alternative, validation of the director's authority can be sought from the Supreme Court but this would require an application to the Supreme Court to validate the relevant actions under section 601AH of the Corporations Act2001 (Cth) (Corporations Act).[6][5] Party joined’s submissions dated 19 January 2024 at [2 a][6] Party joined’s submissions dated 19 January 2024 at [2 b] The respondent supported the primary submissions made by the party joined and argued that the Letter of Authorisation was not determinative of the issue of whether section 139 had been complied with. The submissions made by the party joined and the respondent are elaborated below. The applicants argued that section 139 of the Act requires a signature and the online DA form specifies that this signature be in a letter of authorisation attached to the DA. The letter of authorisation did not meet the requirements of section 139 of the Act. Section 9 of the ETA specifies the requirements for electronic signature to be acceptable. There must be consent of the person to whom the signature is required to be given to the method used to identify the person who signs, and their intention. The DA form specifies that a signed letter of authorisation be attached. No consent to any other method is evident. Therefore section 9 of the ETA does not negate the need for a valid signed letter of authorisation.[7] At the beginning of the hearing, the Tribunal asked counsel acting for the party joined to explain the purpose of section 139(20(b)(i) of the Act. Counsel responded in words to the effect that the provision is a protective provision which is designed to ensure that the lessee consents to the application and to avoid “rogue applications”.[8] The Tribunal agrees with this interpretation and notes that the important aspect of the subsection is conveying the consent of the lessee. Therefore, when construing the requirements of the subsection, the Tribunal does not consider that other broader considerations such as the public interest or the interests of third-party objectors are relevant to its interpretation. Therefore, in construing the provision, it is necessary to consider whether the relevant communications were sufficient to amount to a communication of the lessee's consent to the application for development approval. That consent is usually conveyed by the letter of authorisation where the lessee is a company because that is the functional equivalent of a “signature” for the purposes of section 139(2) of the Act. However, the subsection uses mandatory language by stating that the application “must” be “signed by” the lessee. The Tribunal also notes that the context of section 139 involves a public process of notification of the DA, so one must be careful about interpreting the requirements of section 139 so as to minimise uncertainties arising in the DA process.The effect of the Letter of Authorisation[8] Recording of hearing dated 27 February 2024 at 10:30 AM