Land and Environment Court
New South Wales
Medium Neutral Citation: Dellara Pty Ltd v Minister for Planning and Penrith City Council [2012] NSWLEC 1186 Hearing dates: 3, 4, 5, 8 August 201123, 24, 27, 28 and 29 February 2012 Decision date: 13 July 2012 Jurisdiction: Class 1 Before: Tuor C and Johnson AC Decision: See paragraph 250
Catchwords: DEVELOPMENT APPLICATION -
waste and resource management facility comprising a non-putrescible waste recycling facility, an ancillary waste emplacement, waste transfer station, continued shale/clay extraction and site rehabilitation. Whether the proposal will result in unacceptable land use conflicts and visual impacts. Whether the clay/shale resource extraction is optimised and can occur with the emplacement of waste. Community submissions and public interest, contribution to road works and conditions of approvalLegislation Cited: Environmental Planning and Assessment Act 1979
Environmental Planning and Assessment Regulation 2000
Contaminated Land Management Act
Protection of the Environment Operations Act
State Environmental Planning Policy (Infrastructure) 2007
State Environmental Planning Policy (Major Development) 2005
Sydney Regional Environmental Plan 9 - Extractive Industries
Sydney Regional Environmental Plan 25 - Orchard Hills
Penrith Local Environmental Plan 2010Cases Cited: New Century Developments Pty Ltd v Baulkham Hills Shire Council (2003) 127 LGERA 303
Pittwater Council v Minister for Planning [2011] NSWLEC 162Category: Principal judgment Parties: Dellara Pty Ltd (Applicant)
Minister for Planning (First Respondent)
Penrith City Council (Second Respondent)Representation: Counsel
Mr C McEwen, SC with Mr M Staunton, barrister (Applicant)Ms S Duggan, SC with Mr Nash, barrister (First Respondent)
Mr J Robson SC with Mr M Fraser, barrister (Second Respondent)
Solicitors
King & Wood Mallesons (Applicant)Department of Planning (First Respondent)
Gadens Lawyers (Second Respondent)
File Number(s): 10928 of 2010
Judgment
This is an appeal under s 75K(2) of the Environmental Planning and Assessment Act 1979 (EPA Act) against the refusal by the First Respondent, the Minister for Planning (the Minister), of a major project under Part 3A of EPA Act. Although Part 3A has been repealed, it continues to apply to the project under Schedule 6A, cll 2 and 3 of the EPA Act.
Penrith City Council (the council) is an objector to the Project application and has applied to the Court under s75K (3) of the EPA Act to be heard as a party to the Appeal. The council is the Second Respondent in the Appeal.
The site and its locality
The site comprises lot 40 DP 738126 and is located at 123-179 Patons Lane, Orchard Hills (site). It has an area of 60ha.
Access to the site is off Patons Lane, which runs off Luddenham Road. Patons Lane is a public road but it is currently unsealed and blocked by gates. Luddenham Road connects with Mamre Road, which provides access to the Great Western Highway and the M4 Motorway, about 5km to the north of the site.
The site has operated intermittently as a quarry since 1981 which has resulted in disturbance across most of the land. The main areas of disturbance consist of two extraction areas,…
Keep reading for free
Create a free CaseChat account to read Dellara Pty Ltd v Minister for Planning and Penrith City Cou... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2012] NSWLEC 1186
- Decision Date
CaseChat Overview and Summary
The central legal issues that the court had to resolve were whether the refusal by the council to grant the development application was lawful, and if the Minister's intervention and subsequent appeal were justified. The court also needed to determine whether the development proposed by Dellara Pty Ltd would have a detrimental impact on the environment and the community, and if the proposed development complied with the relevant planning instruments, including the local environment plan and any other applicable regulations.
The court examined the evidence presented by both parties and assessed the merits of the case. The Land and Environment Court concluded that the refusal by the council was not justified, as it was not based on valid grounds. The court found that the proposed development would not cause significant environmental harm and that it complied with the relevant planning instruments. Consequently, the Minister's intervention and subsequent appeal were deemed to be unjustified. The court ordered that the development application be approved, subject to certain conditions, including the implementation of measures to mitigate any potential adverse environmental effects.
Orders
Orders of the court
See paragraph 250
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi