Decmil Australia Pty Ltd v Avid Australia Holdings Pty Ltd

Link copied
Case Copied 12 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

IN CHAMBERS

CITATION:   DECMIL AUSTRALIA PTY LTD -v- AVID AUSTRALIA HOLDINGS PTY LTD [2022] WASC 183

CORAM:   MASTER SANDERSON

HEARD:   18 MAY 2022

DELIVERED          :   24 MAY 2022

PUBLISHED           :   24 MAY 2022

FILE NO/S:   CIV 2233 of 2021

BETWEEN:   DECMIL AUSTRALIA PTY LTD

Plaintiff

AND

AVID AUSTRALIA HOLDINGS PTY LTD

Defendant


Catchwords:

Practice and procedure - Application for summary judgment - Turns on own facts

Legislation:

Rules of the Supreme Court 1971 (WA)

Result:

Judgment for plaintiff

Category:    B

Representation:

Counsel:

Plaintiff : JE Scovell
Defendant : MG Pendlebury

Solicitors:

Plaintiff : Tottle Partners
Defendant : Summers Legal

Case referred to in decision:

Palaniappan v Westpac Banking Corporation [2016] WASCA 72

MASTER SANDERSON:

  1. This was the plaintiff's application for summary judgment.  Rather surprisingly for a straightforward case, there was some argument about the principles applicable to summary judgment.  I will briefly deal with the relevant principles.  But it is convenient first to outline the facts.  In doing so, I am drawing on the plaintiff's statement of claim lodged 20 December 2021. 

  2. By an agreement dated 19 October 2020 (Head Contract) between the plaintiff and Robe River Mining Co Pty Ltd (Robe River), the plaintiff agreed to design and construct a laboratory located at the Mesa A Mine Site in the State's northwest.  By an agreement dated 13 January 2021 (Mesa A Subcontract) between the plaintiff as contractor and AVRWA as subcontractor, AVRWA agreed to perform and complete the Mesa A project in accordance with the terms of the agreement. 

  3. Ordinarily in a contractor/subcontractor relationship, the contract would provide for payment by the contractor to the subcontractor.  This agreement did have such a provision but it also contained a provision which contemplated payment by the subcontractor to the contractor.  The relevant provision is cl 24.15.  I have added cl 24.16 and cl 24.17 for the sake of completeness.  They read as follows:

    24.15Subject to the provisions of the Subcontract and receipt of a valid tax invoice (if Clause 24.29 is specified in Section B - Subcontract Particulars to be not applicable), where a payment schedule issued by the Contractor:

    (a)certifies an amount payable from the Contractor to the Subcontractor, the Contractor must, within the time specified in Section B - Subcontract Particulars, pay to the Subcontractor an amount not less than the amount shown on the payment schedule; or

    (b)certifies an amount payable from the Subcontractor to the Contractor, the Subcontractor must pay to the Contractor an amount not less than the amount shown on the payment schedule within 10 Business Days.

    24.16Without limiting Clause 24.14, the Contractor may issue a revised payment schedule at any time correcting any omission or error discovered in any previous payment schedule or modifying any previous payment schedule issued by it, including as a result of the provision of information under Clause 24.5.

    24.17If the Subcontractor fails to make a progress claim in accordance with the Subcontract, the Contractor may nevertheless issue a payment schedule…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Decmil Australia Pty Ltd v Avid Australia Holdings Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] WASC 183
Decision Date

CaseChat Overview and Summary

In the case of Decmil Australia Pty Ltd v Avid Australia Holdings Pty Ltd, the dispute arose from subcontracts between the parties, which were in turn part of a larger contractual arrangement. The plaintiff, Decmil Australia, sought payment from the defendant, Avid Australia, under the terms of these subcontracts. The defendant, however, refused to make payment until the disputes raised by Decmil were resolved. This refusal led to the plaintiff initiating legal proceedings to compel payment. The case was heard in the Supreme Court of New South Wales.

The primary legal issue before the court was the interpretation and enforceability of the subcontracts, particularly the clauses that required payment of the invoices prior to the resolution of any disputes. Counsel for the defendant argued that such a requirement was commercially unreasonable and not in line with the intended aim of the contract. They proposed that the payment clause could be seen as a 'pay to play' provision, which was not fair or commercially sensible. The court also needed to determine whether a term could be implied into the subcontracts that would allow for a stay of payment if a dispute resolution procedure was initiated.

The court, in its reasoning, referred to the case of Palaniappan v Westpac Banking Corporation, where a similar suspension clause was deemed effective and enforceable. The court noted that the clause in the current case, while requiring payment of the invoice within a specified timeframe, did not suspend the subcontractor's rights to initiate the dispute resolution procedure. This distinction was crucial as it meant that the subcontractor could pursue its rights without being prevented from doing so by the non-payment of the invoice. The court further rejected the argument that a term could be implied into the subcontracts to allow for a stay of payment upon initiation of dispute resolution, as this would contradict the clear terms of the contract and was unnecessary for the contract's efficacy. The court concluded that the commercial arrangement in the subcontracts was sensible and commercially reasonable.

The final orders of the court were that the defendant, Avid Australia, was required to make payment of the invoices as stipulated in the subcontracts. The court found that the terms of the subcontracts were fair and commercially reasonable, and that the defendant's arguments did not justify any modification or implication of terms into the contracts.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established

It was counsel's submission that interpreting the provisions of the subcontracts in a way which required payment of the invoices prior to any dispute being resolved was commercially unreasonable and could not have been the aim of the contract. Counsel for the plaintiff responded by saying that the provision requiring payment prior to the dispute resolution procedure being concluded was a 'pay to play' provision. In fact, suspension clauses (to use a more technical description) are not uncommon, particularly in guarantees. The effect of such clauses was considered by the Court of Appeal in Palaniappan v Westpac Banking Corporation [2016] WASCA 72. The relevant clause under consideration in that appeal was as follows:41.Clause 9 provided:As long as any of the guaranteed money remains unpaid, you may not, without our consent:(a)reduce your liability under this guarantee and indemnity by claiming that you or the customer or any other person has a right of set‑off or counterclaim against us; or(b) exercise any legal rights to claim to be entitled to the benefit of another guarantee, indemnity, mortgage, charge or other security given in connection with the guaranteed money or any other amount payable under this guarantee and indemnity …; or(c)claim an amount from the customer, or another guarantor of the customer's obligations, under a right of indemnity; or(d)claim an amount in the insolvency of the customer or another guarantor of the guaranteed money (including a person who has signed this guarantee and indemnity with you). The question the court had to consider was whether or not a defence could be run despite cl 9 of the guarantee. The court assumed the appellant had a good cause of action. Against that background, the court concluded the suspension clause was effective and enforceable. That clause was more draconian in its effect than the terms of the contract in this case. What is required under the terms of the contract is payment of the invoice within a timeframe. If the invoice is not paid, the subcontractor is not precluded from initiating the dispute resolution procedure. To that extent, there is no suspension of the subcontractor's rights. Nor would the defendant as guarantor be prohibiting from standing in the shoes of the subcontractor and pursuing the subcontractor's rights. Accordingly, there is no basis upon which it could be said that the regime found in the subcontract is in some way commercially improper. The further argument put by the defendant was that it was possible to imply a term into the subcontracts that if the dispute resolution procedure was initiated, there would be a stay of the obligation of the subcontractor to make payment. With respect, there is no basis upon which such a term could be implied. Apart from anything else, it would run counter to the clear terms of the contract itself. Nor would it be necessary to give efficacy to the contract. The 'pay to play' provision of the contract is a perfectly sensible commercial arrangement.