District Court
New South Wales
Medium Neutral Citation: Deane Projects Building Pty Ltd v Kinda Kapers Holdings Pty Ltd [2020] NSWDC 622 Hearing dates: 6-9 October 2020 Date of orders: 19 October 2020 Decision date: 19 October 2020 Jurisdiction: Civil Before: Abadee Decision: See paragraphs 346-350
Catchwords: CONTRACTS – building and construction – variation claims – whether provision for variations was itself varied – whether implied term incorporated through prior course of dealing – alleged defective works – whether owner’s claim limited in time – whether claimed defects appeared during defects liability period – whether builder liable for “design defects” in commercial contract for construction
DAMAGES – claim for rectification costs for defective works – whether owner intended to rectify – whether proposed works reasonable
PRACTICE AND PROCEDURE – building disputes – building experts – conflicting evidence about defects and scope of rectification works – desirability of practitioners ensuring building experts confer and jointly produce report prior to hearing
Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW)
Environmental Planning and Assessment Act 1979 (NSW)
Environmental Planning and Assessment Regulation 2000 (NSW)
Environmental Planning Regulations 1994 (NSW)
Home Building Act 1989 (NSW)
Cases Cited: Bellgrove v Elridge (1954) 90 CLR 613
Bitannia Pty Ltd v Parkline Constructions Pty Ltd [2009] NSWSC 1302
Cellarit Pty Ltd v Cawarrah Holdings Pty Ltd [2018] NSWCA 213
Cordon Investments Pty Ltd v Lesdor Properties [2012] NSWCA 184
The Owners – Strata Plan No 66375 v King [2018] NSWCA 170
Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221
Repfix Industries Pty Ltd v FBD Group [2020] NSWDC 514
Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272
Trimis & Anor v Mina [1999] NSWCA 140; (2000) 16 BCL 288
TSW Analytical Pty Ltd v The University of Western Australia [2017] WASCA 67
Turner Corporation Ltd (Receiver and Manager Appointed) v Austotel Pty Ltd (1994) 13 BCL 378
Update Constructions Pty Ltd v Rozelle Child Care Centre Ltd (1990) 20 NSWLR 251
Texts Cited: J D Heydon, Heydon on Contract (Lawbook Co, 2019)
Category: Principal judgment Parties: Deane Projects Building Pty Ltd (Plaintiff/Cross-Defendant)
Kinda Kapers Holdings Pty Ltd (Defendant/Cross-Claimant)Representation: Counsel:
Solicitors:
Mr M Maconachie for the plaintiff/cross-defendant
Mr G Carolan for the defendant/cross-claimant
Roberts Legal for the plaintiff/cross-defendant
Morrissey Law for the defendant/cross-claimant
File Number(s): 2019/121014 Publication restriction: Nil
Judgment
INTRODUCTION
-
This case concerns the construction of renovation works undertaken in connection with a child care centre operated by the defendant in Toronto, New South Wales. Simply described, the works concerned two buildings, Block ‘A’ (at the front) and Block ‘B’ (at the rear). Both were built with precast concrete exterior walls and had steel framed suspended floors, steel framed roofs and Colorbond treated roof sheeting. Interior walls generally had steel frames lined with plasterboard. Outside the two…
Keep reading for free
Create a free CaseChat account to read Deane Projects Building Pty Ltd v Kinda Kapers Holdings Pty... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] NSWDC 622
- Decision Date
CaseChat Overview and Summary
The primary legal issues the court had to decide were whether the contractual provisions for variations had been altered, whether an implied term was incorporated through the parties' prior course of dealing, and whether the owner's claims for defective works were time-barred. Additionally, the court needed to determine whether the alleged defects were design defects, if the owner intended to rectify the defects, and if the proposed rectification works were reasonable. The court also had to consider whether the building experts' evidence, which conflicted on several issues, was reliable and whether it was prudent for experts to confer and jointly produce a report before a hearing.
In resolving these issues, the court examined the contractual documents, the course of dealing between the parties, and the evidence provided by the building experts. The court found that the variation provisions in the contract were not themselves varied, and no implied term was incorporated through prior dealings. The owner's claims for defects were limited in time, and the defects did not appear during the defects liability period, thus the builder was not liable for design defects. Regarding the claim for rectification costs, the court found that the owner intended to rectify the defects, and the proposed works were reasonable. The court highlighted the desirability of practitioners ensuring building experts confer and jointly produce a report prior to the hearing to avoid conflicting evidence.
The court made several orders, including dismissing the owner's claims for variation costs and defective works, with each party bearing their own costs. The court also directed the parties to confer and, if possible, jointly produce a report from their experts for any future hearings.
Orders
Orders of the court
See paragraphs 346-350
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.