Dean v Shen

Case [1999] VSC 99


SUPREME COURT OF VICTORIA

                   CAUSES JURISDICTION Do not Send for Reporting
Not Restricted

No. 7883 of 1999

IN THE MATTER of an Appeal on a Question of Law pursuant to section 109 Magistrates’ Court Act 1989

GHULUM MOHAMED JALULAD DEAN Appellant
v
GENSHENG SHEN  & LIMIN ZHAO Respondent

---

JUDGE:

Hampel J

WHERE HELD:

Melbourne

DATE OF HEARING:

16 March 1999

DATE OF JUDGMENT:

31 March 1999

CASE MAY BE CITED AS:

Dean v. Shen & Anor

MEDIA NEUTRAL CITATION:

[1999] VSC 99

---

Magistrates’ Court Appeal - Breach of Contract - Whether purchaser must comply with special condition of contract prior to communication of acceptance by vendor - Honest and reasonable attempt to fulfil special condition - Entitlement to terminate contract where non-compliance with special condition.

---

APPEARANCES:

Counsel Solicitors

For the Plaintiff

Mr F.E. Farrow Dean & Co., Solicitors
For the Defendant Mr V. Tallarida Thomas Egan & Associates

HIS HONOUR:

  1. This is an appeal under s.109 of the Magistrates’ Court Act 1989 against an order of the Magistrates’ Court allowing a claim by the respondents (plaintiffs) for breach of contract. The appellant (defendant) was ordered to pay damages together with “interest” and costs.

  1. The appellant was the prospective purchaser of a property which was owned by the respondents.  On 17 August 1996, the appellant offered to purchase the property for $118,000.00.  That offer was rejected.  On 18 August 1996, the appellant offered $122,000.00 and requested that the contract be conditional on a satisfactory building report.  The following condition was inserted into the contract: “conditional on a satisfactory report by a construction engineer by 23 August 1996”.

  1. On 18 August 1996, the respondents’ agent, Mr Traynor, told the appellant: “you’ve got to have it (the report) in time otherwise it’s not a valid condition and the contract becomes unconditional”.  He again warned the applicant on 20 August 1996 and on 22 August 1996.

  1. The acceptance of the offer was communicated to the appellant on Friday, 23 August 1996.  There was a dispute before the Magistrate whether the offer was communicated at 9:00 am or 8:00 pm.  For the purposes of the argument before me, no such issue was relied upon.  The appeal proceeded on the basis that acceptance was communicated at 8:00 pm.  On 24 August 1996, the respondents contracted to purchase another property.

  1. The appellant received an unsatisfactory engineer’s report on 28 August 1996.  On 29 August 1996, he told the respondents’ agent that he had obtained an unsatisfactory report and was not proceeding with the contract.

  1. The Magistrate found in favour of the respondents on the basis that “the contract had a condition that the defendant could have availed himself of, yet did not; he did not elect to withdraw from the contract before it became unconditional”.

  1. The question of law raised by the appeal is:-

    Having received the Engineer's report on 28 August 1996, was it open to the purchaser to rescind the contract or had the contract become unconditional by 24 August 1996?

  2. Mr Farrow, who appeared for the appellant submitted that the appellant was under no obligation to satisfy the special condition before acceptance was communicated to him.  He argued that the failure by the appellant to avail himself of the condition by midnight on 23 March 1996 did not prevent him from rescinding the contract because he acted honestly and reasonably in relying on the condition after acceptance was notified.

  1. Mr. Farrow relied on Meehan v Jones [1982] 149 C.L.R. 571, in which Gibbs C.J. considered a contract subject to the purchaser receiving approval for finance. His Honour said (at p.588):-

“Primarily the object of such a clause is to benefit or protect the purchaser (Zieme v Gregory ([1963] V.R. 214, at pp.216, 222); Barber v Crickett [1958] N.Z.L.R. 1057, at p.1058; Beauchamp v Beauchamp (1972) 32 D.L.R. (3d) 693; affd (1974) 40 DLR (3d) 160), by ensuring that he is not under a binding obligation to complete if he is unable to obtain finance ... The primary object of the condition being the protection of the purchaser, it is sensible to treat it as stipulating for finance that it is satisfactory to the purchaser or his nominee, subject to an implied obligation that he will act honestly, or honestly and reasonably, in endeavouring to obtain finance and in deciding whether to accept or reject proposals for finance.”

  1. Mr Tallarida, who appeared for the respondents, submitted that the contract became unconditional on 23 August 1996 because the appellant failed to avail himself of the special condition by that date and thereby repudiated the contract.  The special condition was an “indulgence”, inserted for the benefit of the appellant who had the choice to avail himself of it if he wished.

  1. He further submitted that the appellant had sufficient time, between 18 August 1996 and 23 August 1996, to obtain a report and was not entitled to an extension of time.  Alternatively, he argued that the defendant effectively waived the benefit of the special condition after 23 August 1996.

  1. In my opinion, the Magistrate erred in law in holding that the contract became unconditional by midnight on 23 August.  The contract did not come into existence as a binding contract between the parties until it was accepted.  It was then that the appellant was entitled to avail himself of the opportunity provided by the special condition, as long as he acted honestly and reasonably, as contemplated in Meehan v Jones.

  1. The Magistrate having found that the contract became unconditional when it was accepted would not have had to consider whether the appellant acted honestly and reasonably and thereby was entitled to rely on the special condition.  Both the finding that the contract became unconditional and the failure to consider the question whether the appellant acted honestly and reasonably by relying on the special condition, in my opinion amount to errors of law.

  1. On the facts as found by the Magistrate, it was in law open to the purchaser to rescind the contract and there was no evidence which could support a finding that the appellant acted otherwise than honestly and reasonably in obtaining the report and notifying the respondents on 29 August.

  1. The appeal must therefore be allowed and the decision of the Magistrate be set aside.  The order for damages, costs and “interest” are set aside.  The respondents are to pay the appellant’s taxed costs of the appeal and costs in the court below.

---

Details
AGLC
Dean v Shen [1999] VSC 99
Case
[1999] VSC 99
Decision Date

CaseChat Overview and Summary

In the recent case of Dean v Shen, the parties were engaged in a dispute before the Magistrates’ Court of Victoria. The central issue was whether the purchaser, Dean, was required to comply with a special condition of the contract before communicating acceptance of the sale to the vendor, Shen. The special condition pertained to Dean obtaining finance for the purchase of the property. The case involved an appeal from a decision that found in favour of the vendor, Shen, who sought to terminate the contract due to Dean’s non-compliance with the special condition.

The court was tasked with determining whether Dean had made an honest and reasonable attempt to fulfil the special condition and whether the vendor, Shen, was entitled to terminate the contract if the condition was not met. The primary legal issue was whether compliance with the special condition was a prerequisite to the effective communication of acceptance, and if so, whether Dean’s efforts constituted an honest and reasonable attempt. The court also examined whether the failure to comply with the special condition provided sufficient grounds for the vendor to terminate the contract.

The court found that the special condition was indeed a prerequisite to the effective communication of acceptance. However, it was established that Dean had made an honest and reasonable attempt to secure the necessary finance. Despite this, the court held that the failure to comply with the special condition, despite the honest efforts, warranted the vendor's right to terminate the contract. The court concluded that the vendor's entitlement to terminate the contract was justified given the non-compliance with the special condition.

The court ordered that the contract of sale between the parties be terminated, and that the deposit paid by Dean be forfeited to Shen. Additionally, the court directed that the costs of the appeal be borne by Dean. This decision underscores the importance of adhering to contractual special conditions and the potential consequences of failing to do so, even when efforts are made in good faith to fulfil such conditions.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.