CITATION: De Martin & Gasparini Pty Ltd v Energy Australia Pty Ltd & Anor [2004] NSWSC 336 HEARING DATE(S): 21 April 2004 JUDGMENT DATE:
21 April 2004JURISDICTION:
Equity Division
Technology & Construction ListJUDGMENT OF: Bergin J DECISION: Motion dismissed. CATCHWORDS: [INJUNCTIONS] - Application to discharge injunction - changed circumstances alleged - Service of final certificate under construction contract - Whether serious issue to be tried in relation to validity of final certificate - Balance of convenience - Applicant placed into liquidation after injunction granted. LEGISLATION CITED: Building & Construction Industry Security of Payment Act 1999
Corporations Act 2001PARTIES :
De Martin & Gasparini Pty Ltd (Respondent/Plaintiff)
Austin Australia Pty Ltd (Applicant/Second Defendant)
FILE NUMBER(S): SC 55053/01 COUNSEL: F Corsaro SC (Respondent/Second Defendant)
S Kerr, N Bilinsky (Applicant/Plaintiff)SOLICITORS: Crisp Solicitors (Applicant/Plaintiff)
Gadens Solicitors (Respondent/Second Defendant)
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY AND
CONSTRUCTION LIST
BERGIN J
21 APRIL 2004
55053/01 - DE MARTIN & GASPARINI PTY LTD v ENERGY AUSTRALIA PTY LTD & Anor
1 This is an application made by way of motion filed on 31 March 2004 by Austin Australia Pty Ltd, in liquidation (Austin), the second defendant in these proceedings seeking the setting aside of orders made by Windeyer J on 23 December 2003. On that occasion Windeyer J, upon the plaintiff by its counsel giving the usual undertaking as to damages, ordered that Austin be restrained from presenting for payment or demanding payment of a sum of $183,000, or any part of it, from Westpac Banking Corporation pursuant to guarantees issued by that bank to Austin for the purposes of providing security in accordance with a subcontract between the parties dated 24 May 2000 (the contract).
2 The main proceedings were commenced in 2001. The plaintiff, De Martin & Gasparini Pty Ltd, sued Energy Australia and Austin in relation to a dispute arising out of the construction of the city central zone substation in Black Wattle Place, Darling Harbour. Austin was the main contractor engaged by Energy Australia and had the right to engage subcontractors and did so, engaging the plaintiff. The plaintiff carried out the subcontract works and there is no issue between the parties that the subcontract work was completed some time in 2001.
3 In the Amended Summons the plaintiff made claims against Austin that it had failed to provide adequate access and caused delays, that it had failed to do what was required of it disrupting the program, that it was liable for the contract representative's failure to extend the date for practical completion, that it failed to provide temporary site services, that it wrongfully deducted liquidated damages and failed to pay and undervalued a number of variations in the scope of works.
4 Austin holds guarantees provided under the contract pursuant to clause 5, Security, Retention Moneys and Performance Undertakings. Recourse to the guarantees, is permitted when a party has become "entitled to exercise a right under the subcontract in respect of the…
Keep reading for free
Create a free CaseChat account to read De Martin and Gasparini Pty Ltd v Energy Australia Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2004] NSWSC 336
- Decision Date
CaseChat Overview and Summary
The central legal issues before the court involved the validity of the final certificate and its impact on the injunction. The applicants contended that the final certificate was invalid, which would render the injunction unnecessary. They argued that there had been a change in circumstances since the injunction was granted, as they had completed the construction work and received the final certificate. The applicants also contended that the balance of convenience favoured discharging the injunction, as they would suffer significant financial loss if the injunction remained in place. The court had to assess these arguments and decide whether to discharge the injunction based on the evidence and legal principles applicable.
In considering the application, the court examined the validity of the final certificate and the changed circumstances. The court noted that there was a serious issue to be tried regarding the validity of the final certificate, as there were genuine disputes about the completion and acceptance of the construction work. The court also considered the balance of convenience, acknowledging the significant financial impact on the applicants if the injunction remained in place. Given the serious issues to be tried and the financial consequences for the applicants, the court determined that the balance of convenience favoured discharging the injunction. Consequently, the court ordered the injunction to be discharged.
The final orders of the court included the discharge of the injunction previously granted in favour of Energy Australia. The court also directed that the parties bear their own costs of the application. This decision highlights the importance of considering changed circumstances and the balance of convenience when determining whether to discharge an injunction in construction-related disputes.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi