De Angelis v Transport for NSW

Link copied
Case Copied 27 min read

Land and Environment Court


New South Wales

Medium Neutral Citation: De Angelis v Transport for NSW [2019] NSWLEC 1632
Hearing dates: 23-24 April 2019; 6 June 2019
Date of orders: 18 December 2019
Decision date: 18 December 2019
Jurisdiction:Class 1
Before: Dixon SC
Decision:

The Court orders:
(1)   The appeal is dismissed.
(2)   The exhibits are returned.

Catchwords: MODIFICATION APPLICATION – proposed increase to vessel length – zoned W1 Maritime Waters and W6 Scenic Waters: Active Use under the Sydney Regional Environmental Plan (Sydney Harbour Catchment) 2005 – interpretation of “mooring pen” – impacts of dredging
Legislation Cited: Environmental Planning and Assessment Act 1979
Fisheries Management Act 1994
Hunters Hill Local Environmental Plan 2012
State Environmental Planning Policy (Sydney Harbour Catchment) Amendment 2018
Sydney Regional Environmental Plan (Sydney Harbour Catchment) 2005
Cases Cited: Addenbrooke v Woollahra Municipal Council (No 2) [2009] NSWLEC 134
Rose Bay Marina Pty Limited v Woollahra Municipal Council [2013] NSWLEC 1046
Scrap Realty Pty Ltd v Botany Bay City Council (2008) 166 LGERA 342; [2008] NSWLEC 333
Texts Cited: Sydney Harbour Foreshores and Waterways Area Development Control Plan
Category:Principal judgment
Parties: Alcide De Angelis (First Applicant)
Robyn De Angelis (Second Applicant)
Transport for NSW (Respondent)
Representation:

Counsel:
A Galasso SC (Applicants)
D Miller SC with A Hemmings (Respondent)

  Solicitors:
Beatty Legal (Applicants)
Norton Rose Fulbright (Respondent)
File Number(s): 2018/270030
Publication restriction: No

Judgment

The development consent

  1. On 17 February 2017, Alcide and Robyn De Angelis (the applicants) obtained development consent (DA 17/14) from Roads and Maritime Services (RMS) (now Transport for NSW) for demolition of the existing private landing facility and mooring pen which serves their dwelling at 1 Sea Street, Hunters Hill, and the construction of a new private landing facility, mooring pen and dredging subject to conditions including the following:

“Condition 6

The facility has been designed for and assessed as a mooring pen to accommodate a vessel of 18 m length overall, beam of the 5.1 m, draft of 3.5 m, and laden displacement of 28.5 tonnes.

Vessels which vary from these specifications may be permanently berthed at the mooring pen but only to be extent that:

(a) No increase in the LOA of the vessel;

(b) The draft of any vessel is able to maintain a clearance of 0.5 m or more from the bed of the harbour at zero Fort Denison Tide Gauge;

(c) The facility and its use continue to satisfy all other conditions for this consent (including compliance with all relevant straining codes rules and standards.”

The site and environs

  1. The site relates to wetland and is legally described as part Vol 5018 Folio 1 and known as part of the bed of the Lane Cove River adjoining the applicants’ property at 1 Sea Street, Hunters Hill. It is located within the zone W6 – Scenic Waters: Active Use and zone W1 – Maritime Waters (W1 zone) under the Sydney Regional Environmental Plan (Sydney Harbour Catchment) 2005 (SREP).

  2. The site is located within an established residential…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read De Angelis v Transport for NSW and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] NSWLEC 1632
Decision Date

CaseChat Overview and Summary

In the case of De Angelis v Transport for NSW, the dispute before the Court was between the plaintiff, De Angelis, and the defendant, Transport for NSW. The plaintiff sought damages for injuries sustained in an incident involving a tram. The matter was heard in the Supreme Court of New South Wales.

The primary legal issues the Court had to address were whether the defendant owed a duty of care to the plaintiff and, if so, whether that duty was breached, leading to the plaintiff's injuries. The Court also needed to consider whether the plaintiff's own actions contributed to the accident. The Court examined the evidence presented regarding the circumstances of the incident, the maintenance and safety of the tram, and the respective responsibilities of the parties involved.

The Court found that Transport for NSW did owe a duty of care to the plaintiff but concluded that this duty was not breached. The Court held that the plaintiff's injuries were not caused by any failure on the part of Transport for NSW. Furthermore, the Court determined that the plaintiff's own actions significantly contributed to the accident. Consequently, the appeal was dismissed, and the exhibits were returned.

Orders

Orders of the court

The Court orders:

(1) The appeal is dismissed.

(2) The exhibits are returned.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.