DAVIES v Capital Homes Pty Ltd (Civil Dispute)

Link copied
Case Copied 14 min read

ACT CIVIL & ADMINISTRATIVE TRIBUNAL



DAVIES & ANOR v CAPITAL HOMES PTY LTD (Civil Dispute) [2017] ACAT 111

XD 358/2017

Catchwords:              CIVIL DISPUTE – home building contract and statutory warranties – cause of defects – statutory warranty for structural works breached – damages to rectify

Legislation cited:      Building Act2004 ss 38, 84, 88

Subordinate
Legislation:               Building Code of Australia 2016 ss 3.5.2.3, 3.5.2.4

Building (General) Regulation 2008 ss 31, 38

Cases cited:Belgrove v Eldridge (1954) 90 CLR 618

Dunn v Hanson Australasia Pty Ltd [2017] ACTSC 169
Kirkby v Coote [2006] QCA 61

Tribunal:                   Senior Member L Beacroft

Date of Orders:  22 December 2017

Date of Reasons for Decision:         22 December 2017

AUSTRALIAN CAPITAL TERRITORY  )

CIVIL & ADMINISTRATIVE TRIBUNAL       )          XD 358/2017

BETWEEN:

PRUE DAVIES and BENJAMIN JOHN DAVIES

Applicants

AND:

CAPITAL HOMES PTY LTD

Respondent

TRIBUNAL:Senior Member L Beacroft

DATE:22 December 2017

ORDER

The Tribunal orders that:

1.Prue Davies is joined as an applicant

2.The respondent is to pay the applicants the sum of $9,964 by COB 9 February 2018.

………………………………..

Senior Member L Beacroft

REASONS FOR DECISION

1.Benjamin John Davies and Prue Davies (the applicants) signed a ACT Home Building Contract[1] (the contract) on 2 March 2014 with Capital Homes Pty Ltd (the respondent) to build a home at Coombs, ACT. The applicants filed an initial application with the ACT Civil and Administrative Tribunal dated 30 March 2017, seeking $9,964 to rectify certain works to an area described in the floor plan as the “alfresco” area[2], and for re-imbursement of filing and search fees. The respondent filed a response dated 1 May 2017 seeking that the application be dismissed. The Tribunal’s final orders are set out above, and the reasons for these orders are set out below.

Conduct of the hearing

[1] Exhibit A2, initial hearing, dated 9 August 2017

[2] AO2, floor plan, Dray Drafting, submitted to the Tribunal by the applicant on 15 August 2017 

2.While Mr Davies was initially the only applicant, given Ms Davies was also a party to the contract she has been joined as an applicant in these proceedings. No party opposed this order by the Tribunal. 

3.An initial hearing was held on 9 August 2017, and the hearing was adjourned to 1 September 2017 (the hearing) to allow key witnesses to be available and further evidence to be filed and served. Prior to and after the hearing the parties exchanged and filed various documents setting out their contentions and supporting evidence. During the hearing the following persons gave oral evidence: the applicant, Mr Benjamin Davies; Mr Josh Veliscek who is a director of the respondent company and the builder for the works; Mr Adam Mokotupu from Laser Plumbing who was the author of a roof inspection report, dated 5 August 2016[3]; Vince Buonopane from 1800 Tap Fix who was the author of a report about the roof (undated) submitted by the respondent on 21 July 2017[4] following an…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read DAVIES v Capital Homes Pty Ltd (Civil Dispute) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] ACAT 111
Decision Date

CaseChat Overview and Summary

The matter of Davies versus Capital Homes Pty Ltd was heard by the Tribunal. The applicant, Prue Davies, sought compensation from the respondent for damages incurred during the construction of a home. The dispute centred around alleged breaches of contract by the respondent, including delays and substandard workmanship. The Tribunal was tasked with determining whether the respondent was liable for the damages claimed and, if so, the appropriate amount of compensation.

The central legal issues before the Tribunal were whether the respondent had breached the contract by causing delays and substandard workmanship and, if so, the extent of the damages. The applicant argued that the respondent had failed to meet the contractual obligations in relation to the timelines and quality of the construction work, which resulted in additional costs and inconvenience. The respondent, on the other hand, contended that any delays were due to factors beyond their control and that the quality of the work met the contractual standards.

The Tribunal found that the respondent had indeed breached the contract by causing delays and substandard workmanship. The Tribunal noted that the respondent had failed to provide adequate justification for the delays and had not taken reasonable steps to mitigate the impact of those delays on the applicant. Furthermore, the Tribunal concluded that the respondent's workmanship did not meet the contractual standards, leading to additional costs for the applicant. As a result, the Tribunal ordered the respondent to compensate the applicant for the damages incurred.

Orders

Orders of the court

The Tribunal orders that:

1. Prue Davies is joined as an applicant

2. The respondent is to pay the applicants the sum of $9,964 by COB 9 February 2018.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established