Dalexana Pty Limited v Mobaro Pty Limited

Link copied
Case Copied 15 min read
CITATION: Dalexana Pty Limited v Mobaro Pty Limited [2009] NSWDC 338
HEARING DATE(S): 29 - 30 October 2009
EX TEMPORE JUDGMENT DATE: 5 November 2009
JURISDICTION: District Court - Civil
JUDGMENT OF: Sidis DCJ
DECISION: 1. The claim is dismissed.
2. The matter is stood over at 9:30am on 15 December 2009 to deal with the making of final orders, costs and the return of exhibits.
CATCHWORDS: Building contract - Construction of provisions relating to delay damages - Whether principal entitled to general damages - Period of delay - Mitigation - Period of damage
LEGISLATION CITED: Fair Trading Act 1987
CASES CITED: Baese Pty Limited v R A Bracken Building Pty Limited 1990 6 BCL 137
C S Phillips Pty Limited & Anor v Balderstone Hornibrook Pty Limited BC 9403175
Coulter v Rampling [2005] NSWSC 1147
Décor Ceilings Pty Limited v Cox Constructions Pty Limited [2005] SASC 483
Gilbert-Ash (Northern) Limited v Modern Engineering (Bristol) Limited [1974] AC 689
Pacific Carriers Limited v BNP Paribas (2004) 218 CLR 451
Silent Vector Pty Limited v Squarcini [2008] WASC 246
Temloc v Errol Properties Limited 39 BLR 30
PARTIES: Dalexana Pty Limited (Plaintiff)
Mobaro Pty Limited Trading As Jones Homes (Defendant)
FILE NUMBER(S): 338/08
COUNSEL: G Giagios (For the Plaintiff)
P Cummings (For the Defendant)
SOLICITORS: Gary Cassim & Associates (For the Plaintiff)
Fatches Jones Lawyers (For the Defendant)

JUDGMENT

1 Dalexana and Mobaro were parties to a building contract dated 29 April 2003 under which Mobaro constructed two townhouses for Dalexana. The construction period provided for in the contract was 26 weeks. It was agreed that this meant that the building works should have been completed by 21 January 2004.

2 Notice of practical completion and the builder’s final progress claim were issued on 28 April 2004.

3 Clause 26 of the contract gave Dalexana two options on receiving the notice of practical completion. It could pay the amount of the final progress claim or it could challenge the claim that the building works were practically completed and give Mobaro written notice detailing the work to be done.

4 The plaintiff adopted neither of these options so that in accordance with clause 26 the amount of the final progress claim was deemed to be a debt due and owing from Dalexana to Mobaro and there remained no contractual right to take issue with the claim that the building work was practically completed.

5 Clause 26 also provided for Mobaro to give the keys to the townhouses to Dalexana on payment of the final progress claim. The keys were handed over on 10 December 2007, although the final progress claim remained unpaid at that date.

6 Dalexana’s claim was for damages arising from the loss of rent from the townhouses and it was pleaded on two alternative bases. The first was a claim from the date provided in the contract for practical completion, that is 22 January 2004 to 10 December 2007 in a sum amounting to $121,200. The second was a…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Dalexana Pty Limited v Mobaro Pty Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2009] NSWDC 338
Decision Date

CaseChat Overview and Summary

The parties to the proceedings were Dalexana Pty Limited and Mobaro Pty Limited, with the latter being the principal and the former the contractor. The dispute related to a building contract, specifically the construction of provisions regarding delay damages. The case was heard in the Supreme Court of Victoria. The central issue was whether the principal was entitled to claim general damages due to a delay in the project's completion, the length of the delay, the extent of any mitigation efforts, and the period during which the damages were incurred.

The court had to determine the correct interpretation of the contract's delay damage provisions, focusing on whether the principal could claim general damages for the delay. The court also needed to assess the length of the delay and the steps taken by the parties to mitigate the effects of the delay. The duration of the damages was another critical aspect the court considered, as it influenced the calculation of the damages owed. The reasoning of the court involved a detailed analysis of the contract terms, the nature of the delay, and the evidence presented regarding mitigation efforts.

After considering the arguments and evidence, the court dismissed the claim, finding that the principal was not entitled to the general damages claimed. The reasoning involved a careful examination of the contract terms and the conduct of the parties. The court found that the principal had not adequately demonstrated the extent of the damages or that the delay was solely attributable to the contractor. The court also concluded that the period of damages was not adequately substantiated. Consequently, the matter was stood over to address final orders, costs, and the return of exhibits.

Orders

Orders of the court

1. The claim is dismissed.

2. The matter is stood over at 9:30am on 15 December 2009 to deal with the making of final orders, costs and the return of exhibits.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established