Dalby Constructions Pty Ltd v Queensland Building and Construction Commission

Link copied
Case Copied 44 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Dalby Constructions Pty Ltd v Queensland Building and Construction Commission & Ors [2025] QCAT 75

PARTIES:

DALBY CONSTRUCTIONS PTY LTD

(applicant)

v

QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION

(first respondent)

ZELJKO VRABEL

(second respondent)

LJILJANA VIDOVIC

(third respondent)

APPLICATION NO:

GAR120-23

MATTER TYPE:

General administrative review matters

DELIVERED ON:

26 February 2025

HEARING DATE:

23 October 2024

HEARD AT:

Brisbane

DECISION OF:

Member Chapple

ORDERS:

1.     The internal review decision of the Queensland Building and Construction Commission dated 17 January 2023 is set aside and replaced with a decision by the Tribunal that the Contract was not validly terminated.

2.     No order as to costs.

CATCHWORDS:

ADMINISTRATIVE LAW – GENERAL ADMINISTRATIVE LAW – application by builder to review a decision by QBCC that homeowner validly terminated the contract having the consequence of allowing a claim for non-completion under the Queensland Home Warranty scheme

Queensland Building and Construction Commission Act 1991 (Qld), s 86(1)(i), s 86A(1), s 86E, s 87, Sch 1B

Queensland Building and Construction Commission Regulation 2018 (Qld), Sch 6

Queensland Civil and Administrative Tribunal Act 2009 (Qld)

Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (1989) 166 CLR 623

APPEARANCES & REPRESENTATION:

Applicant:

Mr C H Matthews, instructed by All Building Law

First respondent:

Mr R Ensbey SC, Gadens

Second and third respondents:    


MS M CAMPBELL, HEARTHSTONE LEGAL

REASONS FOR DECISION

Background

  1. This is an application by the applicant, Dalby Constructions Pty Ltd (‘Dalby Constructions’) for the review of an internal review decision made by the first respondent, Queensland Building and Construction Commission (‘the Commission’) dated 17 January 2023 confirming the original decision of the Commission made on 27 October 2022 that the domestic building contract between Dalby Constructions and the second respondents, Zeljko Vrabel and Ljiljana Vidovic (‘Vrabel and Vidovic’), the homeowners, was validly terminated for incomplete work. As a result, the claim by Vrabel and Vidovic under the statutory insurance scheme (known as the Queensland Home Warranty Scheme) was accepted by the Commission in full.

  2. Part 2 of Schedule 6 of the Queensland Building and Construction Commission Regulation 2018 (Qld) provides for assistance to the homeowner where the building work is carried out under a fixed price residential contract, the contract ends within two years after the day work starts under the contract, and the work is incomplete. Section 4(1)(a) of Schedule 6 provides that a fixed price residential contract ends if the contract is validly terminated on the default of the licensed contractor.

  3. Section 86(1)(i) of the Queensland Building and Construction Commission Act 1991 (Qld) (‘the QBCC Act’) provides that a decision that a domestic building contract has been validly terminated having the consequence of allowing a claim for non-completion under the statutory insurance scheme is a reviewable decision. Section 86A(1) confers the right to internal review of that decision, and by section 86E, an internal review decision is also a reviewable decision. Section 87 confers the right to apply to the Tribunal, as provided under the Queensland…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Dalby Constructions Pty Ltd v Queensland Building and Constr... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] QCAT 75
Decision Date

CaseChat Overview and Summary

Dalby Constructions Pty Ltd sought judicial review of a decision by the Queensland Building and Construction Commission (QBCC) that a homeowner had validly terminated a construction contract under the QBCC New Home Construction Contract. The homeowner, Mr Zjelko Vrabel, had terminated the contract on the basis that Dalby Constructions Pty Ltd had not commenced work on the scheduled start date, and had not completed the work within the completion period. Dalby Constructions Pty Ltd argued that the homeowner did not have the right to terminate the contract, and that the QBCC had erred in its decision. The key legal issues were whether the homeowner had the right to terminate the contract under the terms of the contract, and whether the QBCC had made an error of law in its decision. The court found that the homeowner did not have the right to terminate the contract as the starting date and completion period had not been agreed upon by the parties. The court also found that the QBCC had erred in its decision by failing to consider the evidence properly. The court set aside the QBCC's decision and replaced it with a decision that the contract was not validly terminated. The court made no order as to costs.

Orders

Orders of the court

1. The internal review decision of the Queensland Building and Construction Commission dated 17 January 2023 is set aside and replaced with a decision by the Tribunal that the Contract was not validly terminated.

2. No order as to costs.

Background

Background to the litigation

Evidence

Evidence Before The Court

I am satisfied the Tribunal has jurisdiction to hear and decide this application.The evidence Mr Shane Dalby, a director of Dalby Constructions, filed two signed statements of evidence dated 22 June 2023 and 22 August 2023 in respect of which he gave oral evidence at hearing. Mr Zjelko Vrabel filed one signed statement of evidence dated 27 July 2023 in respect of which he gave oral evidence at hearing. The Commission’s statement of reasons for the decision under review and other documentary evidence filed by the parties prior to hearing are contained in the paginated three-volume hearing book filed in the Tribunal on 18 October 2024. The Form 6 Decision Notice Approval dated 16 December 2020 was filed post hearing and agreed by the parties to form part of the evidence. Screen shots of certain text messages from “Concreter Dan” dated 22 July 2022, and 5 and 6 September 2022 were filed post hearing and agreed by the parties to form part of the evidence.The Contract Dalby Constructions and Vrabel and Vidovic entered into and signed a QBCC New Home Construction Contract on 31 October 2020 for the construction of a highset dwelling at 33 Eyre Street, Mt Gravatt East in the state of Queensland at a contract price of $538,431 (‘the Contract’). Item 2 of the schedule to the Contract provides for the payment of a deposit in the amount of $26,921.55. Item 6 of the schedule to the Contract provides for a completion period of 268 days from the starting date to the date for practical completion comprised of: 170 business days for construction of the works; 10 business days’ allowance for inclement weather; and 88 non-working days (including weekends and public holidays). Item 5 of the schedule to the Contract dealing with the starting date is not completed. Item 7 of the schedule to the Contract dealing with the date for practical completion is not completed. Below, where the date can be inserted, there is an alternative option, which reads: “Completion Period of ____ calendar days (see Schedule Item 6) from the Starting Date or the date on which the work under the Contract is commenced, whichever is the earlier”. Item 8B of the schedule to the Contract provides for progress payment stages as follows:Stage 1: Base stage 25% $134607.75Stage 2: Frame stage 20% $107686.20Stage 3: Enclosed stage 25% $134607.75Stage 4: Fixing stage 20% $107686.20Practical Completion stage 5% $26921.55 The dollar amount in Item 10 of the schedule to the Contract dealing with liquidated damages for each calendar day of delay in achieving practical completion is completed as ‘$NIL’. Clause 24.2 of the General Conditions to the Contract provides that if item 10 is left blank, the default amount of $50 per day shall apply. Item 15 of the schedule to the Contract provides that the plans are supplied by the owner and the specifications and foundations data are supplied by the contractor. The “Specifications & Inclusions” are set out over two pages signed by the parties and annexed to the Contract. They cover 21 aspects of the construction in varying degrees of particularity. Relevant to the matters in dispute are the following particulars:Concrete slab:Steel reinforced concrete slab to engineer’s footing and slab designFull termite protection to AS standardN.B. Excavation of rock and removal of excess soil will incur an extra costFront porch/balcony/patio:Colourbond roof, fully lined ceiling and tiling to floorLandscaping and other:Slab for shed

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established