Dagenham Nominees Pty Ltd v Shanks

Link copied
Case Copied 51 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Full Court)

DAGENHAM NOMINEES PTY LTD v SHANKS

[2012] SASCFC 41

Judgment of The Full Court

(The Honourable Chief Justice Doyle, The Honourable Justice Anderson and The Honourable Justice White)

26 April 2012

CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES - CONSTRUCTION AND INTERPRETATION OF CONTRACTS - IMPLIED TERMS - GENERALLY

SALE OF GOODS - CONDITIONS AND WARRANTIES - IMPLIED CONDITIONS AND WARRANTIES - QUALITY OR FITNESS FOR PARTICULAR PURPOSE - FITNESS FOR PARTICULAR PURPOSE - IN GENERAL

EVIDENCE - BURDEN OF PROOF, PRESUMPTIONS, AND WEIGHT AND SUFFICIENCY OF EVIDENCE - GENERALLY - ONUS OF PROOF - OTHER MATTERS

DAMAGES - GENERAL PRINCIPLES - MITIGATION OF DAMAGES - WHAT MATTERS MAY BE CONSIDERED

Appellant designed, supplied and installed the mast and rigging for a 56 foot racing yacht. The mast broke during a race.

Whether mast installed was fit for its purpose - whether the way in which the yacht was sailed caused or contributed to the mast failure - whether trial judge correctly found the mast was not fit for its purpose because of lack of strength in spreader and mast - whether respondent failed to mitigate its loss - whether trial judge correct on onus of proof.

Held: Trial judge correctly held that the cause of the broken mast was the insufficient strength of the spreader and mast - there was expert evidence to support the findings of the trial judge - mast not fit for its purpose, the trial judge correctly held that the manner of sailing did not cause or contribute to the broken mast - the respondent did not fail to mitigate its loss - judge erred in discussing onus of proof but correctly decided that the respondent had proved its case in any event.

Dagenham Nominees Pty Ltd v Shanks [2011] SADC 81; Dagenham Nominees Pty Ltd v Shanks [2003] SASC 219; Dagenham Nominees Pty Ltd v Shanks [2007] SASC 242; Sanpine v Koompahtoo Local Aboriginal Land Council [2005] NSWSC 365; J Kitchen & Sons Pty Ltd v Stewart's Cash and Carry Stores (1942) 66 CLR 116, considered.

DAGENHAM NOMINEES PTY LTD v SHANKS
[2012] SASCFC 41

Full Court:       Doyle CJ, Anderson and White JJ

  1. THE COURT:

    Introduction

  2. This is an appeal from a judgment of the District Court:  see Dagenham Nominees Pty Ltd v Shanks [2011] SADC 81. The Judge dismissed a claim by the appellant (Dagenham) for the unpaid costs of designing, manufacturing and installing a new mast for the respondent’s yacht. The Judge allowed a counter claim by the respondent (Dr Shanks) for the expenses incurred in replacing the mast. The mast had broken during a yacht race in Gulf St Vincent.

  3. Dagenham agreed with the respondent to design, supply and install a new mast and the associated rigging. There is no dispute that Dagenham knew the purpose of the new mast and rigging, namely, for use on a yacht in ocean racing including the Sydney to Hobart yacht race.  Dagenham admits…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Dagenham Nominees Pty Ltd v Shanks and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2012] SASCFC 41
Decision Date

CaseChat Overview and Summary

Dagenham Nominees Pty Ltd appealed a decision of the trial judge who found in favour of Dr Shanks. The dispute concerned the collapse of the mast and rigging of Dr Shanks' yacht, *Doctel Rager*, during a race. Dr Shanks alleged that the mast and rigging were not fit for their intended purpose, which included offshore yacht racing, and counterclaimed for the cost of replacement. Dagenham denied liability, asserting that Dr Shanks had mishandled the yacht and overloaded the mast and rigging.

The Full Court of the Supreme Court of South Australia was required to determine whether the trial judge had erred in finding that the mast and rigging supplied by Dagenham were not of merchantable quality or reasonably fit for the purpose of offshore yacht racing. The court also considered whether the trial judge had adequately addressed Dagenham's defence that Dr Shanks had failed to mitigate his loss by not recovering the mast.

The court reasoned that the trial judge's findings regarding the inadequacy of the mast's strength, particularly the lower starboard spreader, were well-supported by expert evidence. The judge accepted the evidence of Mr Dovell and Mr Mitchell, who concluded that the mast and spreader were substantially under strength for their intended purpose. The court found that Dagenham's attempts to challenge this evidence, including Mr Banwell's photographic survey regarding spreader fixation, were unconvincing and did not demonstrate error in the trial judge's findings. The court also noted that Dagenham had not provided expert evidence to counter the findings of inadequate strength.

The Full Court dismissed the appeal, upholding the trial judge's finding that Dagenham was liable for breach of contract. The court found that the mast and rigging were not fit for their intended purpose and that Dagenham had not established that Dr Shanks had failed to mitigate his loss. The trial judge's award of damages to Dr Shanks was therefore affirmed.

Background

Background to the litigation

The issue at trial was whether the mast and rigging supplied were reasonably fit for their intended purpose. That issue can be further refined to one of whether the mast and rigging had been manufactured with the requisite strength for ocean racing by Doctel Rager.Background Facts Dr Shanks is the owner of Doctel Rager, a 56ft sailing yacht. In February 2001 Dr Shanks was racing Doctel Rager in Gulf St Vincent, off Outer Harbour. During the race he changed course by performing a gybe. In the course of this manoeuvre Doctel Rager broached and the mast collapsed. A broach is a sudden change in direction of a yacht, involving the yacht turning broadside to the wind and becoming unbalanced. The mast was cut loose and sank. The Judge found that the mast failed because of the failure of the lower starboard spreader, and that this failed because it was not adequate to meet the loads that would be placed upon it. A spreader is a piece of wood or metal, attached to the mast of a vessel, that is used to spread apart the shrouds, a wire that runs from the top of the mast to each of the spreaders, on each side of the mast, and then is attached to the side of the vessel. The shrouds are part of the rigging used to hold the mast upright. Dagenham carried on a business which included the design, supply and installation of masts and associated rigging for yachts. It was retained by Dr Shanks. Between April 2000 and October 2000 Dagenham, through Mr Banwell, prepared the design, and supervised the construction and installation, of the mast in question. The mast was 22.85 metres in height. In preparing the design, Dagenham used a computerised design program developed by a naval architect, Scott Jutson. Dagenham issued proceedings in June 2001 claiming payment for its work. Dr Shanks counterclaimed for the cost of replacing the mast. He alleged that it was not fit for its intended purpose, which included offshore yacht racing, including races such as the Sydney to Hobart yacht race. Doctel Rager had raced in a number of Sydney to Hobart yacht races, and in other offshore races. Dagenham admitted that it agreed to design and supply and install such a mast. Dagenham denied that the mast failed by reason of it having inadequate strength, or because of any deficiency in its design, construction or installation. Dangenham alleged that Dr Shanks had mishandled Doctel Rager on the day in question. It alleged that he overloaded the mast and rigging by setting too much sail during the leg in question, and then by allowing Doctel Rager to broach as it did in the course of the gybe. Dagenham also alleged that Dr Shanks failed to take reasonable steps to minimise his loss by failing to recover the mast. The trial Judge found in favour of Dr Shanks, and awarded him damages of $69,643.21, after allowing for an offset in favour of Dagenham. Dagenham now appeals. The case has an unfortunate history. Dr Shanks was successful in an earlier trial, but on appeal the decision was set aside because the Judge had not made findings on matters essential to his conclusions: see Dagenham Nominees Pty Ltd v Shanks [2003] SASC 219. The case was remitted to the trial Judge for further hearing. Further evidence was given. The Judge again found for Dr Shanks. Dagenham again appealed, and again the Full Court found that the Judge’s reasons were inadequate: see Dagenham Nominees Pty Ltd v Shanks [2007] SASC 242. The Court ordered a retrial before a different Judge. The present appeal is against the decision in that retrial.Preliminary Comment

Decision

Reasons for decision

Finally, the fact that Mr Doherty’s computerised modelling could not explain the break of the mast raised issues about its utility. The fact of the matter was that the mast had broken as a result of the forces to which it and the rigging had been subject.The Judge’s Conclusions concerning the Strength of the Mast and Spreaders As noted earlier, Mr Dovell’s conclusions, based on his comparative analysis, were hardly contested at the trial. Nor was there any suggestion that Mr Mitchell’s recommendations involved a degree of over-engineering, or special purpose design. Mr Scragg’s submissions on appeal did not indicate any error by the Judge in her conclusion that the spreader and the mast as constructed by Dagenham were well below the strength which was appropriate. The Judge’s conclusion appears in the following passages:[87]… Both Mr Dovell and Mr Mitchell said that in particular the second panel of the mast was substantially under strength compared to Mr Mitchell’s calculations as cross checked by Mr Dovell. Mr Dovell said it was only 57% of the strength proposed by Mr Mitchell. Mr Dovell indicated his opinion that the most likely cause of mast failure was the failure of the first spreader on the starboard side. He said this was consistent with the photograph of damage of the remains of the mast.[88]The plaintiff did not call any expert evidence, beyond that given by Mr Banwell, on the topic of the strength of the mast or spreader. Despite the content of the Arup Water report there is no evidence from Mr Doherty that the designed strength of the mast or spreader was adequate. This was not his approach. He worked on the basis that his modelling did not suggest the spreader or mast should have broken given a range of different scenarios. Of course he was working on different data to that provided to Mr Mitchell and Mr Dovell a topic to which I will turn shortly.[89]Neither Mr Dovell nor Mr Mitchell’s evidence on this topic was shaken in cross examination and I accept it. Although the notice of appeal alleges 26 separate errors by the Judge, it did not include any complaint concerning the Judge’s findings contained in these passages. At the trial, Dagenham devoted much time to its challenge to the opinions of Mr Dovell and Mr Mitchell that there should not be rigid fixation of the spreader at its inboard end and that the rigid fixation meant that the spreaders had to be considerably stronger. This involved leading evidence as to the forces to which the spreader may be subject in a variety of configurations. Mr Banwell undertook a photographic survey of mast and spreaders attachments on various boats in November 2009 which indicated, he claimed, that it was not industry practice to have some form of pivot at the inner end of a spreader. The Judge regarded Mr Banwell’s photographic survey as of limited value as the tendered photographs did not display adequately the fixation method, the size of the boats or the construction of the various spreaders: at reasons [104].

Ratio Decidendi