Cyclone Constructions Pty Ltd v Queensland Building and Construction Commission

Case [2014] QCAT 3


CITATION: Cyclone Constructions Pty Ltd v Queensland Building and Construction Commission [2014] QCAT 003
PARTIES: Cyclone Constructions Pty Ltd
(Applicant)
v
Queensland Building and Construction Commission
(Respondent)
APPLICATION NUMBER: GAR084-13
MATTER TYPE: General administrative review matters
HEARING DATE: On the papers
HEARD AT:  Brisbane
DECISION OF: Member Howe
DELIVERED ON: 7 January 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1.   The application for a stay of the operation of the Scope of Works is refused
CATCHWORDS:

Application for a stay – insurance claim already processed and paid – grant of stay without purpose or utility

Queensland Building and Construction Commission Act 1991 s 86

Cyclone Constructions Pty Ltd v Queensland Building Services Authority [2012] QCAT 621
Cyclone Constructions Pty Ltd v Queensland Building Services Authority [2013] QCAT 484

APPEARANCES and REPRESENTATION (if any):

This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (QCAT Act).

REASONS FOR DECISION

Background

  1. By order made 12 September 2013 the Tribunal declared that Cyclone Constructions Pty Ltd had made application for review of the decision of the Commission about the amended Scope of Works to be undertaken under the statutory insurance scheme to rectify defective building work within the time required by s 86 of the Queensland Building and Construction Commission Act 1991.[1]

  2. Prior to that order being made, in March 2012 the Commission had sent a Notice of Potential Debt to Cyclone advising that a claim under the statutory insurance scheme had been approved and enclosing a Scope of Works covering the remedial work.

  3. Cyclone applied to the Tribunal to both review that decision and to extend time to enable it to make the application for review.  Both applications were dismissed[2] on the basis the application was out of time.

  4. Subsequently the Commission concluded more extensive remedial work was necessary to remedy the defective work than first estimated.

  5. A second Notice of Potential Debt with an amended Scope of Works was issued.  Cyclone applied for a review of the second Scope of Works and also applied for a stay to the operation of that Scope of Works.

  6. As stated, the Tribunal found on 12 September 2013 that Cyclone had made application for review of the amended Scope of Works within time.  The matter of the stay application was not dealt with at that time, and that is the matter presently requiring attention.

  7. The Commission submits the stay should be refused because there is no utility in making such an order.  The claim under the statutory insurance scheme has already been approved.  The rectification work has already been completed.  The rectification work has been paid for.

  8. The Commission accepted the owner’s claim under the statutory insurance scheme in a timely fashion because amongst other things there was the potential for further deterioration in the dwelling.  There was nothing objectionable in that.  Indeed the owner probably thought it was only appropriate.

  9. There was unfortunate confusion in Cyclone’s application for review of the Scope of Works and notice of the review was only given to the Commission subsequent to acceptance of the owner’s claim under the insurance. 

  10. The extent of Cyclone’s liability will appropriately be determined during the review of the Scope of Works application.  There is no utility or sense in ordering a stay in the operation of the Scope of Works at this late stage[3].

  11. The application for a stay should be refused.


Details
AGLC
Cyclone Constructions Pty Ltd v Queensland Building and Construction Commission [2014] QCAT 3
Case
[2014] QCAT 3
Decision Date

CaseChat Overview and Summary

Cyclone Constructions Pty Ltd applied to the Queensland Civil and Administrative Tribunal (QCAT) to review a decision by the Queensland Building and Construction Commission regarding the amended Scope of Works required to rectify defective building work under the statutory insurance scheme. The Commission had already approved the claim and completed the rectification work, and payment had been made. Cyclone sought a stay of the operation of the amended Scope of Works. The Commission opposed the stay, arguing that the claim had already been processed and paid, and that there was no utility in granting the stay.

The legal issue before the Tribunal was whether there was any purpose or utility in granting a stay of the operation of the amended Scope of Works, given that the claim had already been approved, the rectification work had been completed, and payment had been made. The Tribunal needed to determine if there were any circumstances that would justify a stay at that late stage.

The Tribunal found that there was no utility in granting the stay. The Commission had accepted the owner's claim under the statutory insurance scheme in a timely fashion due to the potential for further deterioration in the dwelling. The extent of Cyclone's liability would be determined during the review of the Scope of Works application. The confusion in Cyclone's application for review and the late notice of the review to the Commission did not justify a stay at that stage. The Tribunal concluded that the application for a stay should be refused.

The Tribunal refused the application for a stay of the operation of the amended Scope of Works, finding that there was no utility in granting such a stay at that late stage.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.