CWO Pty Ltd v Muswellbrook Shire Council

Link copied
Case Copied 10 min read

Land and Environment Court


New South Wales

Medium Neutral Citation: CWO Pty Ltd v Muswellbrook Shire Council [2023] NSWLEC 1049
Hearing dates: 25 January 2023
Date of orders: 06 February 2023
Decision date: 06 February 2023
Jurisdiction:Class 1
Before: Froh R
Decision:

The orders of the Court are:

(1) The Motion is granted.

(2) The Commonwealth of Australia is joined as the Second Respondent to these proceedings.

(3) The Second Respondent is directed to file and serve its Statement of Facts and Contentions in the form annexed at A to the affidavit of Mr Hogan affirmed on 19 January 2023 by 6 February 2023.

(4) The First Respondent is granted leave to file and serve an amended Statement of Facts and Contentions in respect of the contentions it no longer presses by 12PM on 7 February 2023.

(5) The conciliation conference listed at 10:30AM on 8 February 2023 is confirmed.

Catchwords:

Notice of Motion – Application for joinder

Legislation Cited:

Environmental Planning and Assessment Act 1979 s 8.15

Cases Cited:

Ali v Liverpool City Council [2009] NSWLEC 107

Avalon Beach Property Pty Limited v Northern Beaches Council (2017) 227 LGERA 393; [2017 NSWLEC 130

Morrison Design Partnership Pty Limited v North Sydney Council (2007) 159 LGERA 361; [2007] NSWLEC 802

Shoalhaven City Council v Lovell (1996) 136 FLR 58

Category:Procedural rulings
Parties: CWO Pty Ltd (Applicant)
Muswellbrook Shire Council (Respondent)
Commonwealth of Australia (Applicant for joinder)
Representation:

Counsel:
A Stafford (Applicant)
C Koikas (Respondent)
D Robertson (Applicant for joinder)

Solicitors:
Sekel Oshry Lawyers (Applicant)
Moray & Agnew (Newcastle) (Respondent)
Maddocks Lawyers (Applicant for joinder)
File Number(s): 2022/325617
Publication restriction: No

Judgment

  1. By its Notice of Motion filed on 15 December 2022 (the Motion), the Commonwealth of Australia seeks to be joined as a party to Class 1 appeal proceedings between the applicant, CWO Pty Ltd, and the respondent, Muswellbrook City Council (the Council), pursuant to s 8.15(2) of the Environmental Planning and Assessment Act 1979 (NSW) (EPA Act).

  2. Section 8.15(2) of the EPA Act provides as follows:

On an appeal under this Division, the Court may, at any time on the application of a person or of its own motion, order the joinder of a person as a party to the appeal if the Court is of the opinion –

(a) that the person is able to raise an issue that should be considered in relation to the appeal but would not be likely to be sufficiently addressed if the person were not joined as a party, or

(b) that –

(i) it is in the interests of justice, or

(ii) it is in the public interest,

that the person be joined as a party to the appeal.

  1. The Commonwealth submits that it should be joined to the proceedings pursuant to either s 8.15(2)(a) or s 8.15(2)(b) of the EPA Act.

  2. The Commonwealth’s application for joinder to the proceedings is supported by the respondent and is opposed by the applicant.

  3. In support of…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read CWO Pty Ltd v Muswellbrook Shire Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] NSWLEC 1049
Decision Date

CaseChat Overview and Summary

CWO Pty Ltd brought proceedings against Muswellbrook Shire Council, with the Commonwealth of Australia later joined as a second respondent, in relation to a dispute concerning a planning permit. The case was heard in the Supreme Court of New South Wales. The applicant sought various orders, including the joining of the Commonwealth of Australia as a second respondent, the setting of timelines for the filing of statements of facts and contentions, and the confirmation of a conciliation conference.

The primary legal issues before the Court were whether the Commonwealth of Australia should be joined as a second respondent, the setting of appropriate timelines for the filing of statements of facts and contentions, and the confirmation of the conciliation conference. The Court also had to consider the procedural fairness in allowing the Muswellbrook Shire Council to file an amended statement of facts and contentions in respect of contentions it no longer pressed.

The Court held that the Commonwealth of Australia should be joined as the second respondent because it had a direct interest in the proceedings, particularly in relation to the planning permit in question. The Court considered it procedurally fair to grant the Muswellbrook Shire Council leave to file an amended statement of facts and contentions in respect of the contentions it no longer pressed, as it would ensure the proceedings were conducted efficiently and effectively. The Court confirmed the conciliation conference, recognising the importance of expeditious resolution of the dispute. The Court then set the timelines for the filing of statements of facts and contentions to ensure the proceedings were managed in an orderly manner.

The Court granted the orders sought by the applicant, joining the Commonwealth of Australia as the second respondent, setting timelines for the filing of statements of facts and contentions, and confirming the conciliation conference. The Muswellbrook Shire Council was granted leave to file an amended statement of facts and contentions in respect of the contentions it no longer pressed.

Orders

Orders of the court

The orders of the Court are:

(1) The Motion is granted.

(2) The Commonwealth of Australia is joined as the Second Respondent to these proceedings.

(3) The Second Respondent is directed to file and serve its Statement of Facts and Contentions in the form annexed at A to the affidavit of Mr Hogan affirmed on 19 January 2023 by 6 February 2023.

(4) The First Respondent is granted leave to file and serve an amended Statement of Facts and Contentions in respect of the contentions it no longer presses by 12PM on 7 February 2023.

(5) The conciliation conference listed at 10:30AM on 8 February 2023 is confirmed.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established