Creevey v Lyons

Link copied
Case Copied 6 min read
CITATION: Creevey v Lyons [2014] QCAT 41
PARTIES: Matthew Creevey
(Applicant)
v
Damien Lyons
(Respondent)
APPLICATION NUMBER: BDL279-13
MATTER TYPE: Building matters
HEARING DATE: 31 January 2014
HEARD AT: Brisbane
DECISION OF: Member Deane
DELIVERED ON: 3 February 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1.    Damien Lyons is to pay Matthew Creevey the sum of $30 by 4.00pm 28 February 2014.
CATCHWORDS: DOMESTIC BUILDING DISPUTE – contract partly in writing and partly oral – owner builder claims for variations by omissions – whether the reasonable costs of variations had been allowed

APPEARANCES and REPRESENTATION (if any):

APPLICANT: Matthew Creevey, in person
RESPONDENT: Damien Lyons, in person

REASONS FOR DECISION

  1. Mr Creevey, as an owner builder, contracted with Mr Lyons to perform building work on his house. The terms of the contract were partly in writing and partly oral.  Mr Creevey claims that variations by omissions have not been properly reflected in the amount payable and paid and that a refund is due.

  2. It is not disputed that:

    a)Mr Creevey provided to Mr Lyons a scope of work[1].  The scope of work did not provide for painting;

    b)Mr Lyons quoted for work in 2 stages[2].  The quote is dated 30 July 2013 and the quoted amount for stage 1 was originally $8,800 (incl GST).  In view of the dispute which arose in relation to the price to be paid for stage 1 the parties agreed not to continue with stage 2;

    c)Mr Creevey and Mr Lyons discussed that Mr Creevey intended to supply some labour and if he was able to source materials at a cheaper price he would supply those materials and the contract price would be adjusted to reflect these omissions.

    d)No hourly rate to be applied and no mechanism or methodology for valuing Mr Creevey’s contribution in labour or materials was agreed at the time that the contract was entered into.  This is the source of the dispute between the parties.

    e)Mr Creevey supplied a laminated beam and supplied some labour on the first day Mr Lyons was on site.  There is a dispute as to whether the first day on site was 7 August 2013 or earlier.

    f)Mr Lyons offered to reduce the contract price to $7,700 (incl GST) to reflect the supply of the beam and some labour.  This offer was made either on 6 August 2013 or before.[3]  There is a dispute as to whether the offer was made before or after the first day on site.

    g)The parties agreed to vary the scope of work to defer some work to stage 2.  On 6 August 2013 Mr Lyons offered to reduce the contract price further to $6,600 (incl GST).

    h)On 7 August 2013 Mr Creevey paid $6,600.

    [1]Appendix 1 to Application for domestic building disputes.

    [2]Appendix 2 to Application for domestic building disputes.

    [3]Appendix 5 to Application for domestic building disputes.

  3. Mr Creevey gave evidence that in addition to supplying the beam and some labour on the first day he also supplied framing, which…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Creevey v Lyons and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2014] QCAT 41
Decision Date

CaseChat Overview and Summary

Matthew Creevey, the applicant, and Damien Lyons, the respondent, were involved in a domestic building dispute, where the former claimed that variations by omissions were not properly reflected in the amount payable and due to him. The contract between the parties was partly in writing and partly oral, and the scope of work did not include painting. The original quoted amount for stage 1 of the work was $8,800, but the parties agreed not to proceed with stage 2 due to a dispute over the price. The parties also discussed that Creevey would supply some labour and materials, and the contract price would be adjusted accordingly. However, no hourly rate or methodology for valuing Creevey's contributions was agreed upon, leading to the dispute.

The court needed to determine whether the reasonable costs of variations by omissions had been allowed and whether the amount offered by Lyons was sufficient. The applicant bore the burden of proving both entitlement and the amount of the claim. The court noted that there was little evidence provided to support the claim and that Creevey had not provided any evidence of the actual cost of the beam or framing, which he still possessed. Furthermore, there was no evidence of the reasonable costs of the work performed by Creevey and his associate or the materials supplied. Additionally, there was no evidence as to the reasonable value of the deferred work. The court concluded that there was no evidence upon which it could find that the reasonable costs of the variations by omission were more than the amount offered by Lyons.

The court found that the value of the variation by omission in relation to fees for removal of rubbish was $30. The court accepted Lyons' evidence that the cost of the beam was between $450 and $500, and the amount allowed for labour by Lyons was equivalent to at least 10 hours. Even if all the work performed by Creevey and his associate was taken into account, the total man hours were no more than 13. The court found that there was no evidence before it upon which it could rely to find that the reasonable costs of the variations by omission in relation to labour and the supply of the beam were more than the amount offered by Lyons.

In conclusion, the court ordered Damien Lyons to pay Matthew Creevey the sum of $30 by 4.00pm on 28 February 2014. The court found that there was no evidence to support the applicant's claim that the reasonable costs of the variations by omission were more than the amount offered by Lyons. The court accepted Lyons' evidence as to the cost of the beam and the amount allowed for labour, and found that there was no evidence to suggest that the reasonable costs of the variations by omission were more than the amount offered.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established